Title: Renewable Energy Supply Curves for E3 GHG Calculator
1Renewable Energy Supply Curves for E3 GHG
Calculator
Energy Environmental Economics, Inc. Greenhouse
Gas Modeling UpdateOctober 2, 2007
2Overview Key Tasks
3Supply Curve Overview
- Key input to E3 Calculator
- Cost of new renewable generation is represented
in supply curves - Based on all-in levelized costs including
capital, operating, interconnection / collection - Separate supply curves for CA and 10 other WECC
zones
4WECC Zones in GHG Model
5Supply Curve Key Tasks
- Collect and assess existing public data
- Develop resource availability within each WECC
zone - Develop levelized costs within each WECC zone
- Input data into spreadsheet model
- Create supply curves
6Data Sources and Assessment
7Supply Curve Data Overview
- Five renewable technologies evaluated
- Wind
- Geothermal
- Hydro
- Biomass
- Solar Thermal
- General approach Use uniform cost assumptions
and let resource class/availability drive zonal
supply curves - Mainstream estimates for 2007 technology
- Use publicly-available data
8Data Sources
- WGA, Clean and Diversified Energy Advisory
Committee (CDEAC) reports (2006) - NREL WinDS Model
- CEC 2007 IEPR Scenario Analyses Project
- California Biomass Collaborative CA Assessment
2006 - ORNL, Biomass as a Feedstock, Billion Ton Vision
Report (2005) - NREL, A Geographic Perspective on the Current
Biomass Resource Availability in the United
States (2005) - EIA, Annual Energy Outlook 2007
- CEC, Central Station Generation Costs (2007)
- AWEA Wind Vision
- BC Hydro, 2006 IEP
- Utility IRPs
- AESO 2005 10-Year Transmission Plan and 2003
20-Year Outlook - NTAC, Canada-Northwest-California Transmission
System Options (2006) - CEC Intermittency Analysis Project (2007)
- NW Power Council, 5th Power Plan (2005)
- NW Power Council, 4th Power Plan (1998)
- Geothermex/CEC, New Geothermal Site
Identification and Qualification (2004) - INL, Virtual Hydro Prospector Estimation of
Economic Parameters of U.S. Hydropower Resources
(2003) - Sargent Lundy/NREL, Assessment of Parabolic
Trough and Power Tower Solar Technology Cost
(2003) - Black Veatch, Economic, Energy, and
Environmental Benefits of Concentrating Solar
Power in California (2006) - MIT, The Future of Geothermal Energy (2007)
- Petty Porro, Updated U.S. Geothermal Supply
Characterizations (2007) - Wiser Bollinger, LBNL, Annual Report on U.S.
Wind Power (2006) - Conversations with Utilities, EIA, State
agencies, Research labs, Resource developers,
Industry groups - CEC Strategic Value Analyses (2003)
9Resource Assessment Methods
- Wind Solar Thermal
- Top-down resource potential assessments with
filters - Geothermal, Hydro Biomass
- Bottom-up project-level evaluation based on costs
conditions, expert opinion
10Cost Estimation Methods
- Used EIAs Assumptions to Annual Energy Outlook
2007 as baseline for conventional and renewable
technology costs - Substituted other technology cost estimates for
EIA values as appropriate - Used adjustment factors to account for inflation
of materials costs since time studies were
completed - Adjusted using regional capital cost multipliers
from U.S. Army Corps of Engineers (range CA
1.20 to WY 0.92) - Cost estimates shown here exclude federal PTC/ITC
and state-level tax incentives (but will include
in base case) - Rule of thumb estimates of gen-tie and
interconnection costs, usually based on distance
to transmission
11Supply Curves
12Total Renewable Resource Availability by Region
(MW)
- Biomass small hydro resources limited
- Some geothermal potential in most areas
- The main story is wind and solar thermal
13DOES NOT INCLUDE LONG-DISTANCE TRANSMISSION COSTS
14DOES NOT INCLUDE LONG-DISTANCE TRANSMISSION COSTS
15DOES NOT INCLUDE LONG-DISTANCE TRANSMISSION COSTS
