Title: QUARTERLY IN POWER POINT


1
MONTHLY STATUS REVIEW EOS ICE, CLOUD LAND
ELEVATION SATELLITE (ICESat) PROJECT Code 425
Project Scientist
Dr. J. Zwally / 971 Project Manager
Joseph Dezio Deputy Project
Manager Gregory Smith DPM /
Resources Linda
Greenslade Instrument Development
Dr. J. Abshire / 924 Ground System
Development ESDIS / 423 Spacecraft
Contractor Ball
October 15, 2001
2
ICESat PROJECT SUMMARY STATUS AS OF 9/30/01
Major Interfaces
Resources
Prime
JUL AUG SEP
JUL AUG SEP
Spacecraft Bus
JUL AUG SEP
R G G G
Y G G G
G G G G
G G G G
Launch Vehicle
G G G G G G
G G G G G G
Y G G G
R G G G
G G G G G G
Program Management
Launch Site (VAFB)
Subcontracts
Ground SYS / OPS (EOS)
Systems Engineering
JPL GPS Receivers
Subsystems
Spacecraft IT
Observatory IT
Science / Operations
Instruments
Business
JUL AUG SEP
JUL AUG SEP
JUL AUG SEP
GLAS
Y
Y
Y
R G G G
R G G G
G G G G
RD Budget
G
GLAS
G
G
Procurement
Workforce
Travel
Summary Assessment
LEGEND
Technical Cost Schedule
Overall
Good Shape
G
R
Y
R
R
Minor Problem
Y
Major Problem
R
3
SCHEDULE ICESat PROJECT

STATUS
AS OF 9/30/01
DATE ESTAB COMPL 10 / 15 11
/ 1 10 / 15 11 / 30
PROBLEM / ISSUES PROGRAMMATIC
IMPACT ACTION
R
  • Codes 400 and 500 are discussing ways to contain
    this problem
  • Expedite thermal performance evaluation of
    optical system
  • Latest GLAS completion schedule causes negative
    slack to the June 1, 2002 LRD.
  • GLAS component rework cycles continue to erode
    GLAS integration and test schedule longer GLAS
    integration effort needed
  • Launch manifest uncertainty
  • CURRENT STATUS
  • Latest GLAS delivery schedule slips delivery date
    to January 28. Discussions with Code 500
    management are underway to apply specific
    solutions to observed problems.
  • GLAS instrument assembly complete for first
    baseline CPT scheduled for late October.
  • Project and AETD management are actively pursuing
    options for earliest GLAS optical stability
    evaluation in thermal vacuum.

4
GLAS IT PROBLEMS IN
WORK OPTICAL / MECHANICAL ICESat PROJECT


STATUS AS OF 9/30/01
DATE ESTAB COMPL 4 / 01
11 / 30 4 / 01 11 / 01
(CLOSED) 11 / 30
PROBLEM/ISSUES PROGRAMMATIC
IMPACT ACTION
Y
  • Rework Required for
  • Optical Stability of
  • Lateral Transfer
  • Retroreflector
  • - Laser Select Mechanisms

Schedule and System Level Technical Risk may
impact the proposed June 02 LRD
Assess, Analyze, Rework, Retest and Expedite
Affected Components LTR Cover Mounting reworked
and retested Evaluate test results from T / V
to confirm performance
  • CURRENT STATUS
  • LSM-1 INVAR counterweights installed and tested.
    Delivered to IT.
  • LSM-1 stability performance good LSM-2 marginal,
    but acceptable for system evaluation.
  • Proceeding with instrument integration and test
    to characterize instrument behavior as entire
    system.

5
COST ICESat PROJECT

STATUS AS
OF 9/30/01
DATE ESTAB COMPL 7/ 01 11 /
01
PROBLEM / ISSUES PROGRAMMATIC
IMPACT ACTION
R
  • Request additional overguide funding after new
    LRD is determined.
  • Cannot meet proposed 6 / 1 / 02 LRD without
    additional funding.
  • ICESat is unfunded beyond 3 / 31 / 02.
  • CURRENT STATUS
  • 13.6M POP 01-1 overguide now reduced to 11.9M
    due to cost cap on launch vehicle delay penalty.
    Additional 7.6M required in FY02 to meet 6 / 1 /
    02 LRD.

