ERCOT Zonal Market in Theory and Practice - PowerPoint PPT Presentation

1 / 22
About This Presentation
Title:

ERCOT Zonal Market in Theory and Practice

Description:

... dispatch process works. Decentralized unit commitment works ... Direct assignment of congestion rents on all transmission lines. Resource-specific offer curves ... – PowerPoint PPT presentation

Number of Views:84
Avg rating:3.0/5.0
Slides: 23
Provided by: eschu
Category:

less

Transcript and Presenter's Notes

Title: ERCOT Zonal Market in Theory and Practice


1
ERCOT Zonal Market in Theory and Practice
  • Eric S. Schubert
  • Market Oversight Division
  • Public Utility Commission of Texas
  • December 10, 2004

2
Definition of Zonal and Nodal Prices (1)
  • Nodal Each point has its own energy price
  • Zonal One energy price across a large area
  • Substantive Rule 25.501 (Texas Nodal)
  • Resources would have nodal prices
  • Load would have zonal prices

3
Definition of Zonal and Nodal Prices (2)
Zonal
Nodal
NE
N
W
H
S
Commercially Significant Constraint
4
Summary of Presentation
  • Which model to use zonal or nodal?
  • Basic assumptions of zonal model
  • Elements of original ERCOT zonal market design
  • Experience of operating zonal model
  • Possible remedies to current problems

5
Which Model to Use Zonal or Nodal? (1)
  • Debate in ERCOT and SPP in 1999-2000
  • How much of the network needs to be modeled?
  • Theoretical rather than empirical
  • Working wholesale markets at the time
  • Nodal PJM (1999), NYISO (1999)
  • Zonal CAISO, NEPOOL

6
Which Model to Use Zonal or Nodal? (2)
  • Zonal Min ISO
  • Market decisions have small impact on reliability
  • Decentralized commitment and dispatch process
  • Nodal Max ISO
  • Market decisions have large impact on reliability
  • Centralized commitment and dispatch process
  • Is the transmission grid more like life in
    Manhattan or West Texas?

7
ERCOT Chooses Zonal Market Design
  • Zonal was an easier starting point in 2001
  • ERCOT was moving to a single control area
  • ERCOT never had been a power pool
  • Gave QSEs ability to manage their plants close to
    real-time
  • Clearing prices seen in the bid stack
  • Market participants, not ISO, have large range to
    make decisions

8
Basic Assumptions of Zonal Model
  • Local congestion is random and infrequent
  • Zonal prices are sufficient for siting resources
  • Adjusting the number of CSCs and load zones will
    be systematic and timely
  • Market decisions have a small impact on
    reliability
  • Decentralized dispatch process works
  • Decentralized unit commitment works

9
Elements of Original Zonal Model (1)QSE Bids
and Offers
  • Balanced schedules that bind a few hours before
    real-time deployment
  • Portfolio offer curves
  • ISO RT balancing energy market
  • Must offer requirement in the form of OOMC and
    OOME to meet immediate reliability needs

10
Elements of Original Zonal Model (2)Day-Ahead
Energy Market
  • Bilateral market in DA energy
  • ERCOT procures residual AS in DA
  • No centralized unit commitment

11
Elements of Original Zonal Model (3)Settlement
and Local Congestion
  • Direct assignment of congestion rents
  • Only on key lines (CSCs)
  • Rest is uplifted
  • Commission had targeted limits on uplift
  • Directly assign congestion rents on all lines if
    congestion is significant
  • In 2001, Commission set the significant
    threshold level at 20 million

12
Elements of Original Zonal Model (4)Settlement
and Zones
  • Load zones not stable by design
  • CSCs are determined yearly
  • ERCOT stakeholders determine CSCs
  • Thresholds on congestion costs determine
    candidates
  • Load flows studies by ERCOT look at potential
    zonal boundaries
  • New CSCs must produce zones that are
    sufficiently competitive
  • Flowgates (TCRs) as hedges for energy flows
    between zones

13
Elements of Original Zonal Model (5)Entry and
Exit of Resources
  • Expedited permitting of resources
  • Resource Adequacy
  • No explicit resource adequacy mechanism
  • Commission reviewing issue (Project 24255)
  • Reliability Must-Run (RMR) units Substantive
    Rule 25.502
  • Load Resources
  • Loads Acting as Resources
  • BULs

14
Elements of Original Zonal Model
(6)Transmission and Retail
  • Socialized cost of transmission grid
  • Statute Postage stamp payment of TCOS
  • Commission Generation interconnection
  • Retail market
  • Retailers unbundled from transmission and
    generation
  • Zonal settlement of load

15
Experience of ERCOT Zonal Model2001-2004
  • Local congestion is systematic and frequent
    (2001-2002)
  • Inefficient siting dispatch of resources (2002)
  • Adjusting number of CSCs and load zones is
    problematic (2003)
  • Portfolio dispatch hinders real-time operations
    (2003-2004)
  • Decentralized unit commitment may be inefficient
    (2004)

16
Local Congestion is Systematic and Frequent
(2001-2002)
  • Zonal congestion August 2001
  • Local congestion March 2002
  • Local congestion through August 2004

17
Inefficient Siting and Dispatch of Resources
(2002)
  • Uneconomic and confusing dispatch
  • Cheaper units OOMEd or restricted
  • Inc and Dec instructions at same bus
  • Lack of transparency in the market
  • Siting generation
  • McCamey (Wind rush)
  • Generator pocket in northeast part of ERCOT

18
Adjusting CSCs and Load Zones is Problematic
(2003)
  • Annual adjustments only
  • Slow and political process
  • North-Houston (STP goes down)
  • DFW area (OOMC uplift)

19
Portfolio Dispatch Hinders Real-Time Operations
(2003-2004)
  • Portfolio ramp rates complicate dispatch
  • ERCOT has to guess how QSEs will deploy their
    resources
  • Portfolio system can be gamed

20
Decentralized Unit Commitment May Be Inefficient
(2004)
  • Oversupply of capacity operating at any given
    time
  • Suppliers fail to offer their excess energy in
    the balancing energy market
  • The market can suffer from an inefficient
    undersupply of committed capacity.

21
Potential Remedies for Five Problems in ERCOT
Wholesale Market
  • Direct assignment of congestion rents on all
    transmission lines
  • Resource-specific offer curves
  • Centralized unit commitment in day-ahead market

22
Questions?
Write a Comment
User Comments (0)
About PowerShow.com