New Millennium EO1 Advanced Land Imager 23 January 1998 - PowerPoint PPT Presentation

1 / 35
About This Presentation
Title:

New Millennium EO1 Advanced Land Imager 23 January 1998

Description:

Overview of Successful Tests from the First CPT. Omissions During the First CPT ... run on the exciter in the vertical configuration with the use of a head expander ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 36
Provided by: markperrys
Category:

less

Transcript and Presenter's Notes

Title: New Millennium EO1 Advanced Land Imager 23 January 1998


1
System Testing forEarth Observing-1
Mark Perry EO-1 Lead Systems Engineer Swales
Aerospace
2
Agenda
  • System Testing Topics
  • Overview of System Tests
  • Details of Aliveness Test
  • Development of the EO-1 CPT
  • Details of Functional Test
  • EO-1 CPT Design
  • CPT Sections
  • Highlights of the First CPT
  • Overview of Successful Tests from the First CPT
  • Omissions During the First CPT
  • Problems During Execution
  • Problems during Execution
  • Status of System-Level Testing
  • Objectives of First CPT
  • Summary

3
System Testing Topics
  • Description of system tests
  • Detailed description of comprehensive performance
    test
  • Results of first comprehensive performance test
  • Plans for system testing through launch

4
Overview of System Tests
  • Aliveness
  • Verifies that each subsystem and payload
    operates, including basic functionality
    mechanical motion, (configuration or life time
    limited)
  • Used when system configuration or time
    limitations prevents a full functional test
  • Quick verification of satellite health after a
    move
  • After each axis of vibration
  • Prior to acoustics test
  • During launch countdown and during countdown
    simulations
  • Functional
  • Verify every interface, command, telemetry point,
    and function
  • Uses EGSE as stimulus and to test systems more
    fully than aliveness test
  • Performed after vibration and acoustic tests, and
    on the LV

5
Overview of System Tests (CONTINUED)
  • Comprehensive Performance Test (CPT)
  • Measures performance of each subsystem, and EO-1
    as a system
  • Dry-run of the CPT performed at Swales in May
    baseline in July
  • Three other CPTs during thermal-vacuum test,
    after environmental tests, and at the launch site
  • Special tests. These tests need special support
    equipment, or are conducted only a single time.
    Some FDC tests are special tests.
  • Some examples of special tests
  • RCS high-pressure test (tank has limited
    permissible high-pressure cycles)
  • High/low-voltage test (single-time verification
    of function)
  • Exhaustive command permutation test (not
    necessary every CPT)
  • 1773 SEU test (requires special GSE)
  • Inserted into the schedule when procedures and
    equipment available

6
Details of Aliveness Test
  • Every component, subsystem, instrument, and
    payload is turned on
  • Nominal telemetry provides initial
    state-of-health verification
  • Includes imaging and end-to-end data flow which
    is extensive test of ALI, Hyperion, AC, WARP, and
    X-band
  • ACS modes and components tested
  • All power-system functions tested
  • All CDH tasks tested
  • All downlink rates tested, S-band and X-band

7
Development of the EO-1 CPT
  • Based on Spacecraft Test Operating Language
    (STOL) Procedures as much as possible
  • Automatic command verification and limit checking
  • Executes quickly
  • Can repeat with precision
  • Procedures are directly transportable to
    operations team
  • Can check STOL procedures before running first
    CPT
  • Bottoms-up, modular approach
  • Using tests developed for box testing and
    integration
  • Some tests also used in aliveness and functional
    tests
  • Each subsystems tests verify all subsystem
    functions and requirements. These tests are
    listed and cross-referenced to CPT sections.
  • Where possible, conduct tests of different
    subsystems in parallel to shorten the duration of
    the CPT
  • TRMM and XTE CPTs used for reference

