Progress and Performance Measurement and Evaluation - PowerPoint PPT Presentation

1 / 39
About This Presentation
Title:

Progress and Performance Measurement and Evaluation

Description:

Current status of project (schedule and cost) ... Performance Indexes provide context for how grossly we misestimated project costs and times. ... – PowerPoint PPT presentation

Number of Views:1626
Avg rating:3.0/5.0
Slides: 40
Provided by: charli148
Category:

less

Transcript and Presenter's Notes

Title: Progress and Performance Measurement and Evaluation


1
Progress and Performance Measurementand
Evaluation
  • Chapter 13

2
(No Transcript)
3
Project Monitoring System for Control
  • A Project Monitoring System needs to address 4
    questions
  • What data are collected? Typically
  • Current status of project (schedule and cost)
  • Actual completion times (compared to planned
    durations)
  • Estimates of
  • Remaining cost to compete project
  • Date that project will be complete
  • Potential problems to be addressed now
  • Out-of-control activities requiring intervention
  • Cost and/or schedule overruns and the reasons for
    them
  • Forecast of overruns at time of project completion

4
Project Monitoring System
  • 2. Collecting data (and analysis)
  • Who will collect project data?
  • How will data be collected?
  • When will the data be collected?
  • 3. Who will compile and analyze the data?
  • 4. With respect to reports and reporting .
  • Who will receive the reports?
  • How will the reports be transmitted?
  • When will the reports be distributed?

5
Project Progress Report Format
  • One typical format (may be others)
  • Progress Since Last Report
  • Current Status of Project
  • Schedule
  • Cost
  • Scope
  • Problems and Issues Since Last Report
  • Actions and resolution of earlier problems
  • New variances and problems identified
  • Summarize Cumulative Trends
  • Any Corrective Action Planned?
  • Format your report appropriately for the audience

6
The Project Control Process
  • Control
  • The process of comparing actual performance
    against plan to identify deviations, evaluate
    courses of action, and take appropriate
    corrective action
  • Project Control Steps
  • Setting a baseline plan
  • Measuring progress and performance
  • Comparing plan against actual
  • Taking actions

7
Monitoring Time Performance
  • Tools Used to Catch Negative Variances from Plan
    and Communicate Project Schedule Status
  • 1. Tracking and baseline Gantt charts
  • Show expected, actual, and trend data for event
    duration performance
  • MS Project allows tracking, but in actuality very
    few PMs seem to utilize this functionality.
  • 2. Control charts
  • Plot the difference in scheduled time on the
    critical path with the actual point on the
    critical path

8
Milestones! Milestones! Milestones!
  • Used correctly, milestones help keep a project on
    track (or let you know early if you are lost)
  • In Planning Phase, construct project to have
    Milestones that are
  • Spaced throughout the project
  • Tied to concrete deliverables (e.g. documents) or
    otherwise non-fudge-able events, like code
    handoffs.
  • Paired milestones for client-facing projects
    (submit, then approval)
  • For large projects can report 2 levels of
    milestones
  • one for the executives
  • one for the PMs and functional managers

9
Project Control, Reporting and Ethics
  • Projects often fail because
  • They get behind schedule, so
  • Someone covers the delay, so
  • Unpleasant surprise at the end
  • Example What is the typical process path in
    developing software?
  • Which process is most likely to get shortened?
  • Structure the project plan so that delays will be
    apparent early and cannot be hidden
  • Other ideas?

10
Earned Value Cost/Schedule System
  • An integrated project management system based on
    the earned value concept that uses a time-phased
    budget baseline to compare actual and planned
    schedule and costs
  • Pioneered by the government so that means.

11
Glossary of Terms
  • First, look at PV (Planned Value)
  • The time-phased baseline of the value of the work
    scheduled. An approved cost estimate of the
    resources scheduled in a time-phased cumulative
    baseline (was BCWSbudgeted cost of the work
    scheduled).
  • Then, as project begins, estimate... EV
  • The percent complete times its original budget.
    The percent of the original budget that has been
    earned by actual work completed. Fun Fact The
    older acronym for this value was BCWPbudgeted
    cost of the work performed.
  • And also record AC
  • The actual cost of the work completed. The sum of
    the costs incurred in accomplishing work. (was
    ACWPactual cost of the work performed).
  • This will allow you to calculate CV
  • Cost variance is the difference between the
    earned value and the actual costs for the work
    completed to date where CVEV-AC.

