Title: Fostering Renewable Energy Sources in Chile: A crossroad approach between legal and financial incent
1Fostering Renewable Energy Sources in Chile A
cross-road approach between legal and financial
incentives
- UNFCCC Workshop on Innovative Options for
Technology Transfer Financing
- Bonn, 20-21 October 2005
Orlando Jiménez (Ph.D.) Deputy Head, Investment a
nd Development Division Economic Development Agen
cy (CORFO)
CHILE
2Presentations Summary
- Context
- The Chilean Electric Market
- The amendments of the Electric law (2004 and
2005)
- The CORFOs Agenda on Renewable Energies and the
CDM
3Energy Background
Chile has not achieved (and wont in the near
future) a decoupling between economic growth and
energy consumption
4The Electric sector in Chile (1/3)
- Total installed capacity for grid connected
systems 11.626 MW (source CNE 2004)
- Four main electric systems SING, SIC, Aysen and
Magallanes. SING (29) and SIC (70) concentrates
99 of total installed capacity.
- Generation, transmission and distribution
operated by different enterprises to avoid
vertical integration (legal requirement)
- Generation market highly concentrated and shared
by 7 large companies. Small companies account for
only 10 of installed capacity.
- Dispatch according to the rule of the least
operation marginal cost.
- Energy (spot market) paid according to the
operation marginal cost of the whole system
- 95 coverage for rural households demand, highly
subsidized for investment and operation.
5Electric sector (2/3)
No interconnection between systems.
Source Comisión Nacional de Energía, 2004
6Electric sector (3/3) Central Interconected
System
Evolution 1992 - 2001
SIC annual gross electric generation
Drought
Source CDEC SIC
7Situation of SM sized Non-Conventional Renewable
Energy Projects
- By default legal discrimination against small-and
medium-sized projects.
- Historical context
- Loose planning approach
- Very little contribution nation-widewhy? Because
there wasnt any market for them! Just, so many
entry barriers
- Higher investment costs
- Difficulties to connect to the grid (access to
the discretion of the grid owner)
- This situation created a de-facto system of
discrimination against SM sized projects. This
monopsonic relationship led to far below market
prices paid to the generator. - Hookup toll fee for small generators
- No recognition of backup generation capacity
8Electric crisis
- 1998 Severe drought in central and southern
Chile affecting SIC system (70 of installed
capacity 85 of population). Electric supply
shortages during 1998 and early 1999, affecting
industries and households. - 2004 and 2005 Natural Gas supply reduction from
Argentina affecting both SING and SIC systems. No
shortage on electric supply recorded but spot
prices rose (4 to 5 times) due to generation with
diesel.
9Electric Law Amendments (Law 19.940, March 2004)
Article 91 (1/3)
Regardless its size, generation technology and
energy source, the generator is entitlement to
- Sell its energy to the system at the spot market
price.
- Distribution grid owner is responsible for doing
the additional work needed to connect the new
facility and the generator pays the costs.
- Price paid for installed capacity or the backup
capacity during peaks of demand.
- Possibility to sell to independent clients, to
the distributor and to the spot market.
- No connection toll fee (fee (9 and
- Generators (all size) are free to establish
energy supply contracts with any consumer with
power demand over 500 kW. Before the law, this
size was 2.000 kW - ABOVE ALL IT CREATED CASH FLOW (Long-term
incentive) for the projects.
10Impacts of the Law 19.940
-
- The operation in the spot market, the
recognition of installed capacity (backup
capacity during peaks), and the actual
possibility to sell the energy improved the
profitability of renewable energy projects,
making the most out of them.
11CORFOs Actions to Foster the Renewable Energy
Sector
- Feasibility Fund (1,5 US million annually)
- Call for tenders on Renewable Energy projects
- Launched on July 2005. 77 developers presented
proposals. Currently in the assessment process to
allocate resources to the best ones.
- Up to US 50.000 per project
- Matching fund nature of the scheme has a
filtering effect
- Assessment criteria Aimed to buy certainties on
the profitability and the risk of the projects.
- Use the CDM to improve the financial conditions
of the projects.
- Carbon Market Program
- Launched in June 2005, intended to support
projects in order to overcome main barriers
identified.
12CORFOs call for tenders (1/4)
Portfolio so far (out of the 77)
13CORFOs call for tenders By source (2/4)
14CORFOs for tenders Investment by source(3/4)
15CORFOs call for tenders Generation (4/4)
16Thank you!!
17Assessment Criteria
18The program for rural electrification
- The government invests when private investment is
not profitable, but social economic assessment is
positive
- The investment decision is decentralized. Each
region decide where to do the electrification
projects.
- Operation, maintenance and administration costs
are paid by users through a fee.
- Up to day, 95 of coverage for rural households.
- First option for electrification is connection to
the grid. When this is not economically feasible,
in situ generation is used.
19Renewable Energies in Chile and Europa
Although it is very likely that globally, the
renewable share will diminish, comparatively, it
is highly probably that the relative share for
non-conventional renewable will grow.
Source CNE, CDECs and EU Directive 2001/77/CE
20CDM situation in Chile (1/3)
- DNA established in May 2003
- First project portfolio (20 projects) in
September 2003
- 30 projects presented at Carbon Expo I, on June
2004
- 47 projects presented at Carbon Expo II, on May
2005
- Small Hydro 17
- Eolic 3
- Biomass 5
- Cogeneration 3
- Transport 2
- Landfill (Biogas) 7
- Reforestation 4
- Others 6
21CDM situation in Chile (2/3)
- 11 Endorsement letters given by the DNA
- 4 registered projects (3 Agrosúper, 1 Nestlé)
- 3 methodologies developed and approved, 2 other
in process
- 3 projects in validation process (using already
approved methodologies)
- 7 projects that have already sold CERs (3
Agrosúper, Nestlé, Watts, Chacabuquito,
Hornitos). Main buyers from PCF, Japan and
Canada. - Source Conama, Prochile and UNFCCC
22CDM situation in Chile (3/3)
- Small- and medium-sized projects face several
barriers
- Transaction costs
- Financial barriers
- Energy Market barriers
- Information Asymmetries
- CDM Market barriers (most projects account for
less than 20.000 tons of CO2 eq. per year)
- Methodologys development
Currently, many small- and medium-sized projects
have not been able to overcome some of these bar
riers
23Electric Law (Nº 19.940) Special rules for
generation facilities whose installed capacity is
less than 9 MW (2/3)
- Generators must accomplish quality and safety
standards.
- Access to grid is guaranteed in order to bring
the energy to the system.
Right to be connected to distribution grids
- Predictable Market Prices to assess expected
profitability for projects.
- Reduce the variability of the spot marginal
costs, stabilizing projects income.
Selling energy at the marginal stabilized cost
CDEC Dispatch and coordination with special
procedures
- Fixed cost reduction for Systems Coordination,
Control and Administration for small generators.
24Electric Law Special rules for generation
smaller than 9 MW (3/3)
- Distribution Grid Owner is responsible for doing
the additional work needed to connect the new
facility. Small generator is responsibly for the
connecting costs. - Economically Recognized benefits of small
generators connected at the distribution levels
(avoiding transmission losses)
Additional Investment to secure connecting of
small generation and Connecting Costs
25 26(No Transcript)