16DOES NOT INCLUDE LONG-DISTANCE TRANSMISSION COSTS
17Base Case RPS Targets by Region
- RPS currently in effect in 8 of 11 regions
(shaded green) - Assume 5 for other regions to reflect known
renewables plans - WECC-wide gap
- 120,000-150,000 GWh, or
- 13,000-18,000 aMW, or
- 40,000-55,000 MW of wind
18DOES NOT INCLUDE LONG-DISTANCE TRANSMISSION COSTS
19DOES NOT INCLUDE LONG-DISTANCE TRANSMISSION COSTS
20Resource Assessment Cost Estimation
21Wind Resource Cost Data
- Resource Potential from NREL
- GIS input for WinDS model
- 98 resource regions in WECC
- Exclude cities, lakes, Federal lands, gt20 slopes
- Use wind power Class to calculate capacity factor
- Include all resources Class 5
- Include resources lt Class 5 only if local
transmission capacity available - Generation costs (in 2007)
- EIA 2007 Annual Energy Outlook 1595/kW
installed - AWEA Wind Vision 1600/kW installed
- Levelized cost range for all sites in supply
curve 78/MWh - 159/MWh - Interconnection Cost
- Use distance proxy based on NREL GIS data
linear /MW-mile cost - Firming Cost 294/kW installed
22Wind Resources
- 2,400,000 MW of raw potential in WECC
- 277,000 MW included after filtering for power
class and local transmission availability
Total MT Wind54,000 MW
Total WY Wind139,000 MW
23Solar Thermal Resource Data
- Resource Potential from NREL
- GIS data used for WGA CDEAC analysis
- 31 resource regions in WECC
- Exclude cities, lakes, Federal lands, gt1 slopes,
noncontiguous resource areas - Use Direct Normal Irradiation (DNI) class and
Latitude to calculate capacity factor - Include only resources with DNI gt 6.75 kWh/m2/day
- Interconnection Cost
- Used measured distance from center of solar
potential in GIS region to nearest 230 kV line
linear /MW-mile cost
24Solar Thermal Resources
- 128,000 MW of WECC-wide potential included after
applying filters
25Solar Thermal Costs
- Wide range of estimates in literature
- Capital costs range from 2200 to 4400/kW
- Capacity factors from 28 to 56
- Levelized energy cost from 71 to 219/MWh
- Key cost determinants
- Technical progress assumptions
- Tax policy assumptions
- Amount of storage
- Black Veatch (2006) costs used in model
3073/kW - Trough technology with 6 hour storage and 40
capacity factor - EIA 2007 Annual Energy Outlook 3191/kW, 40
c.f. - Levelized cost range for all sites in model
146/MWh - 218/MWh
26Geothermal Resource Cost Data
- Resource Potential
- Project-specific MW and cost estimates
- Use CEC/Geothermex (2004) for CA NV sites
- Use WGA CDEAC (2006) for rest of WECC
- Results after applying EIA filters
- CA 3000 MW at 21 sites
- NV 1300 MW at 43 sites
- BC 185 MW at 2 sites
- Rest of WECC 1500 MW at 24 sites
- Generation Costs
- Site-specific varies with depth, temperature,
proven resource - Cost range for most sites 2400/kW to 3700/kW
- Levelized cost range for all sites 65/MWh to
324/MWh - Interconnection Cost
- Used measured distance from center of site
location to nearest 115 kV line linear
/MW-mile cost
27Hydro Resource Cost Data
- Resource Potential
- Site-specific MW cost estimates
- INL data based on FERC applications
- EIA filtered site list based on costs and other
parameters - E3 selected only sites with existing dam and no
documented barriers - Sites smaller than 30 MW are RPS-eligible
- Total hydro results after applying filters
- CA 660 MW at 41 sites
- NW 2090 MW at 40 sites
- BC 5582 MW
- AB 200 MW
- Rest of WECC 400 MW at 71 sites
- Generation Costs
- Vary by location and conditions
- Range for most sites 1200-1900/kW
- Capacity factors range 15 to 65
- Cost range for all sites 73/MWh to 254/MWh
- Interconnection Costs
- Used INL GIS estimate of distance from site to
existing transmission linear /MW-mile cost
28Biomass Resources
