Williamsburg Bridge Presentation - PowerPoint PPT Presentation

1 / 68
About This Presentation
Title:

Williamsburg Bridge Presentation

Description:

Williamsburg Bridge Presentation – PowerPoint PPT presentation

Number of Views:85
Avg rating:3.0/5.0
Slides: 69
Provided by: p94139
Category:

less

Transcript and Presenter's Notes

Title: Williamsburg Bridge Presentation


1
Waldo-Hancock Bridge
Cable Retrofit
2
(No Transcript)
3
(No Transcript)
4
Existing Bridge - Elevation
5
7 m
8.6 m
Cross Section Main Spans
6
Wood Fillers
37 1 3/8 Dia. Pre-stressed Helical Strands
9 5/8 Diameter
Cross Section Main Cable
7
Main Cable Deterioration
Inspection
8
Wedging Operation
Wedging Operation
PARSONS
9
Stage 1 Surface shiny, some white areas
(zinc corrosion)
10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
(No Transcript)
14
(No Transcript)
15
(No Transcript)
16
Stage 4 corrosion where strands touch (typ.)
Section Thru Main Cable
17
(No Transcript)
18
37 Wire Strand
Typical Wire Corrosion Patterns at Worst Location
19
Multiple Wire Breaks
20
Wire and Strand Testing
21
Stage 4 Pitting
22
Severe Stage 4 Section Loss
23
Legend
Stage 4
Stage 3
Stage 2
Assumptions at PP12E 14E North Cable
24
PARSONS
25
(No Transcript)
26
(No Transcript)
27
Strand Testing
Three Strand Specimens Tested 83 to 67 of
Original UTS
28
Acoustic Monitoring
29
Supplementary Strands
30
Sequence of Construction
Tower and Bent Saddles, Anchorages Pulling of
Structural Strands Installing Strongbacks Cable
Bands Load Transfer
31
CONSTRUCTION TIMELINE Mid-July Decision to
strengthen cables August 25 Mobilization on
site September 2 Start on-site work September
12 Placed first saddle concrete October
17 Started Load Transfer October 26 Completed
Final Steps Complete - 11 weeks after
first meeting
32
(No Transcript)
33
(No Transcript)
34
(No Transcript)
35
(No Transcript)
36
(No Transcript)
37
Free Cable Geometry
4.2 m
1.3 m
.36 m
.36 m
1.3 m
38
Strand Pulling Operation
Rollers Crane
Rollers
Winch
Reel Tensioner
39
Load Transfer Sequence - First Stage
40
Strongback Tie Rod
New Strands
Existing Cable
Threaded Tie Rod
Strong Back
Existing Suspenders
41
Inclined Tie Rod
42
(No Transcript)
43
Original Tower Saddle
44
Tower Saddle
45
Tower Saddle Offset
46
Installed tower extension
47
Cable Bent
48
Installed Cable Bent extension
49
West Anchorage
Bed Rock
50
East Anchorage
New Anchorage
Existing Anchorage
51
East Anchorage
Bridge Bowl
Dywidag Rod
Steel Tube
Strand
Dowels
52
(No Transcript)
53
(No Transcript)
54
Tensioner Position (For Strand Pulling Operation)
55
High Tension Power Cable Tensioner Modified to
Accommodate Cable End (Bridge Bowl) Maintained
10-15 Kips of Tension During Strand Pulling
56
Loading New Strand Spool onto Spool Stand / Brake
57
Spool Stand/Brake
58
Threading Bridge Bowl Onto Tensioner
59
Overview of Entire Strand Tensioning Equipment
Set-Up
60
(No Transcript)
61
Pulling Device to Guide Bridge Bowl Over the
Saddle Rollers
62
(No Transcript)
63
(No Transcript)
64
(No Transcript)
65
Hydraulic Winch for Pulling Strand
66
Installing Cable Clamps on Existing Suspender
Cables
67
Installation of New Suspender Hanger Blocks
68
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com