6
IT SECURITY
ICESat PROJECT

STATUS AS OF
9/30/01
Risk National Management IT
Security Contingency Agency Number Authorization E
lement Plan Plan Plan Check People To
Proceed Ball / LASP Complete Complete Complete To
Center 22 Pending Security ISIPS /
ISF Final in Dec Final in Dec Final in Dec To Be
Sent 18 N / A (GSFC Bldg 22) Number increased
significantly due to changes in IT security
requirement to include data handling personnel.
Forms have been submitted and fingerprinting is
in progress.
7
PMC ACTION STATUS
ICESat PROJECT

STATUS AS OF
9/30/01
Action(s) NONE
Data / Source
Status
8
ICESat SIGNIFICANT PROGRESS
ICESat PROJECT

STATUS AS OF
9/30/01
  • PROJECT PROACTIVELY COORDINATING WITH AETD
    MANAGERS REGARDING THE ABSORPTION OF STAAC
    PERSONNEL AND FUNCTIONS.
  • PROJECT AND CODE 400 MANAGEMENT IS DIRECTING THE
    GLAS TEAM TO MOVE T / V CYCLES TESTING FORWARD
    IN THE IT FLOW TO GET ADVANCED OPTICAL STABILITY
    PERFORMANCE DATA TO SUPPORT LSM ACCEPTANCE OR
    CHANGE OUT. WILL WORK WITH GLAS TEAM AND AETD TO
    IMPLEMENT THIS REQUEST.
  • GLAS STELLAR REFERENCE SYSTEM IS DEMONSTRATING
    EXCELLENT OPTICAL PERFORMANCE. COMPONENT
    POSITION REFERENCE IMAGES ARE IN PROPER LOCATIONS
    WITH EXCELLENT QUALITY.
  • THE LONG-DURATION (24 X 7) MOC SIMULATION TEST
    WAS SUCCESSFULLY COMPLETED AT BALL / LASP.
    ON-ORBIT OPERATIONS WERE PRACTICED INCLUDING
    NORTHERN GROUND STATION PASSES, TAPE RECORDER
    DUMPS, CONTINGENCY BACK-UP, ETC.

9
GLAS SIGNIFICANT PROGRESS
ICESat PROJECT

STATUS AS OF
10/9/01
  • INTEGRATION PROGRESS
  • FIBER PICKOFF BOX TUNING AND PERFORMANCE CHECKS
  • SRS REINTEGRATION CONTINUED
  • ETALON CONTROL LOOP TROUBLESHOOTING CONTINUED
  • FINAL BORESIGHT ALIGNMENT INITIATED
  • EMI/EMC TEST PLANNING AND COORDINATION
  • REWORK PROGRESS
  • INVAR COUNTERWEIGHT LASER SELECT MECHANISMS
    REWORK AND RETEST COMPLETED. DELIVERED TO IT.
  • LSM1 STABILITY GOOD LSM2 THERMAL STABILITY
    MARGINAL. WILL PROCEED WITH FINAL INTEGRATION OF
    INSTRUMENT.

10
SCHEDULE ASSESSMENT
ICESat PROJECT

STATUS AS OF 10/9/01
  • IN FINAL INTEGRATION FLOW - ALL FLIGHT COMPONENTS
    NOW DELIVERED TO IT
  • REMAINING INTEGRATION TASKS
  • FINAL COMPONENT INTEGRATION 10 / 16 / 01
  • FINALIZE FIBER OPTICS INSTALLATION 10 / 16 / 01
  • COMPLETE FINAL BORESIGHT ALIGNMENT 10 / 20 / 01
  • CONDUCT BASELINE CPT 10 / 26 / 01
  • RADIATOR ASSEMBLY INSTALLATION 11 / 01 / 01
  • FINAL DRESS-OUT OF INSTRUMENT 11 / 06 / 01
  • BEGIN ENVIRONMENTAL TEST PROGRAM 11 / 12 / 01