8
Details of Functional Test
  • Same as the CPT with the following exceptions
  • Performance-only tests are eliminated, such as
    the long (spin-down) RWA test
  • The launch and B-dot timelines are shortened
  • Specialized instrument tests eliminated, because
    they are fully tested in a max-data-rate,
    end-to-end test
  • LFSA deployment has a limited number of cycles,
    so its test is eliminated
  • EFF test is shortened to a few cycles
  • Multiple-permutation test of s/a release
    redundancy eliminated (redundant side still
    tested)
  • Dedicated s/a drive test eliminated, since the
    s/a drive is continuously tested in the
    background
  • Orbit tests are eliminated
  • The total duration is about 24 hours, instead of
    the 48-72 hours needed for the CPT
  • As in the CPT, much of the system subsystem
    health, function, performance is confirmed and
    determined from nominal telemetry

9
EO-1 CPT Design
  • Three general phases with 11 sections
  • Begin with a launch, ascent, deployment, and
    sun-acquisition simulation to verify the most
    critical timelines on the mission and to stress
    the power system
  • Follow with a series of tests to verify all
    satellite functions and to measure system
    performance
  • End with several real-time, nominal orbit-cycle
    tests
  • The CPT is designed for ambient testing, with the
    solar arrays un-mounted and all the instruments
    and payloads integrated
  • Modified for first CPT (without Hyperion)
  • Modified for thermal-vacuum testing (Hyperion
    cryocooler operations, PPT firing, and RCS
    pressurization will be different)
  • Modified for launch site (solar arrays will be
    mounted)
  • Data used to begin subsystem trending of key
    parameters

10
CPT Sections
  • CPT0 Launch configuration. The S/C is turned on
    configured as for launch. Nominal performance
    is verified through telemetry
  • CPT1 Ascent through sun acquisition. From switch
    to internal power, through launch, ascent,
    separation, deployment, rate nulling, sun
    acquisition following a worst-case timeline. Real
    time enables assessment of ACS timers the power
    system. During the coast phase, additional
    subsystem tests gain experience in operating the
    S/C with 2kb/s telemetry.
  • CPT2 ACS nominal S/C operations. Nominal
    configuration, except instruments, payloads,
    WARP are off. Timeline driven by ACS tests
    phasing, sensor stimulation, actuator operation,
    GPS, coupling. Power, S-Band, M5 tests
    conducted in parallel. S-Band requires some
    dedicated time.
  • CPT3 Instrument turn-on, including payloads
    WARP. Verify health of instrument most
    functions excluding imaging.

11
CPT Sections (CONTINUED)
  • CPT4 Comprehensive instrument payload tests.
    Each payload performs exhaustive testing,
    including image data, where possible
  • CPT4A ALI. Dark images, cal lamps, heater
    functions, FDC, mechanisms, processor loads,
    timers.
  • CPT4B Hyperion. Dark images, cal lamps, heaters,
    cryocooler, mechanism, timers, FDC.
  • CPT4C AC. Dark images, lab image, gain
    variations, temperature control
  • CPT4D LFSA. Launch release, deploy,
    current/voltage
  • CPT4E PPT. Single multiple firings, both
    tubes, long short pulses
  • CPT4F EFF
  • CPT5 Comprehensive ACS testing. Complete
    performance testing of ACS S/W component
    functions. RCS testing.

12
CPT Sections (CONTINUED)
  • CPT6 Solar-array drive. Orbit rate, ramp up,
    ramp down, open loop test, blind acquisition of
    index, min/max travel limits, rewind,
    potentiometers, glitch test.
  • CPT7 WARP/RF. Correct image data through X-Band,
    correct data through MSSP to X-Band at 2 Mb/s
    (compare X- and S-Band data), correct pointing of
    X-Band.
  • CPT8 End-to-end tests maximum rate. Correct
    data from instruments, through WARP X-Band to
    ground storage. Test maximum data ingest all
    instruments operating at the same time for 60
    seconds.
  • CPT9 Safemode load shed. Transition to
    safemode, ACS, all subsystems put into correct
    configuration. Safemode recovery
  • CPT10 Special command. Test each special
    command reset processors switch to alternate
    PROMs.
  • CPT11 Orbit-cycles. As a minimum
    data-collection orbit with downlink,
    lunar-calibration orbit, delta-V orbit.

