Title: The Do’s and Don’ts of Government Construction Contracts
1The Dos and Donts of Government Construction
Contracts
Or David Lettermans Top Ten Traps for the Unwary
Joseph C. Kovars, Esq. OberKaler 100 Light
Street Baltimore, MD 21202 jckovars_at_ober.com
410.347.7343
Barbara G. Werther, Esq. OberKaler 1401 H
Street, N.W. Washington, DC 2005 bwerther_at_ober.com
202.326.5015
www.ober.com
2 Top Ten Traps
- Authority to bind the Government
- Funding of contractAnti-Deficiency Act
- Recognizing constructive changes
- Notice requirements
- Bilateral modification releases
- Documentation letter in/letter out
- Updating schedules
- Cure notices/show cause
- Claim certification
- False claims
3Federal Acquisition Regulation (FAR)
- Provides uniform policies and procedures for
acquisitions by Federal Govt agencies - Parts 1-51 are policies and instructions
- Part 52 is standard form clauses
- Part 53 is forms
- FAR clauses apply to the extent they are
incorporated into the contract, either full text
or by reference. - The Christian Doctrine
4Procurement Methods for Construction
- Sealed bidding FAR Part 14
- Only used where price is sole basis for award
- Contracting by Negotiation FAR Part 15
- Used when factors other than price are considered
- Used for Best Value procurements
- Negotiation is a term of art its not a real
negotiation!
5Sealed Bidding
- Invitation for Bid (IFB) is used
- Bids are publicly opened
- Award goes to lowest price, responsive bid by a
responsible bidder - Responsive bid means complies in every respect
with the requirements of the IFB (FAR 14.404-2) - Responsible bidder refers to financial
resources, integrity, organization and skills,
ability to meet schedule, and past performance
(FAR Part 9.1) - Firm, fixed-price contract results.
6Contracting By Negotiation
- Request for Proposals is used (RFP)
- Tradeoff between price and other factors (Best
Value) - Evaluation factors and significant sub-factors
must be clearly stated (Section M of RFP) - Must state whether all other factors are more
important, less important or equally important as
price - Separate technical and price proposals submitted
(separate volumes)
7Contracting By Negotiation - 2
- Technical evaluation by technical team
- Price evaluation by price team
- Technical price kept separate until final
selection decision - Oral presentations can be used
- Can typically award on basis of initial proposals
without discussions - Or can hold discussions, followed by BAFO
8Contracting By Negotiation - 3
- If discussions are held with one offeror, must
hold discussions with all within competitive
range - Discussions must indicate deficiencies,
significant weaknesses and adverse past
performance information - Exceptions may be taken, but are risky
- Additional features and enhancements may be
offered
9Contracting By Negotiation - 3
- Debriefing of unsuccessful offerors available on
request - When to protest?
- Whats the likelihood of winning a protest?
10Funding Anti-Deficiency Act
- Procurements are funded through appropriations.
- The appropriation is listed on the contract form
should be checked. - Anti-Deficiency Act prohibits Making or
authorizing an expenditure or creating or
authorizing an obligation in excess of the amount
available in the appropriation or fund unless
authorized by law. (31 U.S.C. s. 1341(a)(1)(B))
11Funding Anti-Deficiency Act
- Anti-Deficiency Act -- Governments
representatives cannot make any payment or a
commitment to make payment for work unless there
are sufficient funds in the bank (in the
appropriation) to cover the cost in full. - What does this mean in terms of the multiyear
construction project?
12Funding Anti-Deficiency Act
- Limitation of Funds clause (FAR 52.232-22) -
Monitor costs and notify at 75. Right to stop
work. - Availability of Funds clause (FAR 52.232-19)
Funds are not presently available for
performance beyond ______. . . Implied right to
stop work. - What happens when the Government runs out of
money and there is no new appropriation?
13Changes
- FAR 52.243-4 CHANGES (JUNE 2007)
- (a) The Contracting Officer may, at any time,
without notice to the sureties, if any, by
written order designated or indicated to be a
change order, make changes in the work within the
general scope of the contract, including changes
-- - (1) In the specifications (including drawings and
designs) - (2) In the method or manner of performance of the
work - (3) In the Government-furnished property or
services or - (4) Directing acceleration in the performance of
the work.
