Fostering Renewable Energy Sources in Chile: A crossroad approach between legal and financial incent - PowerPoint PPT Presentation

1 / 26
About This Presentation
Title:

Fostering Renewable Energy Sources in Chile: A crossroad approach between legal and financial incent

Description:

Fostering Renewable Energy Sources in Chile: A cross-road approach between legal ... Chile has not achieved (and won't in the near future) a decoupling between ... – PowerPoint PPT presentation

Number of Views:118
Avg rating:3.0/5.0
Slides: 27
Provided by: unf9
Category:

less

Transcript and Presenter's Notes

Title: Fostering Renewable Energy Sources in Chile: A crossroad approach between legal and financial incent


1
Fostering Renewable Energy Sources in Chile A
cross-road approach between legal and financial
incentives
  • UNFCCC Workshop on Innovative Options for
    Technology Transfer Financing
  • Bonn, 20-21 October 2005

Orlando Jiménez (Ph.D.) Deputy Head, Investment a
nd Development Division Economic Development Agen
cy (CORFO)
CHILE
2
Presentations Summary
  • Context
  • The Chilean Electric Market
  • The amendments of the Electric law (2004 and
    2005)
  • The CORFOs Agenda on Renewable Energies and the
    CDM

3
Energy Background
Chile has not achieved (and wont in the near
future) a decoupling between economic growth and
energy consumption
4
The Electric sector in Chile (1/3)
  • Total installed capacity for grid connected
    systems 11.626 MW (source CNE 2004)
  • Four main electric systems SING, SIC, Aysen and
    Magallanes. SING (29) and SIC (70) concentrates
    99 of total installed capacity.
  • Generation, transmission and distribution
    operated by different enterprises to avoid
    vertical integration (legal requirement)
  • Generation market highly concentrated and shared
    by 7 large companies. Small companies account for
    only 10 of installed capacity.
  • Dispatch according to the rule of the least
    operation marginal cost.
  • Energy (spot market) paid according to the
    operation marginal cost of the whole system
  • 95 coverage for rural households demand, highly
    subsidized for investment and operation.

5
Electric sector (2/3)
No interconnection between systems.
Source Comisión Nacional de Energía, 2004
6
Electric sector (3/3) Central Interconected
System
Evolution 1992 - 2001
SIC annual gross electric generation
Drought
Source CDEC SIC
7
Situation of SM sized Non-Conventional Renewable
Energy Projects
  • By default legal discrimination against small-and
    medium-sized projects.
  • Historical context
  • Loose planning approach
  • Very little contribution nation-widewhy? Because
    there wasnt any market for them! Just, so many
    entry barriers
  • Higher investment costs
  • Difficulties to connect to the grid (access to
    the discretion of the grid owner)
  • This situation created a de-facto system of
    discrimination against SM sized projects. This
    monopsonic relationship led to far below market
    prices paid to the generator.
  • Hookup toll fee for small generators
  • No recognition of backup generation capacity

8
Electric crisis
  • 1998 Severe drought in central and southern
    Chile affecting SIC system (70 of installed
    capacity 85 of population). Electric supply
    shortages during 1998 and early 1999, affecting
    industries and households.
  • 2004 and 2005 Natural Gas supply reduction from
    Argentina affecting both SING and SIC systems. No
    shortage on electric supply recorded but spot
    prices rose (4 to 5 times) due to generation with
    diesel.

9
Electric Law Amendments (Law 19.940, March 2004)
Article 91 (1/3)
Regardless its size, generation technology and
energy source, the generator is entitlement to
  • Sell its energy to the system at the spot market
    price.
  • Distribution grid owner is responsible for doing
    the additional work needed to connect the new
    facility and the generator pays the costs.
  • Price paid for installed capacity or the backup
    capacity during peaks of demand.
  • Possibility to sell to independent clients, to
    the distributor and to the spot market.
  • No connection toll fee (fee (9 and
  • Generators (all size) are free to establish
    energy supply contracts with any consumer with
    power demand over 500 kW. Before the law, this
    size was 2.000 kW
  • ABOVE ALL IT CREATED CASH FLOW (Long-term
    incentive) for the projects.

