Title: Port Access Project: The Port of Miami Tunnel
1Port Access ProjectThe Port of Miami Tunnel
July 11, 2007
2Port AccessImportance of Port
- POM is top international cruise terminal, 10th
international cargo port based on containerized
shipments, and top seaport in Florida based on
dollar volume
- 20.7 billion in imports/exports
- 81,800 jobs
- 5 billion in wages
- 12 billion in economic output
3Port Access Change is Badly Needed!
- College students, faculty visitors at risk from
POM traffic - Federal judges see port-bound heavy vehicles as
major security risk - Overtown Park West residents want port traffic
off neighborhood streets - Upper reaches of downtown being developed
4Port AccessExisting truck routesthrough
Downtown Miami
- Trucks currently travel through NE 1 and 2nd
Avenue - Must go through 6 to 7 signals inbound and
outbound
5Port AccessTruck traffic will increase
- Nearly 5,500 trucks buses travel to/from POM
through downtown streets - By 2030, estimated truck traffic
will nearly double
6Port AccessYears of Planning
- Since 1979, improved access to Port of Miami seen
as necessity - Nearly every option explored
- In 1989, FDOT analyzed eight alternatives in
Project Development Environmental (PD E) study
7Port AccessOption Selected
- Tunnel under main channel of Government Cut
- Roadway work on Dodge and Watson Islands
- MacArthur Causeway Bridge widening
8Port AccessBuilding the Tunnel
- Involves specially-constructed Tunnel Boring
Machine approx. 42 ft. high - TBM consists of cutter head and trailing support
gear - Excavation will take just over one year6 months
in each direction
9Port Access FDOT Procurement Schedule
- December 5, 2005 Industry Forum
- February 17, 2006 Releases Request for
Qualifications - April 12, 2006 Receives Statement of
Qualifications from potential bidders - April 28, 2006 Announces short-list of bidders
- November 1, 2006 Publishes Request for Proposals
- March 5, 2007 Receives proposals from 3
short- listed bidders - May 2, 2007 Best Value Proposal named - MAT
- Next Step MAT (Miami Access Tunnel) Contract
Execution
10Port AccessPPP Overview
- Concessionaire will design, build, finance,
operate and maintain tunnel - Proposals received on March 5, 2007
- Best Value Proposal named on May 2, 2007
- Miami Access Tunnel Team was identified under
Notice of Intent to Award, subject to local
funding
11Port AccessTunnel PPP Agreement
- 35-year agreement between FDOT concessionaire
- FDOT begins availability payments once tunnel
opens, adjusted for inflation - Estimated to be 2012
- Payment subject to reduction if tunnel not
operational during required hours - Tunnel will be returned to FDOT in first-class
condition at end of contract
12Port Access Project Capital Cost
- Top Ranked Proposal capital and related cost -
665 million - 150 million for risk reserve for geology risk
and related items - 50 million for project inspection
- Total capital cost - 865 million (FDOT cost
estimate at 1.2 billion)
13Port Access Construction Schedule
- Upon execution of Concession Agreement, FDOT will
issue a Notice to Proceed design - MAT will have nine-month period to begin
construction - In RFP response, MAT stipulated a 47-month
construction schedule - MAT must meet defined construction period
14Port Access Construction Schedule
5-Year Construction Period beginning in 2008
15Port AccessFunding the POMT
- FDOT contributing 50 of capital cost (432.5
million) from Strategic Intermodal System (SIS)
funds - Local partners must match capital costs
- FDOT funding tunnel Operations Maintenance from
statewide maintenance funds (about 200 million
over 30 years)
16Port AccessFunding the POMT
- Cash Flow
- 100 million during construction
- 350 million upon POMT completion
- Remaining in annual availability payment
- Covers both remaining capital and annual
operations and maintenance costs - Proposal at 33 million in 2007 dollars (FDOT
estimate at 68 million) - Amount will adjust based on annual inflation
17Port Access Benefits
- Provide direct connection from POM to interstate
highways from I-395 via Watson Island - Maintain POM as Countys second-leading economic
generator - Relieve congestion from downtown streets
- Keep port competitive
18Port Access Public Support
- Miami Herald encourages County Commission to
endorse FDOTS plan for port tunnel
- Public officials local business owners
recognize tunnel is essential
19Port Access Project Website
www.portofmiamitunnel.com
20Port AccessA Challenge we can meet!