Title: ERCOT Zonal Market in Theory and Practice
1ERCOT Zonal Market in Theory and Practice
- Eric S. Schubert
- Market Oversight Division
- Public Utility Commission of Texas
- December 10, 2004
2Definition of Zonal and Nodal Prices (1)
- Nodal Each point has its own energy price
- Zonal One energy price across a large area
- Substantive Rule 25.501 (Texas Nodal)
- Resources would have nodal prices
- Load would have zonal prices
3Definition of Zonal and Nodal Prices (2)
Zonal
Nodal
NE
N
W
H
S
Commercially Significant Constraint
4Summary of Presentation
- Which model to use zonal or nodal?
- Basic assumptions of zonal model
- Elements of original ERCOT zonal market design
- Experience of operating zonal model
- Possible remedies to current problems
5Which Model to Use Zonal or Nodal? (1)
- Debate in ERCOT and SPP in 1999-2000
- How much of the network needs to be modeled?
- Theoretical rather than empirical
- Working wholesale markets at the time
- Nodal PJM (1999), NYISO (1999)
- Zonal CAISO, NEPOOL
6Which Model to Use Zonal or Nodal? (2)
- Zonal Min ISO
- Market decisions have small impact on reliability
- Decentralized commitment and dispatch process
- Nodal Max ISO
- Market decisions have large impact on reliability
- Centralized commitment and dispatch process
- Is the transmission grid more like life in
Manhattan or West Texas?
7ERCOT Chooses Zonal Market Design
- Zonal was an easier starting point in 2001
- ERCOT was moving to a single control area
- ERCOT never had been a power pool
- Gave QSEs ability to manage their plants close to
real-time - Clearing prices seen in the bid stack
- Market participants, not ISO, have large range to
make decisions
8Basic Assumptions of Zonal Model
- Local congestion is random and infrequent
- Zonal prices are sufficient for siting resources
- Adjusting the number of CSCs and load zones will
be systematic and timely - Market decisions have a small impact on
reliability - Decentralized dispatch process works
- Decentralized unit commitment works
9Elements of Original Zonal Model (1)QSE Bids
and Offers
- Balanced schedules that bind a few hours before
real-time deployment - Portfolio offer curves
- ISO RT balancing energy market
- Must offer requirement in the form of OOMC and
OOME to meet immediate reliability needs
10Elements of Original Zonal Model (2)Day-Ahead
Energy Market
- Bilateral market in DA energy
- ERCOT procures residual AS in DA
- No centralized unit commitment
11Elements of Original Zonal Model (3)Settlement
and Local Congestion
- Direct assignment of congestion rents
- Only on key lines (CSCs)
- Rest is uplifted
- Commission had targeted limits on uplift
- Directly assign congestion rents on all lines if
congestion is significant - In 2001, Commission set the significant
threshold level at 20 million
12Elements of Original Zonal Model (4)Settlement
and Zones
- Load zones not stable by design
- CSCs are determined yearly
- ERCOT stakeholders determine CSCs
- Thresholds on congestion costs determine
candidates - Load flows studies by ERCOT look at potential
zonal boundaries - New CSCs must produce zones that are
sufficiently competitive - Flowgates (TCRs) as hedges for energy flows
between zones
13Elements of Original Zonal Model (5)Entry and
Exit of Resources
- Expedited permitting of resources
- Resource Adequacy
- No explicit resource adequacy mechanism
- Commission reviewing issue (Project 24255)
- Reliability Must-Run (RMR) units Substantive
Rule 25.502 - Load Resources
- Loads Acting as Resources
- BULs
14Elements of Original Zonal Model
(6)Transmission and Retail
- Socialized cost of transmission grid
- Statute Postage stamp payment of TCOS
- Commission Generation interconnection
- Retail market
- Retailers unbundled from transmission and
generation - Zonal settlement of load
15Experience of ERCOT Zonal Model2001-2004
- Local congestion is systematic and frequent
(2001-2002) - Inefficient siting dispatch of resources (2002)
- Adjusting number of CSCs and load zones is
problematic (2003) - Portfolio dispatch hinders real-time operations
(2003-2004) - Decentralized unit commitment may be inefficient
(2004)
16Local Congestion is Systematic and Frequent
(2001-2002)
- Zonal congestion August 2001
- Local congestion March 2002
- Local congestion through August 2004
17Inefficient Siting and Dispatch of Resources
(2002)
- Uneconomic and confusing dispatch
- Cheaper units OOMEd or restricted
- Inc and Dec instructions at same bus
- Lack of transparency in the market
- Siting generation
- McCamey (Wind rush)
- Generator pocket in northeast part of ERCOT
18Adjusting CSCs and Load Zones is Problematic
(2003)
- Annual adjustments only
- Slow and political process
- North-Houston (STP goes down)
- DFW area (OOMC uplift)
19Portfolio Dispatch Hinders Real-Time Operations
(2003-2004)
- Portfolio ramp rates complicate dispatch
- ERCOT has to guess how QSEs will deploy their
resources - Portfolio system can be gamed
20Decentralized Unit Commitment May Be Inefficient
(2004)
- Oversupply of capacity operating at any given
time - Suppliers fail to offer their excess energy in
the balancing energy market - The market can suffer from an inefficient
undersupply of committed capacity.
21Potential Remedies for Five Problems in ERCOT
Wholesale Market
- Direct assignment of congestion rents on all
transmission lines - Resource-specific offer curves
- Centralized unit commitment in day-ahead market
22Questions?