Title: Replacement of Financial and Human Resources Systems Project of the Long Range Plan for Information Technology Infrastructure and Administrative Systems
1Replacement of Financial and Human Resources
Systems Project of the Long Range Plan for
Information Technology Infrastructure and
Administrative Systems
2- LRTP VISION
- Provide affordable access, appropriate to the
data and informational needs of any USNH user,
that will be available at anytime from anyplace.
- WITH GOAL
- Provide a reliable information technology
infrastructure with sufficient capacity and
responsiveness to support the ongoing operational
and functional requirements of USNH
3Governance Structure
Board of Trustees
Financial Affairs Committee
Chancellor
Administrative Board
Information Technology Planning and
Advisory Council (ITPAC)
Information Technology Coordinating Council (ITCC)
Steering
Committees (1) Decision Support (2)
Facilities (3) Finance
(4) Human Resources (5) Student
Information (6) Library (7)
Alumni/Development (8) Technology/Telecommunicati
ons
4Eight LRTP Projects
- Project 1 Replace FIS and HRIS
- Project 2 Implement research admin system
- Project 3 Analyze alumni/development
- Project 4 Implement Library tech projects
- Project 5 Continue space inventory system
- Project 6 Authentication/authorization system
- Project 7 Network mgmt and analysis system
- Project 8 Consolidate voice, data, video comm.
5FIN/HR Replacement
New Research/Admin.
UNH Alumni development
Enhance catalogs
Electronic Archives
Add UNH-M
Jstor
Media delivery
Migrate to C/S
Authentication/Authorization
Network mgmt system
Improve and Consolidate Communications, Voice,
Data and Video
6PWC Management Letter, 1998
- The current financial and human resource systems
that are in place at USNH expose the University
System to increased risks due to the systems age
and the outdated platforms on which they runThe
incompatibility of applications, hardware, and
operating systems, and relevant upgrades to the
respective pieces, may cause disruption to system
usage and processing, and instability in the
production environment.
7PWC Management Letter, 1998
- The risks that USNH incurs by continuing its
exposure to such an unstable environment include
irregularities in critical processes and
operations, potential non-compliance with
regulatory requirements, and disruption of
services to the campus, system users and key
business functions.
8Risks Associated with the Operation of Current
Financial and Human Resource Systems
- Systems operate on VAX hardware that is no longer
manufactured - Systems rely on VMS system that is obsolete
- CUFS software is no longer vendor supported
- 1032 database and Cobol derived software were
developed internally for human resources
9Implementation Oversight Structure
10Resource/Costing Assumptions
- Functional areas have responsibility to fund
FTEs to support LRTP implementation beyond
budget. - Campus responsibility to provide staff support
for on-going local training/consulting - Campus responsibility to replace necessary
desktop hardware/software on 3-4 year cycle. - FIN/HR project assumes accelerated process and
selection of low cost vendor, commitment to zero
modifications, capability to fill key positions,
and responsiveness of selected vendor.
11Decisions Made as a Result of the Scout Team
Process
- History
- Recommendations and Conclusions
- Other Assumptions
12- Replacement of both HRIS and FIS with external
products is feasible - Enterprise-wide solutions are available
- The selection process should be limited to those
vendors providing integrated solutions already
installed at some higher education site - Concurrent implementation is preferable
13- Vendors should be able to provide 90 of current
functionality - Vanilla or zero modification is the goal
- The task of the Core and the CURT will be to
determine - what functionality will be lost/gained?
- can USNH adapt its practices to fit the product?
- can the product adapt to fit USNH?
14Responsibilities for Selecting New Finance and
Human Resource Systems
15Everyone
- Know that what is decided in this selection
process will determine how we do much of our
business for the next 10-20 years - Read, understand and discuss the RFP, vendor
proposals, and other information on the web site
(fresh.unh.edu) - Attend vendor presentations
- Give your views to the appropriate
Representatives and members of the Core Team
16Campus User Representatives (Campus User Review
Team)
- Review computer system proposals from your campus
and individual professional perspective - Under leadership of your campus Core Team
representative, collect information from
perspectives of other key campus constituencies - Determine how your current business procedures
would have to be changed for each system proposal - Report to your Core Team representative on the
pros and cons of each proposal
17Resource Representatives
- Review computer system proposals from your
individual professional perspective, considering
this professional perspective across the
University System - Includes areas such as Accounting, Audit,
Benefits, Budget, Purchasing, Research,
Technology Infrastructure, etc. - Determine how current business procedures in your
business area would have to be changed for each
system proposal - Report to your Core Team representative on the
pros and cons of each proposal
18Core Vendor Review Team (The Core Team)
- 16 representatives from each campus and various
business service areas across the University
System who will lead the vendor review - Lead campus and professional area reviews of
proposals - Develop evaluation criteria
- Analyze vendor proposals, costs, etc.