11
SCHEDULE ASSESSMENT
ICESat PROJECT

STATUS AS OF 10/9/01
  • HAVE LOOKED AHEAD AT OPTIONS TO PRESERVE AN
    ABILITY TO MINIMIZE SCHEDULE AND TO WORK PROBLEMS
    IN PARALLEL IF NECESSARY
  • HAVE DETERMINED WE CAN CONDUCT AN EFFECTIVE
    EMI/EMC TEST OUT OF SEQUENCE IF NECESSARY
  • HAVE REVISITED THERMAL VAC PLANS AND HAVE
    IDENTIFIED FEASIBLE REORDERING OF T / V TEST
    FLOW TO ENSURE EARLY THERMAL PERFORMANCE CHECK OF
    INSTRUMENT
  • WILL RING OUT ANY OTHER UNDISCOVERED GLAS
    PERFORMANCE ISSUES
  • WILL PROVIDE A MORE CREDIBLE LAUNCH DATE
    PREDICTION

12
SPACECRAFT FLIGHT HARDWARE STATUS ICESat PROJECT


STATUS AS OF 9/30/01
EPS
CDH
PCU
ARRAY PANELS
SCC
SEP
PEC
DBC
PDA
TEST BATT
CTU
SSR
SADA
SADE
MIC
ENV
MIC
EIC
FUNCT
EIC
ENV
FUNCT
1
COMM
OTHER
ACS SENSORS
X-BAND XPNDR
S-BAND XPNDR
FLIGHT BATT
FSW
FSWTB
RF FILTER
GPS
ZENITH ANT
NADIR ANT
THRML RAD
FLT PAF
PROP MOD
MIC
ENV
FUNCT
EIC
STAR TRKR
FLT SIRU
ACS / ACTUATORS
PAF
STRUCT
SUN SENSORS
TORQR RODS
RWA
HRNSS
LRA
SUN SENSORS
MIC
EIC
ENV
FUNCT
Legend
SUN SENSORS (G) (G) (G) (G)
GSE
No Problems Minor Problems Major
Problems Complete/Delivered Integration
Complete GLAS Mounting
ITOC (GSFC)
ETM GPS
GLAS SIM
EM IST/LRS
CTV
MAGNETOMETERS
EIC
MIC
FUNCT
ENV
1. Lost lock once during test thermal
sensitivity under investigation
(G)
13
GLAS INSTRUMENT PROBLEM STATUS ICESat
Project

Status as of
10/9/01
RECEIVER SYSTEM
TRANSMITTER SYSTEM
STELLAR REFERENCE SYSTEM
TELESCOPE
LASER REF TELESCOPE
ROSI STAR TRACKER
COLLIMATED REF SOURCE
HARNESSING
LASER
LASER
LASER
ALTIMETRY TOWER
LASER PROFILING ARRAY
GYRO
LATERAL TRANSFER RETROs
LASER REF SENSOR
L S M
L S M
TRANSMIT OPTICS
LIDAR SYSTEM
FIBER OPTIC SYSTEM
THERMAL CONTROL SYSTEM
CONSTANT CONDUCT HEAT PIPES
LOOP HEAT PIPES/ RADIATORS
LASER (816nm) OTS
LED (532nm) OTS
ETALON
BEAM-SPLITTER ASSY
HEATERS/ INSTRUMENTATION
BLANKETING
SPCMs
LBSM
FIBER OPTICS
GROUND TEST PICKOFF ASSY
Legend
BENCH CHECKOUT EQUIPMENT
ELECTRONICS
TARGETS - MAIN/MINI/SRS
TEST SYSTEMS - ALTIMETER/LIDAR/ GPS
No Problems
MAIN ELECT UNIT
HIGH VOLTAGE PWR SUPPLY
Minor Problems
POWER DISTRIB UNIT
HARNESSING
Major Problems
CONTROL- LERS
WORK- STATIONS
NTGSE
14
GLAS INSTRUMENT INTEGRATION
STATUS ICESat Project