14Changes
- (b) Any other written or oral order (which, as
used in this paragraph (b), includes direction,
instruction, interpretation, or determination)
from the Contracting Officer that causes a change
shall be treated as a change order under this
clause provided, that the Contractor gives the
Contracting Officer written notice stating (1)
the date, circumstances, and source of the order
and (2) that the Contractor regards the order as
a change order. - (c) Except as provided in this clause, no order,
statement, or conduct of the Contracting Officer
shall be treated as a change under this clause or
entitle the Contractor to an equitable
adjustment.
15Changes
- (d) If any change under this clause causes an
increase or decrease in the Contractor's cost of,
or the time required for, the performance of any
part of the work under this contract, whether or
not changed by any such order, the Contracting
Officer shall make an equitable adjustment and
modify the contract in writing. However, except
for an adjustment based on defective
specifications, no adjustment for any change
under paragraph (b) of this clause shall be made
for any costs incurred more than 20 days before
the Contractor gives written notice as required.
In the case of defective specifications for which
the Government is responsible, the equitable
adjustment shall include any increased cost
reasonably incurred by the Contractor in
attempting to comply with the defective
specifications.
16Changes
- (e) The Contractor must assert its right to an
adjustment under this clause within 30 days after
(1) receipt of a written change order under
paragraph (a) of this clause or (2) the
furnishing of a written notice under paragraph
(b) of this clause, by submitting to the
Contracting Officer a written statement
describing the general nature and amount of
proposal, unless this period is extended by the
Government. The statement of proposal for
adjustment may be included in the notice under
paragraph (b) above. - (f) No proposal by the Contractor for an
equitable adjustment shall be allowed if asserted
after final payment under this contract.
17Changes
- The contractor is required to perform the changed
work as directed and make claim under the
Disputes Clause if not paid. (Constructive change
or dispute over unilateral amount granted). FAR
52.233-1(i) - Permissible scope of changes
- Drawings and specifications
- Method or manner of performance
- GFM/GFP
- Directed acceleration
- Time of performance (nights, weekends)
- Place of performance
18Changes
- Types of Changes
- Formal
- Constructive
- Formal/Express Changes
- Directed change or CCD unilateral from
Government - Bilateral supplemental modification to contract
- Accord and satisfaction
- Reservation of rights
- Who may initiate? Either party
19Changes
- Constructive Changes
- Conduct by C.O. or authorized representative
which has the effect of causing the Contractor to
perform work different from that set forth in the
contract, - Even when not described or acknowledged as a
change.
20Changes
- Elements of a Change
- Direction to do something different from existing
contract - Within the general scope of the contract
- Issued by C.O. (or duly authorized representative)
21Changes
- What does within the general scope of the
contract mean? - No exact formula
- 99.99 of every change you will ever see.
- Prohibition on issuing changes outside the
general scope because significantly different
work should be put out for bid. - Changes beyond general scope are cardinal
changes.
22Changes
- Cardinal change
- 1965, Wunderlich Constructing Co. v. U.S., Court
of Claims says changes beyond the general scope
of the contract are cardinal changes - The number of changes, in and of itself, is not
necessarily a cardinal change - More of the same kind of work (i.e., more
asbestos abatement) not a cardinal change - Direction to build an airstrip when the contract
was for the terminal probably is a cardinal
change
23Changes - Authority
- Who has authority to issue changes to the
Contract? (FAR 1.603-3(a)) - Only the C.O. (or authorized representative) has
authority to bind the Government and modify the
contract - Who is the C.O. ?
- What is authority of COTR?, ROICC?, etc.
24Changes - Authority
- The Government is not legally bound by
unauthorized acts or acts of unauthorized agents - Apparent Authority is NOT AVAILABLE AGAINST THE
GOVERNMENT. - Contractors duty to assure authority behind
direction. - Dont be a Volunteer.
25Changes - Authority
- When is the Government bound by unauthorized
actions? - Implied Authority/Course of Conduct
- Ratification
- Equitable Estoppel
26Changes - Authority
- Who does not have authority?
- Inspectors
- Contract administrators
- Getting confirmation
- If you are directed by a Government
representative, send a letter to the C.O. and ask
the C.O. if you are to comply with the directive,
i.e., have the C.O. ratify the directive.
27Constructive Changes
- What is a constructive change?
