THE FAA Office of Dispute Resolution: Offering Assistance to the Procurement Community That Facilita - PowerPoint PPT Presentation

1 / 21
About This Presentation
Title:

THE FAA Office of Dispute Resolution: Offering Assistance to the Procurement Community That Facilita

Description:

A-76 Contests ADR: 31 days. A-76 Contests Adj: 138 days. Federal Aviation ... 4 Contests: Settled in ADR: 2 (50%) 131 Contract Disputes. Settled in ADR 113 (91 ... – PowerPoint PPT presentation

Number of Views:84
Avg rating:3.0/5.0
Slides: 22
Provided by: MTON94
Category:

less

Transcript and Presenter's Notes

Title: THE FAA Office of Dispute Resolution: Offering Assistance to the Procurement Community That Facilita


1
THE FAA Office of Dispute ResolutionOffering
Assistance to the Procurement Community That
Facilitates Quicker Resolution Avoidance of
Prourement Disputes
FAA Small Business Conference
  • Behn M. Kelly, Esq., Dispute Resolution Officer,
    ODRA

Behn M. Kelly, Esq. Dispute Resolution Officer
June 16, 2008
2
TOPICS
  • Overview of the FAAs Procurement Authority
  • Bid Protests Contract Disputes at the FAA and
    The Preference For Alternative Dispute Resolution
  • Types of Resolution Services Offered By the ODRA
  • ADR Outcomes in Bid Protests

3
The FAA Procurement System The Preference For
ADR
  • 2003 Vision 100--Century of Aviation
  • Reauthorization Act (Public Law 108-176),
  • Congress directed the ODRA to
  • use consensual ADR techniques to the
    maximum extent practicable, and to only use
    adjudication for a bid protest or contract
    dispute that is not addressed or resolved in
    ADR.

4
Preference For ADR (Contd.)
  • Under 49 U.S.C. 40110 (d), all bid protests and
    contract disputes that cannot be resolved through
    voluntary ADR shall be adjudicated by the
    Administrator through dispute resolution officers
    or special masters of the Federal Aviation
    Administration Office of Dispute Resolution for
    Acquisition.

5
The FAA Acquisition Management System (AMS)
  • Operational since 1996
  • Incorporates Policy favoring ADR
  • FAA Administrators Authority Delegations of
    Authority
  • Creation of the ODRA

6
Introduction to the ODRA
  • Impartial, independent of program offices and
    their counsel
  • Acts on behalf of and reports to the FAA
    Administrator
  • Resolves protests and contract disputes through
    two established regulatory processes
  • (1) Alternative Dispute Resolution
  • (2) Adjudication

7
ODRA MISSION
  • To attempt to resolve all disputes in ADR by
    providing the FAA and its contractors with
    dispute resolution services that are readily
    available, as well as more timely and less
    expensive than traditional disputes processes.

8
ODRA ADR Characteristics
  • PRIMARY METHOD OF RESOLUTION
  • HIGH RATE OF USE AND SUCCESS
  • PRE-DISPUTE / DISPUTE AVOIDANCE

9
ODRA ADR Characteristics (Contd.)
  • ADR emphasized explored in all cases
  • ODRA Initiated
  • Early intervention efforts
  • Parties retain choice on ADR neutral

10
ADR Services Offered
  • Types of ADR available at the ODRA
  • Neutral evaluation
  • Facilitative mediation
  • Binding arbitration
  • Hybrid of ADR Services

11
Creative ADR Case Management
  • Streamline Protest Adjudication Process
  • Resolve preliminary legal issues in ADR (e.g.
    suspension requests timeliness challenges)
  • Resolve housekeeping matterse.g., protective
    order concerns, request for deadline extensions
  • Focus discovery resolve discovery disputes
  • Parties can elect to pursue ADR concurrent with
    the bid protest adjudication

12
Bid Protest Settlements In ADR
  • Protest Withdrawals
  • Based on enhanced debriefings and evaluations
    offered in ADR by the Agency
  • 60 of Protest Settlements Withdrawals

13
Bid Protest Settlements In ADR
  • Agency Voluntary Corrective Action
  • 40 of Protest Settlements
  • Re-compete immediately or after base year or
    revise specs or permit revised offers
  • Compete in lieu of sole source
  • Capability demonstrations re future
    opportunities
  • Payment of Bid Proposal costs

14
Uses of ADRThe Pre-Dispute
  • Attempt to resolve issues between the Agency and
    a Contractor before a formal bid protest develops
  • Almost always successful
  • Requires consent of all parties
  • Parties generally receptive
  • earlier resolution and dispute avoidance
  • AMS requires CO to use ADR as part of contract
    management responsibilities.

15
ADR Time Frames
  • Comparison of the Average Durations of ADR vs.
    Adjudication
  • Protests ADR 24 days
  • Protests Adj 61 days
  • A-76 Contests ADR 31 days
  • A-76 Contests Adj 138 days

16
ADR STATISTICS
  • 500 Cases filed at the ODRA since 1996
  • 300 Protests
  • Settled in ADR 189 (65)
  • 81 Pre-Disputes
  • Settled in ADR 79 (97.5)
  • 4 Contests
  • Settled in ADR 2 (50)
  • 131 Contract Disputes
  • Settled in ADR 113 (91)

17
Out of the Box ADR Outcomes
  • Subcontracting arrangements have been negotiated
    between Protester and the Awardee based on
    perceived litigative risk
  • Division of the contract (including option years)
    has been negotiated between the Protester and the
    Awardee.

18
Out of the Box ADR Outcomes (3)
  • Negotiation of an ADR Settlement Agreement based
    on marketing considerations.
  • Mentor-Protégé arrangements.

19
ODRA WEBSITEOn the FAA Homepage
athttp//www.odra.faa.gov
  • Guide to ODRA ADR process
  • Sample forms, orders agreements
  • ADR Hyperlinks

20
TIPS From the ODRA
  • Get a clear understanding of the solicitation
    requirement and terms before you submit a
    proposal
  • Ask for a debriefing if you dont win the
    contract award
  • Whenever possible, attempt to resolve issues with
    the CO before filing at the ODRA
  • Start with the ODRAs pre-dispute process if
    possible
  • Know the ODRA Timeliness Rules (published on the
    website and at 14 C.F.R. Part 17)

21
ODRA TIMELINESS RULES