Title: Review of Maintenance Prioritization Schemes from Three Transportation Authorities
1Review of Maintenance Prioritization Schemes from
Three Transportation Authorities
- Christopher L. Farschon, P.E., PCS
- Greenman Pedersen, Inc. Coatings Group
- October 7, 2009
- NACE Eastern Area Conference
2Why Prioritize Bridge Painting?
3Why Prioritize? PLANNING
- Money
- Money
- Money
- Define an acceptable state of existence
- How coating conditions affect a bridge throughout
its lifetime - Identify what funding is needed to meet that need
- Justify painting budgets
4Where to Start Planning?
- Bridge type
- Size
- Proximity
- Location
- Traffic Conditions
- Deck
- Substructure
- Future Rehabilitation
- Coating and Corrosion Condition
5Goals of a Prioritization Program
- Vary by Agency
- Lowest overall cost (today, life cycle, year 20?)
- Define needed funding
- Meet constraints
- Integrate with other work
- Improvements
- Traffic
- Aesthetics
- Be adaptable
6Three Authorities
- A - Toll Authority 1
- Major structures only (9 facilities 26M square
feet) - Metropolitan area
- 100 self funded
- B - Toll Authority 2
- Major highway (hundreds of bridges focus on 16)
- Urban / Metropolitan / Rural
- Combination funding
- C - State DOT District
- Over 1,000 bridges (focus on overpasses)
- Metropolitan and Suburban area
- Federal / state funding
7Historical - Toll Authority A
- Years of as-required maintenance painting
- Increasing environmental concerns
- Increasing steel repair frequency
- Painting Program was planned around 1990,
implemented 1993-1995 - Unofficial Program Goals
- Reduce lead paint liabilities
- Reduce as-needed steel repairs
- Improve bridge appearance
- Define needed funding
8Program Description Toll Authority A
- Based on a facility wide survey conducted in 1993
- Categorizes bridge areas based on paint
conditions and local environments - Appropriate painting is performed in each area to
minimize costs - Access costs very high minimal contracts
- One contract multiple Items multiple methods
9Program Goals Toll Authority A
- Maintain an acceptable paint condition while
maintaining budget goals - Coordinate with Capital improvement projects and
biennial inspections - Address highest priorities within 12 years
10Define the Problem Toll Authority A
11Track Progress Toll Authority A
12Yearly Costs Toll Authority A
Average 21.4M per Year
Average 14.9M per Year
13Types of Painting Toll Authority A
14Unit Cost Trends Toll Authority A
- Low early High middle Lower recently
- Worst corrosion addressed first
- Large projects (economies of scale were good)
- Concurrent with some maintenance
- Aesthetic areas
- Hold until re-paint
- Combination / Rehabilitation Projects
- Difficult projects?
- Some shared costs
- Some additional costs
- Maximize shop painting
15Cost/Specification Factors- Authority A
- Size of the project
- Mobilization and staging areas
- Access to work- placement of equipment
- Lane closures, water - barge etc.
- Environmental controls
- Inspection requirements - warranty
- Configuration or type of structure
- Labor, equipment, and material costs
- Bidding climate (other work, available bidders)
16Program Summary Toll Authority A
- Budgets were justified
- Funding allocated
- Projects designed
- Conditions were monitored with database
population - Influenced priorities on a biennial basis
- Program is in place that relates painting needs
to available time to needed funding - Needs not always driven by conditions
17Toll Authority - B
- Program recently enacted to prioritize painting
of major structures - Not an authority-wide plan (16 of several hundred
structures, but the most significant 16) - Works around/with major capital programs
- Coordination with other maintenance work
- Constructability a key factor
18Project Background Toll Authority B
- Program has 2 objectives
- Part 1 - The investigation and assessment of the
existing coating system on 16 major bridges,
development of a prioritized list of bridges
requiring repainting, and recommendations related
to bridge painting as part of a Ten Year Capital
Program - Part 2 - The design and development of documents
for two (2) Major Bridge Repainting contracts
19Budget / Financial Toll Authority B
- Predetermined budget and timeframe
- anticipated value of 250M
- 10 year effort
- Prioritize the needs based on constraints,
coordination, conditions - Generate project specific engineers estimates
for near-term painting costs
20Bridge Surveys Toll Authority B
- Technical Paint Condition Data Adhesion,
thickness, lab tests, visual survey data for
paint (peeling and corrosion) - Development of square footage quantities
- Other considerations - Deck and Joint condition,
planned rehabilitations and prior painting work
21Painting Options Toll Authority B
- Total Coating Removal and Replacement
- Zone Coating Repair (Beam Ends, Bearings,
Weathering Steel) - Maintenance Spot Painting and Full Overcoating
22Prioritization Toll Authority B
- Rough Budget Estimates Key to project designs
and evening out the workload across the program
duration - Coordination with other work Use of the deck
condition study data, coordination with completed
deck/rehabilitation projects and the capital
improvement projects - Prioritization factors
- Condition of the existing coatings and extent of
corrosion - Condition of the existing deck
- Availability of construction staging areas
- Complexity of maintenance and protection of
traffic - Complexity of containment
- Environmental impacts
- Outside agency coordination
23Prioritization Matrix Toll Authority B
24Project Sequencing Toll Authority B
- Projects of constructible size and duration were
appropriately prioritized / sequenced - Highest 2 priorities under design /construction
- Update survey needed
- Project was a snapshot of conditions combined
with other available data to make the most
appropriate prioritization today - Future survey will justify extending durations
before painting or accelerating certain projects
25Program Summary Toll Authority B
- Select group of bridges
- Projects designed and estimated to fit available
budget - Technical data / conditions were not always the
priority driver - Program is based on a snapshot survey of
facilities - Follow-up survey will be needed
26Authority C
- State Department of Transportation District
- 1998 project
- Over 1,000 bridges
- Majority are highway overpasses and smaller
structures - Semi Automated database system
- Used condition data, constraints,
project-specific factors - Prioritization was based on Return on Investment
27Technical Basis Authority C
- Historical data for coatings in appropriate
environments defines degradation rates - Survey characterizes exposure conditions and
technical paint data - Lowest cost painting option is selected using an
ROI calculation - Current coatings and corrosion condition ratings
- Exposure environment ratings
- Predicted life to next painting event
28Cost vs. Corrosion Theoretical
29Cost vs. Corrosion Actual
30Program Summary Authority C
- Database program generates a list of structures
sorted by ROI - DOT organizes projects to address priorities
(human factor is required) - Condition data easily attained
- Degradation models and cost factors were fixed
- Constraints were variable
- Does not estimate budgets
31Common Threads
- All prioritization programs were custom
- Authority constraints were custom
- All used existing data sources with enhancements
- All need maintenance to remain accurate
- All provide a starting point for defendable
analysis
32Feedback is Needed
- Programs are tools use for designated purpose
and within limitations
Monitor
Design
Learn
33Using Feedback
34Prioritization Program Comparisons
35Prioritization Program Cost
36Inspection vs. Expectation
37Planning a Project
38Conclusions
- Maintenance painting is needed
- All painting can be scheduled with the most
benefit (least cost) by evaluating structures and
implementing a maintenance painting program - Numerous constraints affect a program
- Other work
- Cost trends
- Priorities / Goals
- Program must be adaptable
- Use existing data or existing inspection
activities