- (Subsection (b) of the changes clause)
- A directive to the Contractor
- Requiring the Contractor to perform additional or
changed work - Contractor relied on the Government direction and
incurred increased cost, added time - Notice given
28Changes - Types of Constructive Changes
- 1. Interpretation of specifications and drawings
- Ambiguity in the specifications/drawings
- Patent vs. latent
- The ambiguity is latent
- The contractors interpretation is reasonable
- The Government has a different interpretation and
tells the contractor to perform in accordance
with the Governments interpretation - The contractor incurs additional costs by
complying with Governments interpretation
29Changes - Types of Constructive Changes
- Inconsistencies between drawings and
specifications - FAR 52.236-21
- If only in specifications, or only in drawings,
treat as if mentioned in both places - In case of difference, specifications govern over
drawings - If the discrepancy is patent, duty to inquire
pre-bid - If the discrepancy is latent, give notice,
segregate costs
30Changes - Types of Constructive Changes
- 3. Defective Specification
- The Government warrants the adequacy of its
specifications - Must be a design specification (implied warranty
on Government under Spearin) - Specifications contain errors, omissions,
inconsistencies - Contractor entitled to costs of attempting to
comply and for performing corrective work
31(No Transcript)
32Changes - Types of Constructive Changes
- 3. Defective Specification
- The Government warrants the adequacy of its
specifications - Must be a design specification (implied warranty
on Government under Spearin) - Specifications contain errors, omissions,
inconsistencies - Contractor entitled to costs of attempting to
comply and for performing corrective work
33Changes - Types of Constructive Changes
- Risk of Specification Problems
- Design Specifications Government owns risk
- Performance Specifications Contractor owns risk
- Mixed Specifications It depends (analyze in
detail)
34(No Transcript)
35Changes Types of Constructive Changes
- Risk of Specification Problems (contd)
- Design-Build Contracting
- Building Information Modeling (BIM)
36BIM
37Changes - Types of Constructive Changes
- 4. Inspection and Testing
- Government over-inspection
- Improper or incompetent rejection
- Government directs a change in testing method or
frequency - More stringent testing procedure than that set
forth in contract - Interference by Government in unreasonable
inspecting during performance
38Changes - Types of Constructive Changes
- 5. Changes In The Method And Manner Of
Performance - Where C.O. insists on a change in the
contractors method and manner of performance of
the work - Contractor can recover the difference in cost
between its method and Governments method - Example change in planned sequence
39Changes - Types of Constructive Changes
- 6. Constructive Acceleration
- When Government effectively requires the
contractor to finish earlier than planned
40Changes - Types of Constructive Changes
- 7. Duties of Cooperation, Not to Hinder
- NTP issued, but contractor not permitted to
construct road to worksite - Work on railroad tracks can only be performed
with Owners flagmen and at night, but no flagmen
work at night - C.O. withheld design fix from contractor and
charged contractor LDs for not finishing on
time
41Changes - Types of Constructive Changes
- 8. Cumulative Impact
- Combined impact of a large number of changes
- Ripple effect
- Note Low rate of success in cases. Measurement
of damages is amorphous. - Be careful when signing modifications
- Bell BCI v. United States (Fed. Cir. 2009)
42Changes
- Notice Requirements
- Notice must be timely
- Notice must be in writing
- Notice must be sent to the C.O.
- Notice must set forth the nature of the claim
- Constructive changes notice relates back 20
days, as to costs incurred - No time limit for defective specifications
43Changes
- Exceptions to Strict Notice Requirements
- (1) Where the Government knew about the basis of
the claim - Actual knowledge can be shown from Government
records - Presence of Government personnel on jobsite
- Acts of Government in working with contractor
to address issue - Meetings
- (2) Where the Government considers the claim on
the merits without complaining about lack of
notice - (3) Where the Government is not prejudiced by the
lack of notice - Government has burden of proving it was
prejudiced - Prejudice occurs if Government cannot mitigate
expense or elect any one of available options
44Changes
- Contractor Duty to Proceed
- The Contractor must perform the changed work
- C.O. can terminate contract for default if
contractor does not proceed - Disputes Clause Contractor can submit its claim
- Equitable Adjustment
- Price
- Bruce Construction v. U.S., 324 F.2d 516 (Ct. Cl.
