Value of Lost Load A Critical Parameter for Optimum Utility Asset Investment - PowerPoint PPT Presentation

1 / 18
About This Presentation
Title:

Value of Lost Load A Critical Parameter for Optimum Utility Asset Investment

Description:

Cost benefit analysis of any new asset development ... Payback period due to higher system reliability. 17. Conclusion. Wider scope of application: ... – PowerPoint PPT presentation

Number of Views:179
Avg rating:3.0/5.0
Slides: 19
Provided by: call82
Category:

less

Transcript and Presenter's Notes

Title: Value of Lost Load A Critical Parameter for Optimum Utility Asset Investment


1
Value of Lost Load A Critical Parameter for
Optimum Utility Asset Investment
2005
Dr. Amir Hisham Hashim Daniel Andrew Sen Radzian
A Rahman 6 December 2005
2
Introduction
  • Utilities are responsible for
  • Generation
  • Transmission
  • Distribution

3
Introduction
  • This responsibility includes ensuring
  • System adequacy
  • Security criteria
  • Balanced against the
  • Investment costs
  • Operating costs

4
Background
  • Two approaches for asset optimization
  • Probabilistic approach
  • Deterministic approach

5
Background
  • Reliability worth according to Billington is
  • Outage Cost to Utility includes loss of
    revenue, loss of goodwill, loss of future
    potential sales and increased expenditure for
    maintenance and repair
  • Outage Cost to Industry includes lost of
    production, damaged machineries and products and
    corrective maintenance
  • Outage Cost to Residential this includes lost
    of frozen foods, alternative energy cost

6
Background
  • Often, outage cost to Industry and Residential
    outweigh the outage cost to Utility
  • Cost can be reduced through
  • construction of parallel lines which connect a
    power source to the load

7
Background
  • Utility Asset Investment Balancing Reliability
    Cost and Reliability Worth

8
Value of Lost Load
  • The Value of Loss Load (VoLL) is
  • The estimated amount that customers receiving
    electricity with firm contracts would be willing
    to pay to avoid a disruption in their electricity
    service.
  • The value of these losses can be expressed as a
    CDF
  • Loss (/kW) f(duration, season, time of day,
    notice)

9
Value of Lost Load
  • Example Customer Damage Functions (CDFs)

10
Application of VoLL
  • Example of three networks with different
    reliability levels

11
Application of VoLL
  • Table 1 Example Failure Events

12
Application of VoLL
  • Table 3 Annual Customer Interruption Cost

13
Application of VoLL
  • Calculation show that, statistically, the
    increase of power lines is proven to reduce the
    annual outage time at a load point, and thus the
    outage costs incurred
  • However, building lines incurs investment cost

14
Application of VoLL
  • Assuming the distance is 100m
  • Capital cost of building an additional line would
    be RM50,000
  • Savings derived from adding another line to the
    spur network so that it becomes a double circuit
    is RM2740.00 RM360.56 or RM2379.44 per year
  • Initial investment of RM50,000 can be recovered
    in a period of 21 years of service

15
Application of VoLL
  • Adding another line for a triple circuit network
    is not cost effective because the additional
    savings is only RM46.64 per year derived
  • Therefore, the optimum topology in this
    particular example case is a double circuit
    network

16
Conclusion
  • Determination of VoLL is important
  • Cost benefit analysis of any new asset
    development
  • Comparision of outage cost vs. investment cost
  • Payback period due to higher system reliability

17
Conclusion
  • Wider scope of application
  • Maintenance work worth RM3 million
  • What is the payback period?
  • What is the projected increase in reliability?
  • What is the projected cost savings of this work?
  • What is the optimum amount of work that needs to
    be done?

18
  • The End
Write a Comment
User Comments (0)
About PowerShow.com