Status as of 10/9/01
RECEIVER SYSTEM
TRANSMITTER SYSTEM
STELLAR REFERENCE SYSTEM
TELESCOPE
LASER REF TELESCOPE
ROSI STAR TRACKER
COLLIMATED REF SOURCE
HARNESSING
LASER
LASER
LASER
ALTIMETRY TOWER
LASER PROFILING ARRAY
GYRO
LATERAL TRANSFER RETROs
LASER REF SENSOR
TRANSMIT OPTICS
L S M
L S M
LIDAR SYSTEM
FIBER OPTIC SYSTEM
THERMAL CONTROL SYSTEM
CONSTANT CONDUCT HEAT PIPES
LOOP HEAT PIPES/ RADIATORS
ETALON
BEAM-SPLITTER ASSY
LASER (816nm) OTS
LED (532nm) OTS
HEATERS/ INSTRUMENTATION
BLANKETING
LBSM
SPCMs
GROUND TEST PICKOFF ASSY
FIBER OPTICS
Legend
BENCH CHECKOUT EQUIPMENT
ELECTRONICS
Integrated
TARGETS - MAIN/MINI/SRS
TEST SYSTEMS - ALTIMETER/LIDAR/ GPS
MAIN ELECT UNIT
HIGH VOLTAGE PWR SUPPLY
Complete/Not Integrated
Substitute Hardware Temporarily Integrated
POWER DISTRIB UNIT
Not Delivered to IT
NTGSE
WORK- STATIONS
HARNESSING
CONTROL- LERS
15
SCHEDULE SLACK OVERVIEW


TO PROPOSED 6 / 1 / 02 LRD (1)
ICESat PROJECT

STATUS AS OF
9/30/01
CONTRACT/
DELIVERY CURRENT SOURCE DATE ESTIMATE SLACK G
LAS INSTRUMENT CODE 924 12 / 1 / 01 1 / 28 /
02 -8 WEEKS S/C BUS BALL COMPLETE
(2) OBSERVATORY IT BALL 6 / 1 / 02 7
/ 1 / 02 -4 WEEKS AND LAUNCH NOTES (1) ALL
SLACK BASED ON PROPOSED 6/1/02 LRD AND
INSTALLATION OF INVAR COUNTER
WEIGHTS ON LSMS (2) BALL
SPACECRAFT AND PRE-OBSERVATORY TESTING IS
COMPLETE, IIRR HELD JULY 10 11
16
SCHEDULE SLACK HISTORY
ICESat PROJECT