1963) keep a contractor whole when the
Government modifies the contract. - Actual, reasonable cost ordinarily incurred
because of the change - Actual cost plus reasonable OH P
- May include costs incurred for affected work
areas not changed - Time
- If the change order implicates work on the
critical path, additional time may be required - The Request for Equitable adjustment (REA)
45Delays Suspension
- Types of delays
- Excusable, Compensable, Unexcused
- Special Cases
- Sovereign vs. contractual acts
- Subcontractors suppliers
- Bankruptcy financial inability (unless
Government caused) - Compensable Special Case
- Differing Site Conditions
46Delays Acceleration
- Concurrent delays burden on claiming party to
untangle - Net effect excusable delay no damages
recoverable by either party - Requires two delays on critical path
- Highly fact intensive
- The Hurry Up and Wait problem
47Delays Acceleration
- Notice requirements
- 10 days. Prejudice rule.
- Boards believe in contemporaneous records.
- Right to early completion conceptually
accepted, but difficult to prove. - Schedule must be realistic and relied upon
48Delays Acceleration
- Proving Delay Claims
- Sophistication of Boards and Court of Claims for
delay claims - CPM schedule is normal basis of proof
- Some cases even say hard to imagine proving claim
without CPM analysis - Sophisticated in review/analysis of CPM
presentations - TIA/Windows
- Impacted as planned,
- Collapsed as built,
49Delays Acceleration
- Important to use contemporaneous schedules and
updates. - Have solid schedule as early as possible
- Update it accurately and honestly.
- Will have to live with project schedule for
claims purposes - If Government restricts updates, create shadow
schedule
50Delays Acceleration
- Acceleration
- Well recognized doctrine
- Actual and constructive
- Constructive effect of requiring acceleration
51Terminations
- Terminations for Default FAR 52.249-10
- Draconian a forfeiture - disfavored
- High standard of proof
- Default termination is discretionary with C.O.
- Improper default termination is converted to a T
for C - High stakes a dispute is winner take all
52Terminations
- Terminations for Default (cont.)
- If default sticks, the government recovers its
re-procurement costs from the defaulted
contractor - And, any other rights available to the
Government, such as LDs - Burden of proof is on the Government to show, by
a preponderance of the evidence, that the default
termination was proper.
53Terminations
- Grounds for Default Termination
- Failure to complete the work within the time for
the contract or any extension. - Failure to make progress
- Repudiation by the contractor
- Contractors failure to perform its obligations
under the contract - Failure to provide adequate assurances that
performance will proceed - Failure to continue performance during a dispute
54Terminations
- Cure Notice (or Show Cause) FAR 49.402-3(e)
- Required in supply contracts
- Not required in construction contracts
- But, Government often issues cure notice
- Take this very seriously
- Provide adequate assurances
55Claims and Disputes
- Contract Disputes Act
- Basic statute governing claims
- Established claims process and forums for
disputes - Initiation of claim submitted to CO, request
Final Decision - Definition of claim
- written assertion,
- matter of right,
- payment of sum certain
56Claims and Disputes
- Must be Certified if over 100,000
- Final Decision is prerequisite to
appeal/litigation - Final Decision must be provided in 60 days
- Unless it isnt can specify a longer period
(usually 60 more) - May consider claim as deemed denied if not
timely issued - Interest from date of certification
57Claims and Disputes
- Certification Requirement
- Classic trap for unwary
- Made by authorized person who can bind the
company - Claim made in good faith
- Supporting data are accurate and complete to the
best of my knowledge and belief - Amount requested accurately reflects the
adjustment for which the contractor believes the
Government to be liable
58Claims and Disputes
- Under penalty of perjury
- False Claims Act liability criminal and civil,
company and personal - Subcontractor issues want subcontractor to
certify to you - Even if the sub does so, need to do due diligence
independently, - Cant rely blindly on sub certification.
- Pass thru agreements-- need to remain liable to
sub for what sub is claiming.
59Claims and Disputes
- Appealing Contractor Performance Evaluation Todd
Construction v. U. S., 656 F.3d 1306 (Fed. Cir.
2011) - Pre-Todd Rule Unsatisfactory performance
evaluations not appealable. - Post-Todd contractor may appeal UNSAT because it
is a claim relating to the performance under the
contract. - To obtain judicial review, must comply with CDA
claim certification requirements.
