LaRC Office of Chief Financial Officer Presentation to LaRC Contractor Steering Council Contractor C - PowerPoint PPT Presentation

1 / 8
About This Presentation
Title:

LaRC Office of Chief Financial Officer Presentation to LaRC Contractor Steering Council Contractor C

Description:

Langley Research Center. November 18, 2004. 1. LaRC CSC 11182004.ppt ... Langley Research Center. November 18, 2004. 4. LaRC CSC 11182004.ppt. Cost in Excess of ... – PowerPoint PPT presentation

Number of Views:29
Avg rating:3.0/5.0
Slides: 9
Provided by: procureme2
Category:

less

Transcript and Presenter's Notes

Title: LaRC Office of Chief Financial Officer Presentation to LaRC Contractor Steering Council Contractor C


1
LaRC Office of Chief Financial Officer
Presentation to LaRC Contractor Steering
CouncilContractor Cost Reporting and Cost in
Excess of Obligations
November 18, 2004 Lisa M. Oliver, Chief
Accountant
2
Agenda
  • Importance of timely and accurate contractor cost
    reporting
  • Cost in excess of obligations
  • Background
  • Definition
  • Current initiatives
  • Questions

3
Contractor Cost Reporting Why is it Important?
  • Timeliness
  • Facilitates our ability to report actual and
    estimated costs so program/project decisions can
    be made with the latest, most current information
  • Out of LaRCs 73 active contracts subject to
    contractor cost reporting, 53 arrive after the
    contractual due date
  • Accuracy
  • Facilitates decision making based on reliable
    information
  • Out of LaRCs 73 active contracts subject to
    contractor cost reporting, 79 report variances
    between estimated and actual costs in excess of
    10

4
Cost in Excess of Obligations
  • Background
  • Cost in excess of obligations (CIEO) has existed
    in NASA for many years
  • Since NASAs implementation of Core Financial
    (SAP R/3), CIEO has been recorded for internal
    reporting purposes only it has not been reported
    in the general ledger (this is a system design
    limitation within SAP)
  • Recent audit findings have highlighted an area of
    concern due to the materiality of CIEO and
    unrecorded, unfunded liabilities
  • Prior to closing FY 2004, LaRC had over 2M in
    CIEO, out of approximately 160M throughout NASA
  • Complications
  • Continuing resolutions
  • Pace and prioritization of funds distribution and
    funding actions
  • Understanding importance of contract funds
    management

5
Cost in Excess of Obligations (cont.)
  • Definition NASA defines cost in excess of
    obligations when the cumulative cost at the
    appropriate reporting level (task or contract)
    exceeds the amount funded at the same level
  • Cumulative cost is calculated from actual costs
    for the reporting period plus the estimate for
    the current month
  • For example Oct. 04 actual costs 1,000
  • Nov. 04 est. costs 100
  • Total cum. Costs 1,100
  • Total funded 1,050
  • CIEO 50
  • NOTE Contractor cost reports provide a estimates
    for the 2 months following the month being
    reported.

6
Cost in Excess of Obligations (cont.)
  • Current initiatives
  • Agency has mandated that NASA will not record
    CIEO, even for internal reporting purposes
  • During FY 2004 closeout activities, Agency OCFO
    required all centers to actually record the
    obligation and cost for any true CIEO
    situations
  • LaRC did not record any obligation or cost for
    our CIEO we worked with the Contracting
    Officers (CO) and Contracting Officers
    Technical Representatives (COTR) to resolve CIEO
    instances
  • Obtained additional funding from appropriate
    sources
  • Invoked funding limitation clauses on contracts
    to reduce cost to funding levels
  • Notified contractors that they would be
    responsible for absorbing any additional costs
    they incur above the funding limits
  • OCFO and Office of Procurement are jointly
    working short and long-term solutions
  • Take a more proactive approach to funds
    management of our contracts
  • Education for COs, COTRs, Contractors and
    others as appropriate

7
Summary
  • Submission of contractor cost reports timely and
    accurately will enable more effective and
    efficient management of NASAs programs
  • Cost in excess of obligations will become a
    thing of the past as NASA performs more
    effective contract funds management
  • Your assistance is needed if these objectives are
    to be realized!

8
Questions
Write a Comment
User Comments (0)
About PowerShow.com