12
Glossary of Terms- Part II
  • And also allow you to calculate SV
  • Schedule variance (SV) is the difference between
    the earned value and the baseline line to date
    where SVEV-PV.
  • From PV we can initially get BAC
  • Budgeted cost at completion. The total budgeted
    cost of the baseline or project cost accounts.
  • But must wait for project to start to get a
    forecast of EAC
  • Estimated costs at completion . Includes costs
    to-date plus any revised estimated costs for the
    work remaining.
  • More on this later on- but 2 different ways to
    get
  • EACre is determined by experts.
  • EACf is derived from a formula using actual and
    earned value costs
  • and also forecast ETC
  • Estimate to complete.
  • Leading to VAC
  • Cost variance at completion (BAC-EAC), where.
  • VAC indicates expected actual over-or under-run
    cost at completion

13
Developing an Integrated Cost/Schedule System
  • Define the work using a WBS.
  • Scope
  • Work packages
  • Deliverables
  • Organization units
  • Resources
  • Budgets
  • Develop work resource schedules
  • Schedule resources to activities
  • Time-phase work packages into a network
  • Develop a time-phased budget using work packages
    included in an activity. Accumulate budgets (PV).
  • At the work package level, collect the actual
    costs for the work performed (AC).
  • Multiply percent complete times original budget
    (EV).
  • Compute the schedule variance (EV-PV) and the
    cost variance (EV-AC).

14
Project Management System Overview
15
Development of Project Baselines
  • Purposes of a Baseline (PV) An anchor point for
    measuring performance
  • A planned cost and expected schedule against
    which actual cost and schedule are measured
  • A basis for cash flows and awarding progress
    payments
  • A summation of time-phased budgets (cost accounts
    as summed work packages) along a project timeline
  • What Costs Are Included in Baselines?
  • Labor
  • Equipment
  • Materials
  • Project direct overhead costs (DOC)

16
Baseline Data Relationships
17
Development of Project Baselines (contd)
  • Rules for Placing Costs in Baselines
  • Costs are placed exactly as they are expected to
    be earned in order to track them to their point
    of origin.
  • The most common, the easiest, and the one we will
    use is the Percent Complete Rule
  • Costs are periodicallyassigned to a baseline as
    units of work are completed over the duration
    of a work package.

18
Methods of Variance Analysis
  • The heart of it is Comparing Earned Value
  • With the expected schedule value and.
  • With the actual costs
  • Assessing Status of a Project
  • Required data elements
  • Data Budgeted cost of the work scheduled (PV)
  • Budgeted cost of the work completed (EV)
  • Actual cost of the work completed (AC)
  • Calculate schedule and cost variances
  • A positive variance in either EV or AC indicates
    a desirable condition, while a negative variance
    suggests problems or changes that have taken
    place.

19
Methods of Variance Analysis
  • Cost Variance (CV)
  • Indicates if the work accomplished using labor
    and materials costs more or less than was planned
    at any point in the project
  • Schedule Variance (SV)
  • Presents an overall assessment in dollar terms of
    the progress of all work packages in the project
    scheduled to date

20
Assumptions for EV Model and Reporting
  • If an activity costs 1000 to perform, it has a
    total value of 1000.
  • Each cost account has only one work package, and
    each cost account will be represented as an
    activity on the network.
  • The project network early start times will serve
    as the basis for assigning the baseline values.
  • After all adjustments have been made for
    scheduling to resource and budget constraints, of
    course.
  • Baseline value are assigned linearly, unless
    stated differently.
  • For those concerned that EV is measure of
    schedule, not cost variance, this difference is
    less important the closer we get to linear
    valuation.
  • From the moment work on an activity begins, some
    actual costs will be incurred each period until
    the activity is completed.
  • We do not revisit finished tasks or ever go
    backwards

