2006 Building Code Flashing Changes - PowerPoint PPT Presentation

1 / 28
About This Presentation
Title:

2006 Building Code Flashing Changes

Description:

2006 Building Code Flashing Changes & Challenges. Builder Breakfast and Luncheon Series ... 9.27.3.8 Flashing Installation ... for Flashing. 9.27.3 & 9.3.3.2 ... – PowerPoint PPT presentation

Number of Views:193
Avg rating:3.0/5.0
Slides: 29
Provided by: SCAA
Category:

less

Transcript and Presenter's Notes

Title: 2006 Building Code Flashing Changes


1
2006 Building Code Flashing Changes Challenges
  • Builder Breakfast and Luncheon Series
  • Presented by

2
2006 Building Code Flashing Changes Challenges
  • Speakers
  • Mick Ryan, President, Siding Contractors
    Association of Alberta (SCAA)
  • Michael Andrade, Gienow Windows Doors/AHITC
    Subcommittee

3
Code Areas Affected by Flashing Changes
  • 9.3.3.2 9.27.3 Materials for flashing
  • 9.26.4.1 Decks as Structures
  • 9.27.3.8 Flashing Installation
  • These changes apply to all types of exterior
    cladding materials (siding, stucco, masonry,
    etc.)

4
Allowable Materials for Flashing9.27.3 9.3.3.2
  • Lead, galvanized steel, copper, zinc, aluminum
  • No change in thicknesses or materials allowed
  • The Standards for flashing galvanizing have
    changed

5
Flashing at Decks 9.26.4.1
  • Decks balconies that do not permit the free
    drainage of water through the deck must be
    treated as a roof.
  • Unless the surface slopes to the outside of the
    building so water can freely drain over the edge.
  • Flashings should installed
  • between walls and decks
  • at guards in contact with the decks

6
Section 9.27.3.8 Flashing Installation
  • Flashing must be installed at
  • every horizontal change in cladding element
  • every horizontal offset in the cladding
  • every horizontal line where the cladding
    substrate changes, and
  • top and bottom of all penetrations

7
Section 9.27.3.8 Flashing Can Be Omitted Where.
  • the upper cladding elements overlap the lower
    cladding elements by at least 25mm
  • Where drained vented air spaces are used
  • Horizontal joints in stucco with expansion strips

8
Section 9.27.3.8 Flashing Specifications for
Wall Openings
  • Extend at least 50mm upward (1997)
  • Have a minimum 6 positive slope (2006)
  • Have end-dams not less than 25mm high
  • Lap a minimum of 10mm vertically over the
    building element below (2006)
  • Terminate with a drip that extends at least 5mm
    out from the face of the building element (2006)

9
(No Transcript)
10
Installation of Perimeter Flashing
Siding can be clipped over the Perimeter Flashing
or set on top of the flashing in a J Trim
11
Penetration Options
  • Flash each penetration individually
  • Mount all penetrations on battens to allow the
    flashing to be placed on the battens rather than
    each penetration individually.
  • Use self draining/flashed covers that meet code
    requirements

12
Flashing Mechanical Penetrations
2006 Code
1997 Code
13
Penetrations
  • All penetrations must be flashed, top and bottom

14
(No Transcript)
15
(No Transcript)
16
  • Weather Resistant Barrier to overlap 9 on
    vertical joints
  • Weather Resistant Barrier to overlap 4 on
    horizontal shingle laps
  • Caulk behind batten J Trim on verticals
  • Caulk behind reverse flashing on horizontals.

17
(No Transcript)
18
Flashing at bottom of Batten
25mm
19
Batten Flashing Detail Above Window
25mm
25mm Up Dam
20
(No Transcript)
21
Flashing at the Window Sill
  • The 2006 ABC requires flashing at window sills
  • 2 acceptable solutions are recognized
  • Metal sill flashing
  • A self-flashing sill

22
Options for Flashing at Window Sills
  • Acceptable Solution 1
  • Metal Sill Flashing

23
Flashing at the Window SillAcceptable Solution 2
6 Slope Drip 5 mm beyond cladding
Self-flashing sill
24
Drip Accessory Potential Acceptable Solution
Vinyl Window
Metal Clad Window
25
In Summary
  • The 2006 flashing requirements
  • have created additional complexity
  • Number of locations requiring flashings has
    increased
  • Configuration of the flashing
  • Up dams
  • Leg length may vary depending on application
  • Will result in additional cost due to
  • increased install time required
  • increased amount of flashing materials

26
In Summary
  • Talk to your contractors to
  • Ensure that the flashing materials and
    configurations used meet code requirements
  • Galvanization, leg length, 6 slope
  • Ensure deck interfaces are flashed
  • Review designs and add flashing transitions
  • Discuss with your contractors

27
Additional Resources and Information
  • Questions on acceptable solutions
  • Local Code Authority
  • Municipal Affairs help line (866-421-6929)
  • Flashing Details
  • Siding Contractors Association of Alberta
    (403-291-9707)
  • Stucco Toolkit CHBA AB or ANHWP
    (www.chbaalberta.com)
  • AWCA Stucco Resource Guide (403-250-7045)
  • CMHC Flashing Guide (www.cmhc-schl.gc.ca)

28
2006 Building Code Flashing Changes Challenges
  • Questions?
  • Thank you!
Write a Comment
User Comments (0)
About PowerShow.com