Title: PROVINCIAL WATER SUPPLY, SEWERAGE AND SANITATION SECTOR PLAN PW4SP PROVINCE OF BOHOL
1PROVINCIAL WATER SUPPLY, SEWERAGE AND SANITATION
SECTOR PLAN (PW4SP)PROVINCE OF BOHOL
2 Introduction
- PW4SP for the Province of Bohol was prepared by
the PSPT organized by the Provincial Govt. with
members coming from PPDO, PEO, PHO, DILG, PGSO
and BEMO - PSPT was assisted by DILG/WSSPMO together with
GTZ Study Team through Technical Grant Assistance
from German Development Cooperation (GTZ) - Preparation of the sector plan was carried-out by
the team for a period of 4 months (mid August-1st
week of December) with active participation of
other line agencies and the 48 municipalities
3What Is To Be Done?
- Team Appreciation of Questionnaire
- Diverse knowledge
- Different field of experience
- EFFECT
- Individually conditioned to addressed their
respective field of specialization - Data gaps identified
4Who Will Do What?
- Assess existing data
- Identify Major Activities
- Work plan
5PW4SP Work plan for Data CollectionProvince of
Bohol
6How It Was Done And When?
- Focus on Gap
- Identify Major Concerns and Hindrances
- Mobility
- Communication
- Manpower
- Support from GO, SP, VGO
- Office concern vs. Project priorities
- Time management
- Support of LGU
- Municipal Level Priorities vs. Project priority
requirements
7Mobility
- Conflict of Schedule
- Utilization of owned vehicles
- Coordinate with other Sector travel/vehicle
utilization schedules. - Active support of Chief of Office.
8Communication
- Access to Medium communication
- BLECS
- Attendance to regular meeting of SIs, MPDCs,
MES. - Direct Linkages Mun. Water Task Force, Water
providers. - Direct Linkages to other data provider. eg. Mun.
Accountant. - Initiatives of our support staff eg. Driver
- Planned Itinerary of Travel
- Maximize presence of DILG personnel
- Maximize vehicle
9Manpower
- All out support of PMU WSSPMO
- Secondment of Personnel
- Hiring of Casuals
10Then What?
- Conceptualization of a study for a Bohol
Inter-Municipality Water Connection Plan (Coastal
Mun.) - Tapping the following
- Major Rivers Inabanga River, Ipil River, Loboc
River - Major Spring Lila, Valencia and Garcia Hernandez
11DATA ASSESSMENT ON EXISTING SECTOR CONDITIONS
- Water Supply Service Coverage
- Access to Safe Water Sources/Facilities
- Provincial Total - 59 ( 2003
population) - Rural - 59
- Urban - 60
- Without Access/Underserved
- Provincial - 41 or equivalent to 507,610
pop - Sanitation Facilities and Service Coverage
- Household Toilets - 79
- School Toilets - 80
- Public - 82
- Private - 62
- Public Toilets (Parks, Markets - 98
-
-
12WATER SOURCE AVAILABILITY
- Existing Groundwater Sources in the Province
13PROVINCIAL SECTOR TARGETS
14CONDITIONS/ASSUMPTIONS FOR DEVELOPMENT OF THE PLAN
- Number of Households to be served a Level 1
Facility ( 1 Level 1 15 HH) - Level 2 ( 1 Tap Stand 5 to 6 HH)
- Level 3 ( individual connection 1 HH)
- Safe and Unsafe percentages of Level 1 Facilities
( 90) - Standard number of students to be served by a
unit of sanitary toilets ( 40 students 1
sanitary toilet) - Standard number of toilets for a public utility
- Provincial sector targets by sub-sectors (Phase
1) - Water Supply - (Urban 89 Rural 90)
- Sanitation - (Urban 94 Rural 94)
- School - 90
- Public - 100
- Allocation factor/Percentages of IRA ( 20 of the
20 Devt Fund or 4 of the total IRA - For urban water supply (Long-Term), merging of
municipalities (clustering) towards an Integrated
Water Supply System
15Financial shortfall and implementation
arrangements
16Financial shortfall and implementation
arrangements
17Financial shortfall and implementation
arrangements
18Financial shortfall and implementation
arrangements
19INSTITUTIONAL ARRANGEMENTS (LGU Capability)
- Provincial Offices involved in Water and
Sanitation (WATSAN) activities - Provl. Planning and Development Office (PPDO)
- Provl. Engineers Office (PEO)
- Provl. Health Office (PHO)
- Provl. Treasurers Office (PTO)
- Provl. General Services Office (PGSO)
- Provl. Budget Office (PBO)
- Provl. Accountants Office (PAO)
- Provl. Environment Management Office (BEMO)
20INSTITUTIONAL ARRANGEMENTS (LGU Capability)
- PROJECT MANAGEMENT ISSUES AND CONCERNS
- Project Identification and Prioritization
- Preparation of feasibility Studies and detailed
engineering design - Procurement of materials and equipment, and
facility construction and rehabilitation - Operation and Maintenance ( O M ) of facilities
- Water Quality Monitoring
- Private sector capability for the sector project
- Skills and training of LGUs and the
community-based water service providers - Data Base Management
- Financial Aspects
- Cost Recovery Practices by LGUs and Users
21COMMUNITY PARTICIPATION AND GENDER ASPECT
- Demand-responsive community participatory
approaches - - Information Sharing
- - Consultation
- - Decision-making
- - Initiating Action
- Gender-Responsive Community Participatory
Approach - - to be applied from project conceptualization,
planning, implementation, monitoring and
evaluation of the Project
22Gikan sa Bohol
- DAGHANG SALAMAT UG MAAYONG PASKO KANINYONG
TANAN!!!!!