- Meet with people who use the proposed systems on
other campuses - Prepare the final report for the Executive
Steering Committee detailing the strengths and
weaknesses of each proposed system
19Executive Steering Committee
- 5 people responsible for debating all input and
deciding which new system will be selected for
Finance and which for Human Resources - Composed of Vice Chancellor for Planning and
Budget (chair), Vice Chancellor for Financial
Affairs, Director of Human Resources, UNH
Assistant VP for Computing and Information
Services, and USNH Controller - In the final decision, there will be one
representative for each professional area
Technology (VC for Planning and Budget), Finance
(VC for Financial Affairs), and Human Resources
(Director of Human Resources)
20Vendor Selection Phase High Level Evaluation
Criteria
- 1. Basic Product Functionality
- 2. Supplemental Product Functionality
- 3. Product Technology
- 4. Total Costs
- 5. Professional Services and Support
- 6. Financial Viability
- 7. Corporate Strategy
- 8. References
211. Basic Product Functionality
a. Common Items b. Finance c. Human
Resources d. Research/Sponsored Programs
222. Supplemental Product Functionality
a. Common Items b. Finance c. Human
Resources d. Research/Sponsored Programs
233. Product Technology
Platforms on which software runs, system
architecture, etc.
244. Total Costs
Cost of ownership over the estimated system
life cycle, including anticipated internal costs
255. Professional Services and Support
Implementation and on-going a. Basic
Services b. Optional Services, Ideas, and
Proposals
266. Financial Viability
Bidders long-term financial viability
277. Corporate Strategy
Bidders mission/vision growth, product
strategy
288. References
Other higher education institutions for which
bidder has provided similar products services
29 What has been done so far
- . Since February 4 approval of the LRTP by
Trustees, we have
30February
- Advertised for Project Director HR Lead
- Appointed RFP Team
- Designed specs for Nesmith Hall operations center
31March
- Addressed BSC Forum UNH FAC
- Decided on 4 vendors for RFP
- Wrote RFP
- Prepared official responses to vendor RFP
questions - Developed LRTP accounting financial reporting
structure
32March (continued)
- Attended 3 vendor user conferences
- Appointed Core Vendor Review Team
- Developed first-cut high-level evaluation
criteria - Created project web site http//www.fresh.unh.ed
u - Created email address mailto
core.steering_at_unh.edu
33 April
- Addressed BSC Forum
- Selected 4 finalists for Project Director
- Finalized Nesmith Hall RR plans, budget
funding - Developing detailed HR evaluation criteria with
key user groups - Visited UNH, PSC and KSC to develop detailed
Finance evaluation criteria
34April (continued)
- Posted detailed Research evaluation criteria to
the web site - Appointed Campus User Review Team
- Appointed Resource representatives
- Held 1st full meeting of Core
- Briefed ESC on user conferences attended
- Held orientation meeting for ESC, Core, CURT,
Resource reps, and others
35 What still needs to be done?
36April
- Complete detailed Finance HR evaluation
criteria - Review/analyze vendor RFP responses
- Interview (and hire??) Project Director
- Fully fund the LRTP accounts
- Manage renovation set up of Nesmith Hall
- Write article for campus newspapers
- Address UNH FAC other campus user management
groups
37May
- Select finalist vendors for on-campus demos
- Move into Nesmith Hall operations center
- Address campus user management groups
- Perform client reference checks
- Perform client site visits
38May 17 June 18
- Approximate dates for vendor presentations
demos - Depends on number of finalist vendors
- Dates, times, locations content to be
determined later - Current plan
- Each vendor spends one day at KSC PSC
- Each vendor spends 4 days at UNH
- Each vendor has at least one day of follow-up
with Core
39Late June
- Core will collect input from CURT, Resource reps
all others - Core will issue preliminary report to ESC on pros
cons of each vendor proposal
40July, August, September
- Perform detailed cost analysis
- Perform due diligence
- Finalize report of pros cons to ESC
- ESC negotiates with finalist vendor(s)
- ESC makes decision on vendor, product proposal
- Address campus user management groups
41October
- Contract signed with successful vendor