U.S. Army Field Support Command - PowerPoint PPT Presentation

About This Presentation
Title:

U.S. Army Field Support Command

Description:

Status (once contracts awarded will move to AMBER) Issue. ... AMBER. GREEN. RED. 07/02/02 'The Force Behind the Force' 17 of 24. Status. Issue. ... – PowerPoint PPT presentation

Number of Views:212
Avg rating:3.0/5.0
Slides: 24
Provided by: iedw
Category:
Tags: amber | army | command | field | support

less

Transcript and Presenter's Notes

Title: U.S. Army Field Support Command


1
U.S. Army Field Support Command
ARMY MATERIEL COMMAND COMBAT EQUIPMENT
GROUP-AFLOAT (CEG-A)
AWRP AMC Execution Plan Briefing 2 July 2002
2
Agenda
  • Operations Event Timeline Update
  • IPR Schedule
  • Critical Events Timeline Update
  • Top Ten AWRP Actions / Issues
  • Resource Update
  • Strong Virginian American Cormorant Download
  • YND Rock Drill
  • Summary


3
Operations Event Timeline
AC D/L
SV D/L
HQDA Implementation Msg
Force Protection (Draft)
7
7
Target YND Site Established
16
Release American Cormorant
8
YND Soil Analysis
8
Embassy Approval
3
3
10
Hythe Branch Plan?
4
Strong Virginian Decision
DA OPLAN Published (Draft)
20
HQDA OPORD / Movements Directive (Still Pending)
?
5
DA Funding
6
CENTCOM Site Survey
9
10-11
20-26
4
AWRP IPR / VTC Schedule (Updated as of 2 JUL 02)
  • CEB-H Internal IPRs (weekly) start 12 FEB
  • AMC CEG-A IPR (VTC) (Monthly 2nd week) 13 FEB
  • DA AWRP IPR/Conference (Orlando, FL) 20 FEB
  • FSC IPR (VTC) (Monthly 4th week) 27 FEB
  • Working Group IPR at YND, Japan 12-15 MAR
  • DA AWRP IPR (VTC) 21 MAR
  • DA AWRP IPR at CEG-A 22-23 MAY
  • ARCENT Contingency IPR at Fort McPherson 4-6
    JUN
  • DA AWRP IPR (VTC) 2 JUL
  • DA AWRP IPR at YND 6-8 AUG

5
AWRP Critical Events 2QFY02
6
AWRP Critical Events 3QFY02
7
AWRP Critical Events 4QFY02
8
Top Ten AWRP Issues / Actions
ISSUE STATUS
1 MOA (AMC / USARPAC)
2 17th ASG ISA
3 Equipment Procurement
4 COSIS Contract Award
5 YND Environmental Review
6 YND LOAD Bearing Study
7 DAC Selections
8 YND Rock Drill Planning
9 SV / AC Download Planning
10 Dredging / Soil analysis at Site 4
AMBER
AMBER
RED
AMBER
AMBER
AMBER
AMBER
GREEN
GREEN
AMBER
  • LEGEND
  • Will not meet the final objective
  • May miss intermediate objective / event but
    will meet final objective
  • Will meet final objective

RED
AMBER
GREEN
9
AWRP Funding Update
  • Surplus Funds (as of 30 Jun 02)
  • 170.4K
  • 100K Power Design
  • 11K Fuel Boom
  • 4K Shelving
  • 55K Manpower
  • UFRs (as of 30 Jun 02)
  • TBD - Potential Impacts of Load Bearing Study
  • TBD - Temp MLC Cost
  • 60K est. SDT
  • TBD MTMC - 100K in program may be
    insufficient

10
Concept of Operation SV AC Download
  • Concept of Operation
  • This is a 4 phase operation
  • Phase 1 Establish YND site
  • Began with the YND site survey in 4QFY01 and
    ends with actions complete to receive watercraft
    UICs on 16 AUG 02
  • Phase 2 SV download
  • Begins with the departure of the SV from CEB-H
    in JUL 02 and ends when all equipment is
    offloaded and positioned at YND and Sagami Army
    Depot in SEP 02
  • Phase 3 AC download
  • Begins with the departure of the AC from DG
    enroute to YND and ends when all equipment is
    offloaded and positioned at YND and Sagami Army
    Depot in SEP 02
  • Phase 4 Transition to End state
  • Begins with the DL of the SV and ends when all
    equipment is stored in final locations DH
    equipment is installed COSIS contractor is
    on-site