STATUS AS OF
9/30/01
12 8 4 0
11 WEEKS TOTAL PROGRAM
4 WEEKS TO GLAS FOR IT COMPONENT PROBLEM
RESOLUTION
W E E K S
REWORK OF HEAT PIPES, SPCMS, LASER ADJUSTMENT
AND DC / DC CONVERTERS
8 WEEKS
LATE SRS AND OTHER COMPONENT DELIVERIES TO IT
ASSUMES GLAS DELIVERY DATE OF 12/1/01 AND 6/1/02
LRD
10-WEEK GLAS DELAY (JULY 01 LRD) LRD CHANGE TO
12 / 15 / 01
INSTALLATION OF INVAR COUNTER WEIGHTS ON LSMS
REPLACED DAMAGED HOP EVALUATED TURNING MIRROR
SCRATCH REPEATED WORKMANSHIP VIBRATION OF LSM-2
FLIGHT E-BOX INDUCTOR REPAIR
2 WEEKS
OPTICAL STABILITY AND E-BOX REWORK
6 / 02 LRD
-4 WEEKS SLACK
6/99 1/00 1/01
1/02
17
BACK UP
18
GSFC
ICESat MASTER SCHEDULE
APPVL RESP
C. SCOLESE
Status As Of
10/12/01
ACCOMP RESP
J. DEZIO
99
00
01
02
C
PROJECT/ELEMENT
4
Y
1
2
3
PER
LRD
FOR
PSR
LRR
MOR
REVIEWS
Time Now
MRR
FRR
SPACECRAFT
Avionics and Harness In-House
BALL AEROSPACE
Procure.s, Fab, Assy, Test
ACDS Prop
S/As
Ctrl Computers
PWR
CDH COM
Struct.
S/S Deliveries
Subsystem IT
- 4 Weeks Reserve
Bus Qual w/Instr Mass Model and Elec I/F C/O
w/Simulators
GLAS IT
Environmental Testing
LRD 6/1
Box, Pack, and Ship
CDR
Drill
Flt
GLAS INSTRUMENT
Flt Lasers 2 3
Launch Operations
Template
1
Flt Laser
Tele
GSFC CODE 900
3
Delv 12/15
PER
Slip Delv to 1/28
Fabrication
Assy Test
Review ATBDs
Original GLAS Delv.
Oral
SIPS Version 3
Version 1
Beta Version
Final
SCF Launch Ready
SIPS Version 1
Reviews
SIPS H/W
SIPS CDR
ATBDs
SIPS Version 2
Report
SCIENCE/ISIPS GSFC CODE 900
ORR
Design/Development/Integrate/Test
FDS PDR
Cmd/Tlm Test
Vac Test
Sim Dress Rehearsals
CTV
MOR
Award
CONTROL CENTER/FOT BALL AEROSPACE
FOT Training
Design/Development/Integrate/Test
Final IGS Test Plan
E-T-E Test
Draft IGS Test Plan
Calibration Validation 10/1
Final MORD
30 Day C/O
GRD ORR
EDOS
AGSNGS
ISF
MOWG 2
NSIDC
ESDIS GROUND SYSTEM OPERATIONS
Development
GLAS C/O
LOX Tanks (C)
LOX Tanks (S)
DPAF (C)
S/C Fit Check
Award
DPAF Assy/Mfgr (S)
Delv
LAUNCH VEHICLE DELTA 7320
Manufacturing , Assembly, and Test
Delivery and Launch Operations
CCAS DMCO
Fuel Tanks (S)
Complete 2nd Stage
Start 2nd Stage
Fuel Tanks (C)
19
END OF MISSION PLAN DEVELOPMENT COMPLETED
ICESat PROJECT

STATUS AS OF 9/30/01
Final Estimate Final Orbital Debris
Generation report was approved by Headquarters on
4 / 9 / 01. The total mission package included
ICESat, CATSAT, DPAF, and launch vehicle. Both
ICESat and CATSAT meet the 8m2 guideline by
significant margins. ICESat is 3.9m2 and CATSAT
0.9m2. ICESat will reenter in 15 years, which is
well under the 25 year guideline. Disposal
Option Assessment Controlled Reentry Not
practical -- 240kg additional fuel and 6 months
delay Safe Orbit Not feasible -- same as
re-entry Shuttle Recovery ICESat polar orbit
not accessible to the shuttle also spacecraft
design not manned-flight rated Expect no changes
when CHIPSAT data becomes available
20
Mission Success Starts with Safety EOS ICESat
Project Safety Report
  • Safety Initiative action(s) taken in (September
    2001 of action)
  • Safety for the public
  • Safety for the astronauts and pilots
  • Safety for the workforce
  • Health and Safety Potpourri
  • Safety for high value assets and equipment
  • Safety Performance Metrics (since September 30,
    2001)
  • Number of personal injury accidents 0
  • Number of lost time injuries 0
  • Cumulative number of lost time days 0
  • Number of non-mission-related asset mishaps 0,
    Estimated cost 0
  • Number of mission-related asset mishaps
    0, Estimated cost 0