13
Highlights of the First CPT
  • The first iteration of the CPT took about 72
    hours. Most tests were successful
  • Tests with the most problems during the first
    execution were re-run on the fourth day, with
    success. These tests were CPT0, CPT1 (launch),
    and some ACS tests from CPT2.
  • There were 36 problem records (PRs), which
    represent hardware or software anomalies. Most
    are resolved.
  • There were about 100 discrepancies in the CPT
    procedures, most of which had not been tested
    previously. Most of the deviations caused test
    delays. Most of the deviations have been
    incorporated into new versions of the procedures.
  • The FOT developed orbital timelines, which were
    tested successfully and resulted in improved
    command sequences

14
Overview of Successful Tests from the First CPT
  • ALI comprehensive Health Safety and imaging
  • All WARP functions, performance and evaluation
  • Power system solar-array drive, power switching,
    and battery-charge management
  • ACS End-to-end open loop phasing of all major
    ACS modes of operation were performed. Completed
    a full performance test of RWAs, IRU, MTBs
  • CDH all thirteen of the M5 CDH tasks performed
    without error
  • GPS update of spacecraft time tested
  • Command sequence (ATS and RTS) tested
  • RCS thruster valves and flow tested

15
Overview of Successful Tests from the First CPT
(CONTINUED)
  • Some contingency and FDC tested
  • HOP (solar-array release) redundancy and backup
    activation
  • ACS timers to delay transitions
  • Transition to safemode
  • 1773 redundancy
  • Watchdog timers, special commands, and re-starts.
  • EFF loaded and executed

16
Omissions During the First CPT
  • Hyperion, Atmospheric Corrector, LFSA and
    Autonomous Star Tracker were not integrated. (AST
    I/F and interaction with the ACS was tested
    verified.)
  • Due to ALI concerns, the PPT was not tested
  • Most FDC was not tested (exceptions stated above)
  • CDH uplink-error tests not performed. (Tested
    at box-level.)
  • RF The S-band RF not tested (GSE Transmitter in
    repair RF was tested during integration.)
  • RF X-band not tested (critical X-band tlm not
    calibrated). X-Band passed all performance tests
    during integration
  • Solar-array drive redundant drive and encoder,
    orbital-motion control by M5 ACS FSW, including
    imaging profile

17
Omissions (CONTINUED)
  • ACS use of GPS position and velocity vectors
    (tested previously during integration)
  • Since the ACE software is just completing
    development, ACE safehold control of the
    actuators (MTB, RWA, SAD) not tested
  • End-to-end phasing for the M5 ACS B-dot control
    mode
  • Thermal thermostatically-controlled heaters will
    not draw power unless the temperature is below 4
    to 8 Celsius
  • Since the ACDS required some software patches, we
    did not perform some M5-reset tests (for example,
    memory-scrub errors), which requires re-loading
    the patches. The re-sets were tested during
    integration and at the box level.
  • Comprehensive testing of PSE and CDH commands
    Some seldom-used commands not tested

18
Problems during Execution
  • About 100 procedure deviations. Most of these
    have been incorporated, already, into corrected
    STOL
  • TSMs did not operate at first. (TSMs were not
    available for testing prior to the CPT). The
    launch TSMs were fixed and re-tested.
  • GPS telemetry had intermittent dropouts, even
    after new s/w (PTR ___ )
  • The ACE software, version 2.03, contained errors
    (2.03 had not been tested prior to the CPT).
    After using an earlier version of the code for
    about 24 hours, ACE 2.04 was loaded and used
    successfully for the remainder of CPT.
  • The magnetic field around the spacecraft was
    different from the previous TAM calibration ALI
    integrated and SAS wiring
  • There is a still-undiagnosed problem using the
    AST load box (EGSE)
  • EFF hogged the M5 CPU for too long and caused a
    warm re-start

