Status Report on the Design, Fabrication and Measurement of 29 quads for ATF2 - PowerPoint PPT Presentation

1 / 15
About This Presentation
Title:

Status Report on the Design, Fabrication and Measurement of 29 quads for ATF2

Description:

Status Report on the Design, Fabrication and Measurement of 29 quads for ATF2 ... history to-date of the design, fabrication and measurement of these quadrupoles ... – PowerPoint PPT presentation

Number of Views:69
Avg rating:3.0/5.0
Slides: 16
Provided by: cher66
Category:

less

Transcript and Presenter's Notes

Title: Status Report on the Design, Fabrication and Measurement of 29 quads for ATF2


1
Status Report on the Design, Fabrication and
Measurement of 29 quads for ATF2
  • By Cherrill Spencer, SLAC, for ATF2 project
    meeting on SATURDAY 4th February 2006

2
4. General Assembly
  • 1). Overview of general assembly QEA-D32T180.

NOT FINAL DRAWING. DO NOT USE
32mm bore 180mm core length 48 turns per water
cooled coil Max gradient 55 T/m
3
ATF2 quadrupoles QEA-D32T180
  • Are 8 quadrupoles in the extension of the ATF
    extraction line
  • Are 6 quads in matching section of ATF2 beamline
  • Are 14 quads in final focus section of ATF2 (
    aside from QF1QD0)
  • Decided an existing KEK quad called the TOKIN
    3390 (QB4 style) would be basis of the design
    for the 28 ATF2 quads listed above.
  • See R. Sugaharas talk to this meeting for
    summary of history to-date of the design,
    fabrication and measurement of these quadrupoles
  • Spencers activities during trip to IHEP, 6th
    -14th Dec 05
  • Observe main trim coil winding forms coil
    winding potting shops
  • Inspect first 4 wound trim coils size,
    resistance and inductance OK
  • Observe the brand new Electric Discharge Machine
    (EDM)
  • Inspect 4 quadrants of the first quads steel
    core before and after EDMing of the
    hyperbolic-shaped poletips
  • Core quadrants assembled and toleranced
    dimensions near poletips measured with micrometer
  • All toleranced dimensions are within tolerance
  • First core sent to CMM for measurement of
    hyperbolic poletips

4
QEA-D32T180 COIL DRAWING- drawn by IHEP
NOT FINAL COIL DRAWING DO NOT USE Coils have 48
turns of 6mm square Copper conductor
5
Trim coil winding form (left) and main coil
winding form set-up on winding machines
6
IHEP film potting apparatus (left) Dr Xuwen Dai
measuring dimensions of first trim coils
7
First core after all machining finished , in the
IHEP Machine Shop. 9th Dec 2005
8
First main coil, before trim added, before
pottingEarly January 2006
9
First main coil after trim added and both potted
together. 9th January 2006
G10 fillers where turns decrease
Epoxy has no Al2O3 filler and so is transparent.
Trim coil
Ground wrap has become transparent through the
potting process
Dimensions of first coil meet tolerances.
Resistance as expected. A 2.5mm ball was pushed
through the conductor, indicating the water
passage is clear.
Two 1st coils been placed over 2 core quadrants-
everything fits OK.
10
First coil package sliced so we could inspect
quality of winding and potting
Conclusions Main and trim coil winding is
satisfactory. Potting process (with wrapped film
to contain the potting epoxy, no mould) works
very well. All dimensions to spec.
11
First fully assembled ATF2 quadrupole, 17th
January 2006
12
First ATF2 quad on measuring stand at IHEP.
Rotating coil being set-up. 19th January 06
13
ATF2 quad gradient versus current measured with
Hall Probe saturated as expected
14
Summary of prelim measurement results on first
ATF2 quad at IHEP
  • Magnet measured up to 150 amps. Cooling is fine.
  • Effective length longer than predicted by usual
    rule of thumb and it decreases by 0.47 from 50
    to 135 amps.
  • Average effective length over all currents
    19.849 cm
  • Quad is 99.27 efficient at 50 amps
  • Quad is 97.32 efficient at 100 amps
  • Quad is 85.43 efficient at 135 amps
  • With actual effective length and max K1 2.5 need
    gradient of 54.76T/m, which is achieved with
    136.2 amps
  • Half the quads will need PS that go to 150 amps

15
First quad measured with Hall probe By values
along X at Z center
Shape of field looks good. Multipoles will be
measured with new rotating coil next week (6-10
Feb) and compared against tolerances. Standardizat
ion procedures will be finalized next week.
Integrated strength versus current data what
can ATF2 PS control system deal with? Each magnet
has own polynomial or not?
Write a Comment
User Comments (0)
About PowerShow.com