11
YND Rock Drill (6-8 Aug 02)
  • Key Participants
  • DA
  • AMC
  • OSC / FSC (AT/FP Ops)
  • CEG-A (Ops)
  • CEB-H (Lead)(Ops / OPP Leader)
  • CEB-NEA (AWRDS)
  • Stanley INC
  • USARPAC
  • USARJ
  • 17th ASG
  • 35 SS BN
  • FORSCOM
  • 7th TC GRP
  • MSC
  • MTMC
  • 836th TC BN

12
Summary
  • 49 Days to SV download at YND
  • Key Events HQDA AWRP IPR (including FSC YND
    Rock Drill)
  • 6-8 AUG 02
  • Must immediately resolve all issues potentially
    impacting DL and storage of watercraft IAW
    timeline
  • MOA / ISA
  • Equipment Procurement (DH Mooring Access
    Equip)
  • COSIS Contract Award

CONTINUES TO BE A GOOD NEWS STORY Considerable
effort to meet end state objectives by all
commands
13
Back Up Charts
14
MOA (AMC / USARPAC)
  • Status
  • Issue.
  • MOA required for AMC mission at YND, Sagami
    Army Depot, and US Army Ammunition Depot/Akizuki
  • Discussion.
  • Initial draft MOA developed during MAR 02 IPR
    at USARJ
  • USARPAC provided signed MOA to HQAMC 12 Jun
    (significant revisions without staffing with AMC
    )
  • FSC draft MOA complete (27 Jun)
  • Timelines MAY NOT meet requirements prior to
    personnel / equipment on-site
  • Recommendation. That the MOA accurately
    reflects current HQDA regulations and directives
  • LEAD USARPAC POC Mr. D.R. Brown, USARPAC
  • Mr. Butch Boyett, AMC

AMBER
15
17th ASG ISA
  • Status
  • Issue.
  • ISA completion dependent on MOA finalization
    and signature
  • Discussion
  • Draft ISA developed between 17th ASG and AMC
    LNO
  • Draft ISA being staffed through CEB-H/AMCCEG-A
  • Timelines MAY NOT meet requirements prior to
    personnel / equipment on-site
  • Recommendation. That the MOA accurately
    reflects current HQDA regulations and directives
  • LEAD USARJ (17th ASG) POC Mr. David
    Brown, 17th ASG
  • Mr. J Kirby, AMCCEG-A

AMBER
16
Equipment Procurement
  • Status (once contracts awarded will move to
    AMBER)
  • Issue.
  • Equipment to dehumidify, moor and gain access
    to prepositioned watercraft in forward storage at
    YND may not be procured prior to the arrival of
    the SV/AC
  • Discussion
  • Initial List of Specs/Dwgs provided Mar 02
  • Finalized List of Specs/Dwgs provided Apr 02
  • PR Cs prepared and submitted to 374th Cont
    Squadron for procurement May 02
  • IBOP forms submitted for D/H and Fenders
  • IBOP on D/H rejected by 374th CS
  • All procurements pending no contracts to date
  • Lead times extended for most of this equipment
  • Recommendation. Continual pressure from HQ
    leadership required to ensure this equipment is
    procured prior to downloads
  • LEAD USARJ / 374th Contracting SQRDN POC

RED
17
YND Environmental Review
  • Status
  • Issue.
  • An Environmental Review required to access
    impact of storing APS watercraft at YND
  • Discussion
  • Issue was addressed during AUG 01 site survey
    at YND and USARJ IPR in Mar 02
  • USARJ stated this was not an issue
  • FSC required written verification to ensure
    watercraft storage, and COSIS operations,
    complies with existing environmental laws
  • No Valid EA/R available
  • USARJ determined ER is required for storage and
    supplemental ER for dredging
  • Recommendation.
  • Ensure ER for watercraft storage is kept
    separate from the SER for dredging. Amend COSIS
    contract if required based on final ER
  • LEAD USARPAC POC LTC Cromby USARJ DCSEN

