Status Report on the Design and Fabrication of 29 quads for ATF2 - PowerPoint PPT Presentation

About This Presentation
Title:

Status Report on the Design and Fabrication of 29 quads for ATF2

Description:

Status Report on the Design and Fabrication of 29 quads for ATF2 ... China to make new drawings and fabricate 29 quads (1 spare) by March 31st 2006. ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 7
Provided by: cher66
Category:

less

Transcript and Presenter's Notes

Title: Status Report on the Design and Fabrication of 29 quads for ATF2


1
Status Report on the Design and Fabrication of 29
quads for ATF2
  • By Cherrill Spencer, SLAC, for ILC-BDS weekly
    meeting on 22nd November 2005

2
ATF2 quadrupoles QEA-D32T180 Activity from
June September 2005
  • Are 8 quadrupoles in the extension of the ATF
    extraction line
  • Are 6 quads in matching section of ATF2 beamline
  • Are 14 quads in final focus section of ATF2 (
    aside from QF1QD0)
  • Decided back in June these 3 sets could all be
    made from same design.
  • Decided an existing KEK quad called the TOKIN
    3390 (QB4 style) would be basis of the design
    for the 28 ATF2 quads listed above.
  • Contract signed in early July with the Magnet
    Shop of the Institute of High Energy Physics
    (IHEP) in Beijing, China to make new drawings and
    fabricate 29 quads (1 spare) by March 31st 2006.
  • In July Spencer wrote very detailed
    specifications for this quad, new name
    QEA-D32T180. Defined precisely the type of
    materials to be used, the fabrication processes
    to be followed and the tolerances to be met. Used
    USA and Japanese standards. Sent some top
    assembly drawings of TOKIN 3390 to IHEP.
  • August-September IHEP drew new drawings for all
    parts and assemblies. IHEP and Spencer negotiated
    substitute Chinese materials to be used where
    Spencer could qualify them to her satisfaction.

3
ATF2 quadrupoles QEA-D32T180 Activity from
September- December 2005
  • Late September new drawing package released by
    IHEP for review. Formal review held by marathon
    video-conference on 29/ 30th Sept.
  • See examples of new drawings (not yet final) on
    next slides.
  • October-November Spencer continues negotiating
    changes in fabrication processes and materials to
    accommodate capabilities of IHEP magnet shop and
    availability of materials, so tight schedule can
    be met.
  • Mid-Late October IHEP designing and fabricating
    coil winding forms
  • October-Late November IHEP machining first
    magnets 4 steel core pieces
  • Late November hollow copper conductor due to
    arrive from Finland
  • Early December Wind and pot first 4 coils
  • Early Dec. finish machining 1st magnets
    poletips with Electric Discharge Machine
  • December 8th 14th Spencer will visit Magnet
    Shops at IHEP to observe coil winding, potting,
    core assembly and first magnets full assembly.
    Core will be measured with CMM and other QC tools
    to check tight tolerances are met. Coils will be
    tested.
  • December onwards if 1st magnet passes all tests
    Spencer will allow rest of magnets to be
    fabricated. Magnetic measurements will start in
    mid-January.

4
3. Coil manufacturing
NOT FINAL COIL DRAWING DO NOT USE
  • 3 ). Detail of coil

5
4. General Assembly
  • 1). Overview of general assembly QEA-D32T180.

NOT FINAL DRAWING. DO NOT USE
32mm bore 180mm core length 47 turns per water
cooled coil Max gradient 55 T/m
6
5. Flow Chart for Manufacture