60Recovering Costs from the Government
- Field overhead
- Can recover as percentage adder to direct costs,
or as extended, time-related cost. - Not both, and only consistent with general
treatment. - This generally means go with percentage markup.
61Recovering Costs from the Government
- Unabsorbed home office overhead Eichleay
Formula - So many restrictions that generally not worth the
trouble any longer - Among other things, requires essentially complete
standby situation, and showing impracticable to
take on replacement work
62False Claims
- False Statements Act, 18 U.S.C. 1001
- False Claims Act, 3729 (a)(1) and (a)(2)
- (a)(1) imposes contractor liability for knowingly
presenting, or causing to be presented, false
claims - (a)(2) imposes contractor liability knowingly
using false records or statements to obtain
payment for false claims. - Numerous Other Fraud/Falsification Statutes
Penalties
63False Claims
- MAIN ELEMENTS
- A claim for payment submitted to the Government
- Falsity (claim itself or records supporting)
- Knowing conduct
64False Claims
- CLAIMS
- Requests for progress payments
- Request for final payment
- Requests for Equitable Adjustments and Claims
- Statements Regarding the Quality of the Work
65False Claims
- FALSITY
- Does the Contractors Conduct Comport With Its
Contractual, Regulatory, and Statutory
Obligations - Invoice misrepresenting quantity installed
- Invoice seeking payment for non-conforming work
- False certification of payment of Davis Bacon Act
wages - Payment and/or proper classification of workers
- REAs with factual misrepresentations.
66False Claims
- Knowing Conduct
- Did Contractor have
- actual knowledge of the falsity,
- deliberately ignore the truth or falsity of the
information, or - act in reckless disregard of the truth or falsity
of the information - Did the Government have prior knowledge of the
facts allegedly constituting a false claim?
67False Claims
- OTHER EXAMPLES
- False certifications of compliance with the
contract requirements - Representations of timely payment to
subcontractors - Billing amounts not intending to pay subs
- Seeking or obtaining payment for work the
Contractor knows does not conform to the contract
requirements - Inflated quantities in an invoice
68False Claims
- Daewoo v. United States
- Forfeiture of affirmative claim due to fraud
- 65 M claim became 50 M adverse judgment
- Affirmed on appeal
- Numerous mistakes -- Unclear consequences
69Ethics/Compliance
- BASIC ELEMENTS
- Written code of business ethics and code of
conduct - Internal audit of company policies, procedures
and controls - Mechanism for anonymous reporting of violations
- Compliance/ethics education program for employees
- Enforce disciplinary actions for violations
- Cooperation with government investigations
70Ethics/Compliance
- Mandatory Disclosure Rule (FAR 52.203-13)
- Contractor shall timely disclose in writing to
OIG and CO, when credible evidence that the
Contractor has - Committed a violation of Federal criminal law
(fraud, bribery, gratuities, conflict of
interest) - Committed a violation of the civil False Claims
Act or - Obtained a significant overpayment from the
Government. - Duty continues for 3 years following final
payment. - Failure to make required disclosure is grounds
for debarment. FAR 3.1003 -
71Ethics and Conduct Requirements
- FAR 52.203-13 requires Contractors (except
commercial item contracts and small businesses - Have a written code of ethics and conduct
- Exercise due diligence to prevent and detect
criminal conduct - Encourage ethical conduct and promote a culture
of ethical compliance - Implement ongoing business ethics awareness and
compliance program
72Ethics/Compliance
- Procurement Integrity Act and FAR 52.203-14
require Contractors to exercise due diligence
to ensure that no employee gains an unfair
competitive advantage by possessing - Proprietary information obtained from a
government official without permission, or - Source selection information that is not
available to all competitors. - In the event of an OCI or PCI, Contractor must
disclose to the Government.
73Ethics/Compliance
- Strategy to Mitigate OCI/PCI Risks
- Develop a comprehensive plan that includes
detection, mitigation and removal of conflicts of
interest. - Screen employees and acquisition targets for OCI
and PCI risks and avoid acquiring/hiring them, if
possible. - Assign a senior ranking individual as compliance
officer for the firm - Assess OCI and PCI risks periodically
- Prepare OCI and PCI disclosures when necessary.
74Questions?