AMBER
18
YND Load Bearing Study
  • Status
  • Issue.
  • USARJ requested a load bearing survey be
    initiated at YND to access impact of watercraft
    dry storage
  • Funding not identified
  • Discussion.
  • Issue was addressed during site survey in Aug
    01 and USARJ IPR in Mar 02
  • USARJ did not identify this as a requirement
  • Last load bearing study carried out 15 years
    ago
  • Without study DPW cannot ensure that no damage
    will result from the storage of AWRP equipment
  • Land cradle have been design to reduce /
    eliminate potential problems
  • DA reprogrammed . Contract funded and in
    execution.
  • Recommendation.
  • CEB-H design land cradles to significantly
    reduce / eliminate load issues and develop
    alternate storage location COAs
  • USARJ expedite completion of load bearing study

AMBER
19
COSIS Contract Award
  • Status
  • Issue Award of COSIS contract extended to 23
    Sep 02
  • Discussion
  • RFP issued May 02 revision issued 14 Jun 02
  • No contractor participation at site visit
    mid-Jun or Pre-Proposal Conference 21 Jun
  • Contractors expressing interest but requesting
    additional time
  • OSC contracting submitted revised dates of
  • Proposal due date to 25 Jul
  • Conduct proposal evaluations 26 Jul - 13 Sep
  • Source Selection decision evaluation 16-20 Sep
  • Revised target award date is 23 Sep
  • Recommendation.
  • Extend proposal due date to 25 Jul 02with
    contract award 23 Sep. Develop Temp MLC as
    bridge between download and contractor on-site
    date.

AMBER
20
Dredging / Soil Analysis at Site 4
  • Status
  • Issue Dredging at Site 4 Required for permanent
    mooring of 10 x LCU2000s
  • Discussion
  • Site 4 dredging depth insufficient to store
    10xLCU 2000s
  • Two soil analysis at site 4 are inclusive
    (insufficient number of samples and insufficient
    depth of samples)
  • Further testing will be required to meet
    dredging depth requirements
  • If dredging of site 4 cannot be completed,
    temporary location at site 3 may become permanent
  • Dredging is unfunded
  • Recommendation USARPAC expedite soil sampling
    / environmental actions necessary to program /
    fund / execute dredging
  • LEAD USARJ POC Mr. Noah

AMBER
21
DAC Selections
  • Status
  • Issue.
  • Recruitment process for the 3 x DACs has
    extended beyond projected timelines
  • Discussion
  • DAC management team consists of a Logistics
    Manager (GS13), Contract Specialist (GS12), and a
    QA Ship Surveyor (GS12)
  • Job descriptions, recruitment packages
    completed (30 day slip)
  • Selection lists contain adequate qualified
    applicants to fill positions
  • Selection panels on-going
  • Selections scheduled for NLT 16 Jul
  • Team projected on-site 16 Sep (60 day PCS)
  • Recommendation.
  • Continue with adjusted schedule
  • Maintain LNO and CEB-H personnel on-site

AMBER
22
YND Rock Drill
  • Status
  • Issue.
  • Developing YND Rock Drill
  • Discussion
  • Preliminary planning and training aid
    development on-going
  • SV and AC OPORDs (draft) completed
  • OPORD staffing on-going
  • Final concept briefing 8 JUL
  • Recommendation.
  • NA
  • LEAD AMC (CEB-H) POC Tom Ferguson, CEB-H
    CEA
  • Ivor Edwards, Operations

GREEN
23
Strong Virginian / American Cormorant Download
Planning
  • Status
  • Issue.
  • Development of SV and AC OPORDs for DL at YND
  • Discussion
  • Draft OPORDs complete
  • Staffing on-going
  • Final OPORD to be published pending release of
    HQDA AWRP OPORD 2002-XX, Feb 02
  • Recommendation.
  • NA
  • LEAD AMC(CEB-H) POC Tom Ferguson, CEB-H
    CEA
  • Chris Gill, Operations

GREEN
Write a Comment
User Comments (0)
About PowerShow.com