- Biomass includes many different technologies
and resource types - Solid Biomass
- Sub-Categories Wood, Mill Waste, Municipal Solid
Waste, Ag Residues - Constraints Fuel supply is uncertain and has
competing uses - Biogas
- Sub-Categories Landfill Gas (LFG), Wastewater
Treatment, Dairy/Manure - Constraints Most potential is for projects lt1
MW, uneconomic to develop - High gross potential, but difficult to determine
how much is economically developable
29Biomass Resource Cost Data
- Resource Potential
- NREL state-level biomass availability by type
used as reference point - Scaled NREL data using estimate of likely
development in California by 2020 (CEC/California
Biomass Collective 2006) - Results
- CA 600 MW of solid biomass 300 MW of biogas
- Rest of WECC 1700 MW of solid biomass 300 MW
of biogas - Generation Costs (in 2007)
- Biogas (EIA 2007 Annual Energy Outlook) 2492/kW
- Biomass (CEC/CBC 2006) 3646/kW
- Capacity factor 80 for both technologies
- Fuel costs 1.81/MMBtu (biogas) 3.64/MMBtu
(biomass) - Levelized cost range 112 - 135/MWh (biomass)
91 - 111/MWh (biogas) - Interconnection Costs
- Assumed generators locate near transmission, so
interconnection costs minimal
30Treatment of Intermittent Resources
- Wind
- Firmed wind to 90 capacity factor on peak by
adding capital cost of 0.7 MW of CTs for each MW
of wind (net of CT energy benefit) - Added hourly integration costs that increase with
winds share of area generation (5/MWh- 12/MWh)
- Solar Thermal
- Assumed 6 hours of thermal storage allowing 90
capacity factor on peak with no firming - Added 6.25/MWh energy benefit because production
occurs during peak hours - Assumed no hourly integration costs
31Summary of Renewable Energy Costs
- Notes
- Levelized costs include
- Interconnection financing costs
- Fuel costs (for biomass biogas)
- Firming and shaping costs (for wind hydro)
- Regional capital cost adjustments from U.S. Army
Corps of Engineers (e.g., CA 1.20 WY 0.92) - Solar thermal variable costs include peak period
energy benefit - Small hydro and geothermal capital costs are for
generic plant only - Each site in data has its own capital cost
- Costs across sites range widely
32Our Renewables Costs Look High Because
- Tried to account for recent cost inflation (at
least 50 in most cases) - Includes full tax workup based on IOU financing
- Includes estimates of funds used during
construction - Includes estimates of transmission integration
costs - Excludes federal tax credits
- Wind resource is firmed with CTs
33Conventional Resources
- Five technologies considered
- Gas combined-cycle combustion turbine (CCCT)
- Pulverized coal steam
- Coal integrated gasification combined cycle
(IGCC) - Coal IGCC with carbon capture and sequestration
(CCS) - Nuclear
- Assume no limit on quantity of conventional
resources that can be developed in each region
34Comparison of Conventional Resource Costs
- Todays technology
- Same financial, tax credit, and recent cost
inflation assumptions as renewables - Regional differences driven by fuel prices and
capital cost differences
35Key Data Uncertainties
- Solar Thermal generation cost
- Wide range of current costs estimates
- Large uncertainty about future costs
- Interconnection costs
- Variability can be large
- Estimation techniques important, especially for
wind - Data limitations result in different estimation
methodology for different technologies
36Key Modeling Uncertainties
- Include federal and state tax incentives?
- Will PTC ITC expire?
- Modeling CA resources
- Statewide potential vs resource zone approach
- Affects what user can specify in dashboard
- Treatment of intermittent renewables
- Firming integration costs, esp. for wind
- New long-line transmission (e.g. CA-WY)
- What to assume for base case?