Title: Docket 7081 Transmission Planning Information Workshops Third Workshop September 30, 2005
1Docket 7081Transmission Planning Information
WorkshopsThird WorkshopSeptember 30, 2005
- Shaping Demand-Side Resources
- To Address Transmission Constraints
- John Plunkett
- Optimal Energy, Inc.
2Shaping Demand-Side ResourcesTo Address
Transmission Constraints
- Determining desired shape of DSM resources to
address transmission constraints - Shape of reliability solutions needed for
Southern Loop - Developing and integrating demand-side options
into Southern Loop transmission planning
31. Determining Desired Shape of DSM Resources
- Seasonal timing of additional capacity
requirements - Future timing of capacity requirements
- Hourly duration of capacity requirements
4Determining Desired Shape of DSM Resources
(Continued)
- Seasonal timing of additional capacity
requirements - Summer and/or winter peaking?
- NRP disregarded all space-heat fuel-switching
- Southern Loop peak driven by ski area
development, so cooling savings irrelevant.
5Determining Desired Shape of DSM Resources
(Continued)
- Future timing of capacity requirements
- DSM savings take time to build momentum and
accumulate. - A consistent advance planning horizon is needed
to effectively integrate DSM into transmission
planning (3-10 years).
6Determining Desired Shape of DSM Resources
(Continued)
- Hourly duration of capacity requirements
- The longer the hourly duration of constraint, the
more kWh per kW of peak reduction needed - Efficiency is often superior to load control,
curtailment, or shifting because efficiency kWh
follow hourly load curve before and after the
system reaches peak kW loading
72. Reliability needs of the Southern Loop
- Load growth driven by ski areas and surrounding
communities from southwestern to southeastern
Vermont - Steady load growth due to ski area expansion
since 1980s - Winter peaking, despite shift to statewide summer
peak late 1990s - CVPS steadily reduced load growth with DSM
programs throughout 1990s - Past emphasis has been on space-heating and
water-heating fuel-switching from electricity,
high-efficiency snowmaking equipment,
interruptible contracts - Efficiency Vermont continued efficiency
investment 2000-present - Reliability solutions needed imminently at
current loads - Over time, reliability needs intensify under
continued load growth
83. Developing and Integrating Demand-Side
Options into Southern Loop Transmission Planning
- As part of Southern Loop collaborative, CVPS used
the DUP scoping tool to assess potential for DSM
to defer need for TD upgrades - Preliminary findings indicated that additional
DSM - could not defer immediate problems
- Could defer need for subsequent TD investment to
meet reliability needs in future
9Developing and integrating potential demand-side
TD capacity options for the Southern Loop
(continued)
- VELCO and CVPS engaged Optimal to assist in
detailed analysis of potential efficiency and
renewable options for the Southern Loop - Scope of alternatives to be examined includes
efficiency, cogeneration, and photovoltaic
10Developing and integrating potential demand-side
TD capacity options for the Southern Loop
(continued)
- Progress to date
- Updated scoping tool analysis to incorporate
changes in available technologies (e.g.,
super-T8s, T-5s) - More detailed cost-effectiveness analysis using
program cost-effectiveness analysis tool and more
detailed market and technology characterizations - Analyzed EVT experience in Southern Loop to
refine assessment of remaining potential
11Developing and integrating potential demand-side
TD capacity options for the Southern Loop
(continued)
- Next steps
- Work with CVPS and VELCO to determine where in
region demand reductions would have most impact
on relieving reliability needs (e.g., Manchester) - Work with EVT project managers to determine which
efficiency measures and which customers would
provide additional cost-effective savings - Perform detailed site visits to a sample of
customers to further refine estimates of
achievable potential costs and savings - Develop draft RFP specifications soliciting
demand-side solutions - Possible that VELCO/CVPS could apply to PSB for
combined approval for - Initial wires solution to address immediate
reliability need - Expenditures for targeted DSM initiatives to
defer need for subsequent TD investments