10
Impacts of the Law 19.940
  • The operation in the spot market, the
    recognition of installed capacity (backup
    capacity during peaks), and the actual
    possibility to sell the energy improved the
    profitability of renewable energy projects,
    making the most out of them.

11
CORFOs Actions to Foster the Renewable Energy
Sector
  • Feasibility Fund (1,5 US million annually)
  • Call for tenders on Renewable Energy projects
  • Launched on July 2005. 77 developers presented
    proposals. Currently in the assessment process to
    allocate resources to the best ones.
  • Up to US 50.000 per project
  • Matching fund nature of the scheme has a
    filtering effect
  • Assessment criteria Aimed to buy certainties on
    the profitability and the risk of the projects.
  • Use the CDM to improve the financial conditions
    of the projects.
  • Carbon Market Program
  • Launched in June 2005, intended to support
    projects in order to overcome main barriers
    identified.

12
CORFOs call for tenders (1/4)
Portfolio so far (out of the 77)
13
CORFOs call for tenders By source (2/4)
14
CORFOs for tenders Investment by source(3/4)
15
CORFOs call for tenders Generation (4/4)
16
Thank you!!
17
Assessment Criteria
18
The program for rural electrification
  • The government invests when private investment is
    not profitable, but social economic assessment is
    positive
  • The investment decision is decentralized. Each
    region decide where to do the electrification
    projects.
  • Operation, maintenance and administration costs
    are paid by users through a fee.
  • Up to day, 95 of coverage for rural households.
  • First option for electrification is connection to
    the grid. When this is not economically feasible,
    in situ generation is used.

19
Renewable Energies in Chile and Europa
Although it is very likely that globally, the
renewable share will diminish, comparatively, it
is highly probably that the relative share for
non-conventional renewable will grow.
Source CNE, CDECs and EU Directive 2001/77/CE
20
CDM situation in Chile (1/3)
  • DNA established in May 2003
  • First project portfolio (20 projects) in
    September 2003
  • 30 projects presented at Carbon Expo I, on June
    2004
  • 47 projects presented at Carbon Expo II, on May
    2005
  • Small Hydro 17
  • Eolic 3
  • Biomass 5
  • Cogeneration 3
  • Transport 2
  • Landfill (Biogas) 7
  • Reforestation 4
  • Others 6

21
CDM situation in Chile (2/3)
  • 11 Endorsement letters given by the DNA
  • 4 registered projects (3 Agrosúper, 1 Nestlé)
  • 3 methodologies developed and approved, 2 other
    in process
  • 3 projects in validation process (using already
    approved methodologies)
  • 7 projects that have already sold CERs (3
    Agrosúper, Nestlé, Watts, Chacabuquito,
    Hornitos). Main buyers from PCF, Japan and
    Canada.
  • Source Conama, Prochile and UNFCCC

22
CDM situation in Chile (3/3)
  • Small- and medium-sized projects face several
    barriers
  • Transaction costs
  • Financial barriers
  • Energy Market barriers
  • Information Asymmetries
  • CDM Market barriers (most projects account for
    less than 20.000 tons of CO2 eq. per year)
  • Methodologys development

Currently, many small- and medium-sized projects
have not been able to overcome some of these bar
riers
23
Electric Law (Nº 19.940) Special rules for
generation facilities whose installed capacity is
less than 9 MW (2/3)
  • Generators must accomplish quality and safety
    standards.
  • Access to grid is guaranteed in order to bring
    the energy to the system.

Right to be connected to distribution grids
  • Predictable Market Prices to assess expected
    profitability for projects.
  • Reduce the variability of the spot marginal
    costs, stabilizing projects income.

Selling energy at the marginal stabilized cost
CDEC Dispatch and coordination with special
procedures
  • Fixed cost reduction for Systems Coordination,
    Control and Administration for small generators.

24
Electric Law Special rules for generation
smaller than 9 MW (3/3)
  • Distribution Grid Owner is responsible for doing
    the additional work needed to connect the new
    facility. Small generator is responsibly for the
    connecting costs.
  • Economically Recognized benefits of small
    generators connected at the distribution levels
    (avoiding transmission losses)

Additional Investment to secure connecting of
small generation and Connecting Costs
25

26
(No Transcript)
Write a Comment
User Comments (0)
About PowerShow.com