Project Board December Update for Worcs Community - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Project Board December Update for Worcs Community

Description:

Lorraine Haynes Podiatry. Julie Gittoes. Trudi Wylde SCC. Wyre F PCT. 5 days ... Simon Gartland Podiatry. Elaine Jones District Nursing. R&B PCT. 7 days ... – PowerPoint PPT presentation

Number of Views:59
Avg rating:3.0/5.0
Slides: 19
Provided by: csc294
Category:

less

Transcript and Presenter's Notes

Title: Project Board December Update for Worcs Community


1
Project Board December Update for Worcs Community
MH PAS Deployment Project
  • Ian McGregor Steve Wormald, Chris Ashman

2
Agenda
  • Review Minutes from previous meeting
  • Current Status
  • Project Plan
  • Proposed amendments to approach for approval
  • Risks Issues
  • Registration and Authentication of Smart Cards
  • NCRS User Registration Procedure for approval
  • Communications
  • Amended comms plan for approval
  • NHS Finance Report
  • AOB
  • Conclusion

3
Current Status Cont/
  • Planned Activities for Period Date 01/11/04 to
    30/11/04
  • SDRC2 Checklist
  • Outstanding items to be completed
  • SDRC1 Checklist outstanding items covered off in
    SDRC2 Checklist
  • Business Change
  • Local Configuration review with Community
    Managers
  • Policies and Procedures drafted
  • Requirements for Organisational Change
  • High Level Target Benefits identified
  • Change Implementation Plans updated
  • Re-focus Business Change team structure within
    each of the PCTs and MH
  • Communications
  • Review Communication Strategy and Plan. Cascade
    messages to Users on the Project Status. Team
    briefs etc.
  • Briefing sessions for Senior Management MH, Exec
    Management team SWorcs and further sessions
    planned.

4
Current Status Cont/
  • Planned Activities for Period Date 01/11/04 to
    30/11/04
  • Environments
  • Standing Up of further Environments to support
    Development, Data Migration incl Infrastructure
    to test data (MPI and Patient Activity data)
  • Progress Local Configuration
  • Data Migration
  • Complete loading of the Local Reference Data
  • Migrate LRD to End User Training Environment
  • Commence Data Migration testing
  • Provide a sample subset of files for reporting
  • Produce System Migration Strategy
  • Training
  • Recommence Train the Trainer and re-deliver
    outstanding elements incl
  • Day Care Module
  • Kick off Localisation of Course Content
  • Review Training Strategy and Plan

5
Current Status Cont/
  • Planned Activities for Period Date 01/11/04 to
    30/11/04
  • Infrastructure
  • Deployment of New PCs and Upgrading
  • Discussions with BT on N3 and connecting to the
    Coin
  • Site Audits and set-up of Infrastructure (incl
    Equip) for Registration and Authentication
  • Security (Smart Card)
  • Sign-off of Policy and Procedures
  • Identify Users and Sponsors for Registration,
  • Deliver Registration Schedule

6
Current Status Cont/
  • Achievements for this Period Date 01/11/04 to
    30/11/04
  • SDRC2 Checklist
  • Outstanding items progressed
  • SDRC2.09 System Migration Plan
  • SDRC2.10 Project team resources identified and
    deployed (carried forward from SDRC1)
    Community/Change Manager not assigned across all
    PCTs.
  • SDRC2.15 Infrastructure delivery plan exists
    (carried forward from SDRC1) Incomplete due to BT
    N3 agreement of the Architecture design and roll
    out schedule.
  • Business Change
  • Local Configuration review with Community
    Managers in process
  • Policies - final draft presented for Approval.
  • Procedures outstanding
  • Requirements for Organisational Change not
    progressed
  • High Level Target Benefits identified not
    progressed
  • Change Implementation Plans under review
  • Re-focused Business Change team structure within
    each of the PCTs and MH