21
Additional Earned-Value Rules
  • Rules Applied to Short-Duration Activities and/or
    Small-Cost Activities, either
  • 0/100 percent rule
  • Assumes 100 of budget credit is earned at once
    and only when the work is completed
  • or.
  • 50/50 rule
  • Allows for 50 of the value of the work package
    budget to be earned when it is started and 50 to
    be earned when the package is completed
  • For this class, we will always assume activities
    are long enough to justify use of the regular
    complete rule

22
Cost/Schedule Graph A Typical Example
23
Earned Value Review Exercise
1
2
3
4
24
Work Breakdown Structure and Cost Accounts A
Simple Example- A New Digital Camera
Real projects tend to have Different
organizations involved throughout, Such as QA
for each functional subsystem
25
Digital Camera Prototype Project Baseline Gantt
Chart
26
Digital Camera Prototype Project Baseline
27
Digital Camera Prototype Status Reports Periods
13
We will walk through the same exercise using excel
28
Digital Camera Prototype Summary GraphCV -70,
SV -40
29
Digital Camera Project Tracking Gantt Chart
Showing StatusThrough Period 7
The revisions make some assumptions.
30
Digital Camera Project Rollup at End Period 7
(000)
31
Indices to Monitor Progress
  • Performance Indexes provide context for how
    grossly we misestimated project costs and times.
  • Cost Performance Index measures the cost
    efficiency of work accomplished to date
  • CPI EV/AC
  • Scheduling Performance Index measures scheduling
    efficiency
  • SPI EV/PV
  • Percent Complete Indexes Indicates how much of
    the work accomplished represents of the total
    budgeted (BAC) and actual (AC) dollars to date
  • PCIB EV/BAC Percent of work done
  • PCIC AC/EAC Percent of cost incurred or how
    much of the money that will be spent has been
    spent
  • Can anyone see a problem with the definition of
    PCIC?

32
Indexes Periods 17
Before tackling EAC.
FIGURE 13.13
33
Forecasting Final Project Cost
  • So, how do we predict what the final cost will
    be, based on experiences so far?
  • Baseline estimate was.
  • The text provides two different methods used to
    revise estimates of future project costs
  • EACre (also called EACe)
  • Allows experts in the field to change original
    baseline durations and costs because new
    information tells them the original estimates are
    not accurate
  • EACf
  • Uses actual costs-to-date plus an efficiency
    index to PROject final costs in large projects
    where the original budget is unreliable

34
Estimated (Cost) to Complete- ETCTrend or an
Anomaly?
  • Before we break out the formulae, we need to ask
    ourselves if what has happened to date can be
    expected to continue or if we feel it is
    atypical.
  • If atypical (and if we think our original
    estimates are still sound), then
  • ETC BAC-EV
  • Or If we think we can the rest of the tasks will
    require the same (typically extra) costs, then we
    need to adjust our estimates.
  • ETC (BAC-EV)/CPI

35
Forecasting Model EACf
Here we are assuming that trends continue. Thus
the equations for this forecasting model
36
To Complete Performance Index (TCPI)
  • BAC - EV
  • TCPI BAC AC
  • TCPI the amount of value each remaining
    dollar in the budget would have to theoretically
    earn to stay within budget

37
Group Exercise
  • (Modified from 5 in the book) The following
    information is provided about companys a
    nanotechnology project.
  • Provide a Gantt view of the project, including a
    period by period view of planned and cumulative
    PV? What other information and metrics can we
    compute at this point before we have actual
    progress reports?

38
Group Exercise Continued
  • Now you are given the following information (
    complete and AC) for each of the following 6
    periods (only new info for each period is shown).
    Show how you would compute EV, PV, SV and CV and
    briefly summarize how the project is going.

39
Group Exercise Continued More!
  • Next graph EV, AC and PV for each period, plus
    create a separate index graph for CPI, SPI and
    PCIB. What would you say about these graphs to
    your boss?
  • What is your assessment of your project at the
    end of period 6, including any recommendations?
    Assume that you have the additional information
    that project that this company is fairly well
    funded and the deliverable from project is viewed
    as critical is being awaited impatiently by the
    firms investors. Performance reviews are
    coming up, so youd like to provide as positive a
    summary as possible, while still being honest.
Write a Comment
User Comments (0)
About PowerShow.com