Communication Forum - PowerPoint PPT Presentation

1 / 57
About This Presentation
Title:

Communication Forum

Description:

Communication Forum – PowerPoint PPT presentation

Number of Views:52
Avg rating:3.0/5.0
Slides: 58
Provided by: robinel
Category:

less

Transcript and Presenter's Notes

Title: Communication Forum


1
Communication Forum 29th June 2004 Henry Gun-Why
Estates Management DL
2
Keckwick Lane
3
(No Transcript)
4
(No Transcript)
5
Keckwick Lane Ramp 10mph
6
(No Transcript)
7
(No Transcript)
8
(No Transcript)
9
Daresbury Express Way
  • Traffic Lights on the 5th July 2004 - further
    delays and disruption

10
(No Transcript)
11
(No Transcript)
12
(No Transcript)
13
Keckwick Lane nearly there
  • Apologies for inconvenience
  • Thanks to Steve Dobson, Mike Bailey, Christine
    Mills, Roy Arden and Hazel Harkins for managing
    the co-ordination at weekly meetings with Wates
    Construction.
  • Thanks for your patience

14
Reception Centre Progress
  • Principal Contractor Whites Building Services
  • Start on site Monday 22nd September 2003
  • Demolition w/c 6th October 2003
  • Time Capsules
  • Security Systems transfer being arranged with
    Keith Cope -BITD
  • Completion 23rd July 2004
  • Project Monitoring to Project Team and Project
    Board

15
(No Transcript)
16
(No Transcript)
17
(No Transcript)
18
(No Transcript)
19
(No Transcript)
20
(No Transcript)
21
(No Transcript)
22
(No Transcript)
23
Reception Desk Area
24
(No Transcript)
25
(No Transcript)
26
(No Transcript)
27
(No Transcript)
28
(No Transcript)
29
(No Transcript)
30
(No Transcript)
31
(No Transcript)
32
(No Transcript)
33
Reception Building
34
Daresbury Science Park Progress
  • Internal fit out on Building No 1 complete
  • Completion July 2004.
  • Road Works to Express Way being progressed
  • External Works being progressed.
  • Gas Pipe work being progressed.
  • New 11kV power supply cables have been installed
    to feed the Daresbury Science Park and Daresbury
    Lab reinforcement - HPCy

35
(No Transcript)
36
(No Transcript)
37
(No Transcript)
38
(No Transcript)
39
Building No2 Proposed Cockcroft Institute
40
(No Transcript)
41
Before - October 2002 and after - February 2004
42
Tower ERPL Project
43
Tower ERPL Project
44
Tower ERPL Project
45
Tower Ceiling Tile Removal
46
Tower Ceiling Tile removal
47
Tower Ceiling Tile Removal
48
Cycle Sheds to be relocated
49
Car Park Access to change
50
Main Site Road - realignment
51
Approx new entrance to Main Car Park
52
(No Transcript)
53
(No Transcript)
54
(No Transcript)
55
Estates Management Activity Update and Issues
Raised
  • Decentralisation of Site Heating Gas Supply
    Hobb Lane, A56 Chester Road, down Keckwick Lane
    by July 2004.
  • HSE Fire Precautions Phase 1 - work has commenced
    in the SR and Tower completion September 2004
    Fire Panels replacement
  • Fire System Replacement - Tower, Stores , E
    Block and A Block Summer 2004

56
Estates Management Activity Update and Issues
Raised
  • Proposed Decentralisation of heating system ,
    commencement May 2004, completion September
    2004.
  • Estates Management Website http//www.estates.dl.
    ac.uk , to be updated in June 2004 .
  • Development of a DL Emergency Plan on going in
    draft June 2004 Bike Sheds to be relocated to
    Main Car park , consultation required

57
Estates Strategy - OST proposed funded projects-
2004-2005
  • Replacement Site Water Main
  • Asbestos removal within Tower Building
  • Tower Ventilation system replacement
  • Replacement of Roofs
  • Replacement of CBlock Elevations
  • New Entrance for B Block from Car Park - DDA
  • Upgrade entrance to A and B Blocks- DDA
  • Upgrade Main corridors A and B Blocks
  • Upgrade Road surfaces, replace security barriers
    and replace wooden kerbs.
  • Electrical Testing of Buildings
Write a Comment
User Comments (0)
About PowerShow.com