Title: Toyota Corporate Real Estate and Facilities
1Toyota Corporate Real Estate and Facilities
- Jennifer Drilling
- Construction Management
April 15, 2003 Senior Thesis Presentation
2Presentation Agenda
- Project Background
- Critical Path Investigation
- Interior Partitions
- Energy Optimization
- Mechanical Analysis
- Lighting
- Research
- Contractors Role on a Green Building
- Final Recommendations
3Project Background
- Toyota Project culminates the leasing of 10 other
facilities - Predominantly Open Office Space - 565,000 SF
- Food Court 35,000SF
- Grand Lobby Entrance
- 3 Story Cast-In Place Concrete Tilt-Up Panels
braced by steel
4Site Layout
- Location
- Torrance, Southern California
- 5 Buildings
- 50 Acres
- Lobbies
- 2 Central Plants
- Existing Toyota Facilities
- Construction Fence
- Future Toyota Lot
5Project Delivery
CM AGENT
OWNER
LEED CONSULTANT / COMMISIONNING AGENT
ARCHITECT/ ENGINEERS
CM AT RISK (Cost Plus Fee)
SUBCONTRACTORS (Design-Build)
SUBCONTRACTORS (Lump Sum)
6Client Goals
- Goals
- Quality
- LEED Certification - GOLD
- Addressed by energy optimization tools where
the contractor can play a significant role - Schedule
- Critical move-in date
- Current Construction Sept. 1, 2001 April 17,
2003 - Desires to move in sooner if possible
- Addressed by evaluating critical path for Tenant
Fit-Out - Budget
- Annual loan payment must meet current lease
payments - Addressed by life cycle and annual costs
7Presentation Agenda
- Project Background
- Critical Path Investigation
- Interior Partitions
- Energy Optimization
- Mechanical Analysis
- Lighting
- Research
- Contractors Role on a Green Building
- Final Recommendations
8Interior Partition Investigation
- Typical Floor Plan
- Owner Assumption
- Under Ceiling Walls are more Sustainable and less
costly to remove - INVESTIGATE
9Existing Conditions Interior Partition
- Type A Exterior Part of Building
- Type N Interior
- Type B Interior Exterior
10Interior Partition Investigation
- Assessment of Schedule
- Risky Short interval critical path activities
gives rise to delays - Flow of work is stopped
- Coordination- greater efforts needed
- Loss production time mobilize and tear-down
twice - Solution
- Use over ceiling walls to accelerate schedule
11Interior Partition Investigation
- Every wall has comparative advantage and
disadvantages - All should be considered
- Full Height
- Reduced Schedule- 2 weeks per floor
12Interior Partition Investigation
- New Schedule
- Flow of work is enhanced
- Saves time money on general conditions
- Investigation is not complete until walls are
demolished.
13Demolition
- Under Ceiling wall
- 4 feet replacement on each side of wall
- Grid bends
14Presentation Agenda
- Project Background
- Critical Path Investigation
- Interior Partitions
- Energy Optimization
- Mechanical Analysis
- Lighting
- Research
- Contractors Role on a Green Building
- Final Recommendations
15Mechanical Analysis
- Goal
- To assess the best energy efficient mechanical
system for the Toyota Project - To gain maximum LEED Points 10
- Basis for Investigation
- Research showed successful geothermal systems in
California
16Mechanical Analysis
- Advantages Geo-thermal Systems Bring
- Mechanical equipment and space reduced
- Maintenance costs halved
- Piping would be reduced due to localized zoning
systems - Extremely quiet system
- Can be put virtually anywhere
17Mechanical Investigation
- Investigation of both systems on the Energy
Modeling Tool for California Buildings - EQuest
- Set up Zoning
- 3D Model
- System Flow
- Diagram
- Detailed System
18Geothermal System
- Based on
- 25 systems each
- 10 x 2 well configurations
- Vertical Wells
- 15 foot spacing
- Internal Zoning
19Geothermal System
- Reasons for why geothermal was not ideal
- Ground temperatures much warmer in So. CA 55
- Need 1/3 longer vertical loops than a
northeastern system - Runs solely on electrical energy, 18.7 ratio of
gas to electrical cost in CA - Reasons why absorption chiller favors
- Unusually high COP (.9 compared to .6)
- Very low wet bulb So. CA
- Only need direct (gas-fired) evaporation,
adiabatic low energy use
20Presentation Agenda
- Project Background
- Critical Path Investigation
- Interior Partitions
- Energy Optimization
- Mechanical Analysis
- Lighting
- Research
- Contractors Role on a Green Building
- Final Recommendations
21Lighting Analysis
- Goal
- To investigate the existing lighting system for
- Energy Efficiency
- Cost
- To incorporate more daylight into the space
22Lighting Analysis
- Existing System
- Linear Lighting
- A-B Switching
- 2 lamp T5 Standard
- 2900 Lumens/lamp
- LLF .75
- 66 Watts/fixture
23Existing Lighting
- 1.4 W/SF
- Not including task lighting (allow .3 W/SF)
- Ideal is 1.2W/SFfor office
- .7 W/SF
- Can use with day light only
- Less optical control
- 60 x 42 typical floor space
24Lighting Analysis
- Proposed Energy Efficient Design
- One T5HO lamp w/Advance Stepped Ballast in same
Linear Light Fixture - Orientate Lights horizontally to window
- 1.15 Watts/SF
- Plus task lighting
25Day Lighting Investigation
- Proposal
- Use of Light Shelf
- Better Distribution of light
- Diagram
- Height Illuminance
- Distance is from window
26Day Lighting Investigation
- Existing Day lighting- south (w/out fluorescent
lights) - Harsh glare
- No workable area until 30 back in space
- 400 200 100 75fc 60fc 40fc 35fc 30fc 25fc
20fc
27Day Lighting Investigation
- 3D AutoCAD Model to AGI 32 Day lighting
- Usable occupancy space changes
- More comfort near windows
25
13
400 200 100 75fc 60fc 40fc 35fc 30fc 25fc
20fc
28Cost Savings/Energy Analysis
- New T5HO Design reduces material cost by
299,000 - Annual utility costs by 40,000
29Presentation Agenda
- Project Background
- Critical Path Investigation
- Interior Partitions
- Energy Optimization
- Mechanical Analysis
- Lighting
- Research
- Contractors Role on a Green Building
- Final Recommendations
30Contractors Role on a Green Building
- Literature Review
- Very little information gear towards the
contractors role - Goal
- To develop guidelines of valued added activities
a contractor may perform during a green project - Pre-Construction
- Construction
- Where is their role most significant?