7
Current Status Cont/
  • Achievements for this Period Date 01/11/04 to
    30/11/04
  • Communications
  • Reviewed Communication Strategy and Plan. Cascade
    messages to Users on the Project Status. Team
    briefs, Newsflash, etc.
  • Briefing sessions for Senior Management across
    PCTs and MH ongoing. Well received.
  • Environments
  • Environments available despite challenges
  • End User Training Environment currently being
    prepared
  • FTP process in place to support Data Migration
  • Data Migration
  • Data 93.8 with NHS Numbers
  • Loading of Local Reference Data almost ready to
    perform a Database copy to the End User Training
    Environment
  • 1st pass of Sample MPI performed (5,000 Live
    records) - errors as expected
  • Provided a sample subset of CSV files for
    reporting
  • System Migration Strategy not progressed -
    dependent on Migration tests .

8
Current Status Cont/
  • Achievements this Period Date 01/11/04 to
    30/11/04
  • Infrastructure
  • Deployment of new PCs Build has started. Not
    complete due to notification from BT of change to
    Single Sign On software (Could alter again
    within 90 days). PC Deployment start date
    04/01/05 could be at risk.
  • Discussions with BT regarding N3 integration with
    Worcs Compromise agreement in progress
  • Security Registration Authentication (Smart
    Card)
  • Policy and Procedures (Interim) ready for
    sign-off
  • Identified Users and Sponsors for Registration
    training
  • Approx 1,370 (MHPT list still incomplete)
  • Registration Agents 2/6 identified. Recruitment
    of remainder via Staff Bank in progress. RA
    Training booked for 16/17 Dec.
  • Sites identified Currently being validated for
    suitability

9
Current Status Cont/
  • Planned Activities for next Period Date 01/12/04
    to 30/12/04
  • SDRC2 Checklist
  • Outstanding items to be completed
  • Business Change
  • Progress Local Configuration with involvement
    of Community Managers
  • Sign-off Policies for PCTs and MH
  • Progress procedures for PCTs and MH
  • Identify Initial Go Live Groups
  • Communications
  • Review Communication Strategy and Plan. Cascade
    messages to Users on the Project Status. Team
    briefs, Newsflash, etc.
  • Further cascading of Communications Briefings to
    Management at RB with further sessions being
    planned for Jan05 to SWorcs.

10
Current Status Cont/
  • Planned Activities for next Period Date 01/12/04
    to 31/12/04
  • Environments
  • Preparation of End User Training Environment
    (Master)
  • Data Migration
  • Complete loading of the Local Reference Data
  • Migrate LRD to Environments Data Migration and
    End User Training
  • Further testing of Full MPI data and sample of
    activity data
  • Training
  • Re-deliver Day Care training
  • Progress localisation of course content
  • Preparation of EUT (Master)
  • Update Training Strategy and Plan
  • Train Registration Agents
  • Present on RBAC to facilitate role mapping

11
Current Status Cont/
  • Planned Activities for next Period Date 01/12/04
    to 31/12/04
  • Infrastructure
  • Commence deployment of New PCs and Upgrading
  • Acceptance of compromise agreement with BT
  • Security Registration Authentication (Smart
    Card)
  • Sign-off of Policy and Procedures
  • Finalise list of Users and Sponsors for
    Registration,
  • Deliver Registration Schedule and notify Users of
    dates and venues

12
Project Plan
  • Formal submission of Change Note to Project Board
    for Sign-off
  • Change of Approach
  • Run through approach slides
  • Re-Base line of dates to reflect current state
  • Project Status
  • Plan update

13
Top Issues
14
Top Issues Cont/
15
Top Risks Cont/
16
Top Risks Cont/
17
Conclusion
  • Agreement to continue to proceed
  • Agree Actions from Board meeting
  • Next Board Meeting Thursday the 6th of January
    3pm to 5pm POWCH Conference Room Bromsgrove

18
Resourcing
  • Current commitment of NHS Resources

until Christmas
until 07/01/05
leaving?