21
ACRONYMS
ICESat PROJECT

STATUS AS OF
9/30/01
AFT - (GLAS aft optics) AGS - Alaska Ground
Station ANT - Antenna ARO - After Receipt of
Order ATP - Authority to Proceed CCAS Cape
Canaveral Air Station CM Center of Mass CPT-
Comprehensive Performance Test CTU - Command and
Telemetry Unit DBC - Data Bus Coupler DO
Delivery Order DSU - Data Storage Unit EAC
Estimate at Completion E-BOX - Electronics Box (
MEU) EDAC - Error Detection and Correction EIC -
Electrical Integration Complete ENV - Environment
or Environmental EPS - Electrical Power
Subsystem FOR - Flight Operations Review FOT -
Flight Operations Team
FRR - Flight Readiness Review FSW - Flight
Software FSWTB - Flight Software Test Bench HRG -
Hemispherical Resonating Gyro HVPS High Voltage
Power Supply IGS - ICESat Ground System IIRR
Instrument Integration Readiness Review IRU -
Inertial Reference Units ISF - Instrument Science
Facility I-SIPS - ICESat Science Investigator-Led
Processing IST - Instrument Star Tracker ITOC -
Instrument Test Operations Center LASP -
Laboratory for Atmospheric Space Physics LED
Light-Emitting Diode LHP - Loop Heat Pipe LPA
Laser Profiling Array LRA - Laser Retro-Reflector
Assembly LRD - Launch Readiness Date LRR - Launch
Readiness Review LRS - Laser Reference System
22
ACRONYMS
ICESat PROJECT

STATUS AS OF
9/30/01
LSM - Laser Steering Mechanism MEU - Main
Electronics Unit MIC - Mechanical Integration
Complete MIWG - Mission Integration Working
Group MOC - Mission Operations Center MOR -
Mission Operations Review MORD - Mission
Operations Requirements Doc. MOWG - Mission
Operations Working Group MPS - Multi-program
Support MRR - Mission Readiness Review NADIR
Earth-facing side of spacecraft NGS - Norway
Ground Station NISN - NASA Integrated Services
Network NSIDC - National Snow and Ice Data
Center NTGSE - (Windows) NT Ground Support
Equip ORR - Operational Readiness Review OTS -
Optical Test Source PDA - Power Distribution
Assembly PDU Power Distribution Unit PEC -
Precise External Clock
PRA Probabilistic Risk Assessment RWA
Reaction Wheel Assembly S / A - Solar Array SADA
Solar Array Drive Assembly SADE Solar Array
Drive Electronics SCC - Spacecraft Control
Computer SEP - Spacecraft Electronics
Package SIPS Science Investigator-Led
Processing System SIRU - Space Inertial Reference
Unit SLTC Space Lidar Technical Center SM -
Safe Mode SORD - Systems Operations Requirements
Document SPCM - Single Photon Counting Module SRS
Stellar Reference System
23
PROJECT OVERVIEW
ICESat PROJECT

STATUS AS OF 9/30/01
  • ICESat
  • SIGNIFICANT PROGRESS
  • LATEST GLAS COMPLETION DATE CAUSES NEGATIVE SLACK
    TO THE JUNE 1, 2002, LRD
  • DISCUSSION WILL BE HELD ON OCTOBER 15 WITH CODE
    500 MANAGEMENT TO APPLY SPECIFIC SOLUTIONS TO
    OBSERVED PROBLEMS
  • PROJECT AND AETD ACTIVELY PURSUING OPTIONS FOR
    EARLIEST GLAS OPTICAL STABILITY PERFORMANCE
    EVALUATION IN T / V
  • INVAR COUNTERWEIGHT LSM COMPLETED, TESTED, AND
    INTEGRATED INTO GLAS TO PROCEED INTO
    ENVIRONMENTAL TESTING FOR SYSTEM LEVEL EVALUATION
  • GLAS STELLAR REFERENCE SYSTEM IS DEMONSTRATING
    EXCELLENT OPTICAL PERFORMANCE
  • LONG-DURATION (24 X 7) MOC ON-ORBIT OPERATIONS
    SIMULATION WAS SUCCESSFULLY COMPLETED AT BALL AND
    LASP
  • ISSUES / CONCERNS
  • OPTICAL STABILITY MUST BE SUCCESSFULLY
    DEMONSTRATED IN T / V
  • SCHEDULE EROSION DUE TO CONTINUED REWORK AND
    PROBLEM DISCOVERY