- Establish industry comments, concerns, and
knowledge of issue
31Contractors Role on a Green Building
- Established network of green professionals
around country - 32/60 surveys
- 5 page questionnaire
- Ranking of 94 potential possibilities
- Many comments provided
- 16 Contractors
- 3 Design-Builders
- 5 Architects
- 3 Consultants
- 4 A/E Managers
- 1 Owner
32Contractors Role on a Green Project
ALL PARTICIPANTS
EXPERIENCED PARTICIPANTS
- Design-Build high, more aware of potential of
early involvement - Architects Consultants rate low, feel pre-con
and finishing design is not where the contractor
should have a big impact
- Less experienced people scored high. More
experienced people knew more of what a contractor
could actually accomplish
- Questionnaire Ranking 1 Contractors have
little significance in this role - 4 Contractor has significant impact to this
role
33Contractors Role on a Green Project
Highest Ranked Areas
- HIGH
- Help owner and engineer to produce estimates of
possible LEED points - Locate a recycle facility that can provide the
resources to recycle all types of materials
Lowest Ranked Areas for Pre-Construction
Lowest Ranked Areas for Construction
- LOW
- Encourage conservation of existing natural
features within a site plan - Suggest coogeneration
34Contractors Role on a Green Project
- Common Interesting Comments
- A Design/Build Project delivery system would
enhance the impact of the Construction
Professional in Material/Equipment selection
process Art Hunkele - This industry really wont change until the
design and construction process begin to function
as a seamless whole. - Bill Reed
- Suggested Future Research
- Produce with the LEED guidelines a list of CM
services - Developed a sustainable CII Process
- This Research will be used towards articles for
- Smart and Sustainable Built Environment-
(International Conference Australia) - United Nations Environmental Programme
35Presentation Agenda
- Project Background
- Critical Path Investigation
- Interior Partitions
- Energy Optimization
- Mechanical Analysis
- Lighting
- Research
- Contractors Role on a Green Building
- Final Recommendations
36Final Recommendations
- Change Under Ceiling Walls to Full Height Walls
to accelerate schedule by 2 weeks per floor - Saves money of life cycle by reduced installation
and general conditions (Not offset by demolition
costs) - Keep existing Absorption Chiller System
- Implement T5HO Light Design
- Reduced lighting fixture package amount by
300,000 - Reduced annual utility costs by 40,000
- Addition of light shelves would increase interior
day light and is worth considering - Emphasize contractors significant role on
- Waste Management
- Indoor Air Quality
- Education
37Final Recommendations
- Challenges
- Interior Walls might not meet sustainable
environmental needs to reduce waste during the
demolition phase - Geothermal Heat Pump will not be beneficial in
high electrical priced environment - Hard to investigate energy analysis with light
shelf due to limited energy modeling systems - A contractors role on a green project is
challenging to define, varying with the opinion
of different project team members
38Special Thanks
Toyota Facilities Director Sandy Smith AND ALL
OF THE TOYOTA PROJECT STAFF (MANY FROM TURNER
CONSTRUCTION)
- Faculty
- David Riley
- Dan Mattern
- Andy Lau
- Richard Mistrick
- Kenneth Davidson
- Moses Ling
- John Messner
- Industry Consultants
- Kim Pexton
- Chris Leyenberger
- Andy Pkacik
- Jim Blint
- Research Participants
- Family Friends
39Questions?
40Schedule
41Example of Interior Wall Calculations
42Mechanical Chiller System
43Mechanical Design Parameters
- ASHRAE Commercial Ground-Source Heat Pump
Engineering Manual 1995 - ASHRAE 62-2001, Ventilation for Acceptable Indoor
Air Quality - ASHRAE 90.1-1999, Energy Standard for Buildings
44Mechanical Design Criteria
45Mechanical Design Criteria
- Example ASHRAE 62 Table 2- Occupancy for
Office 7 ppl /1000SF 142.9 Outdoor Air
Requirement 20 CFM/person
46Mechanical Design Criteria
47Geothermal Cost
- Factors affecting cost if you were to use a
geothermal - Higher installation price
- Possible structural enhancement if equipment were
placed at the core of each floor - The reduction of Central Plant space (possible
elimination) - Must increase area slightly for main buildings
48Energy Costs
- Electrical
- Summer
- Peak .202
- Mid-Peak.111
- Off-Peak .0886
- Winter
- Mid-Peak.123
- Off-Peak .08975
- Demand 6.60 KW
- Demand 50 of top
- Peak17.95
- Off-Peak 2.70
49Energy Utility Costs for March 2003
- .1552/kwh46.38/mcf 5.57/mcf gas 18.7
- Source Energy User News
50LEED Energy Optimization
- Current LEED Energy Status as of March, 2003
51Lighting Info
- For T5HO
- LLF .752
- LLD .9 , LDD .87, BF .96