19
Status of System-Level Testing
  • Working on STOL procedures
  • Finish building tests that were omitted from the
    first CPT due to insufficient preparation.
  • Complete revisions of all existing STOL
    procedures
  • Perform test-run of all new and revised
    procedures so that the next CPT executes smoothly
  • Each subsystem working on improving tests
  • Final review of subsystem requirements
  • Complete red and yellow limits for parameters
    that have limits
  • Yellow limits are just outside nominal or
    expected operation and permit a controlled
    response by the TC
  • Red limits indicate impending damage to flight
    hardware and require immediate action
  • Completed two aliveness tests that were
    abbreviated due to missing hardware

20
Objectives of First CPT
  • Met all objectives of first CPT
  • Perform as much functional and performance
    testing of EO-1 as is possible
  • Refine our knowledge of operating EO-1
  • Identify problems and additional work necessary
    before baseline CPT and environmental tests
  • Test the CPT STOL procedures

21
Summary
  • First dry run of CPT was successful, but
    incomplete
  • Successfully tested most of EO-1 but some
    omissions due to lack of hardware (AST, Hyperion,
    etc.) and problems with GSE (S-band and X-band)
  • Some testing also reduced due to some incomplete
    procedures (redundant s/a drive, etc.)
  • Demonstrates that smooth CPT can be completed
    within 72 hours
  • Missing procedures are nearly complete
  • All components and payloads will be mounted for
    the baseline CPT
  • Nearly all Problem Records have been resolved
    only Category C issues remaining
  • Telemetry filter tables for 2 kb/s downlink rate
  • AST interface?
  • FEDS crash
  • Anomalous warm starts (intermittent problem with
    probable causes based on configuration do not
    expect during baseline CPT)

22
Spacecraft Testing
23
Agenda
  • Mechanical Alignment
  • Vibration Testing
  • Shock Testing
  • Mass Properties
  • Acoustic Testing

24
Mechanical Alignment
  • Satellite ground alignment plan (SAI-PLAN-206)
    establishes system requirements
  • The following alignment measurements shall be
    performed to establish the spacecraft primary
    reference frame
  • S/C MRC to S/C datums
  • S/C SRC to MRC
  • IRU SRC will be mapped to the S/C MRC star
    tracker reference cube
  • ALI HSA reference cubes will be mapped to the
    S/C MRC
  • ALI ACI Optics Module shall be co-aligned to
    within 2 arc-mins. Bushings have been fabricated
    to allow adjustment in the position of the ACI OM.

25
Mechanical Alignment Flow
  • Baseline measurements shall be performed after
    all flight components have been installed
  • Alignment measurements shall be performed of the
    IRU and star tracker to S/C MRC prior to
    vibration testing. Post vibration measurements
    will be made to verify that alignment has been
    maintained between components
  • Measurements are taken with one sec accuracy
    theodolites (Model Wild T2) with autocollomating
    eyepieces

26
Satellite Vibration Testing
  • The Delta 7320-10 launch vehicle payload
    environment includes sustained sinusoidal
    vibration as well as quasi-sine transients during
    the launch phase of flight
  • Three separate and distinct sustained oscillation
    conditions typically occur, resulting in both
    lateral and thrust-axis responses. These
    conditions, in the order they occur in flight,
    and the associated frequency bands and sweep
    rates are
  • First pre-MECO (Main Engine Cutoff)25 to 30
    Hz1.5 octaves per minute
  • Second pre-MECO30 to 35 Hz1.5 octaves per
    minute
  • Prior to MECO15 to 20 Hz4 octaves per minute

27
Satellite Vibration Testing
  • Satellite Sine Vibration Test Plan (SAI-PLAN-307)
    has been drafted and is in review by project,
    facility spacecraft personnel
  • The vibration test shall be run in three axes.
    The X Y-axis tests shall be run on the lateral
    slip table the Z-Axis test shall be run on the
    exciter in the vertical configuration with the
    use of a head expander
  • The launch vehicle contractor shall provide a
    Test Payload Adapter Fitting for use during this
    vibration test
  • The MAP S/C vibration test fixture is being used
    for this test. The fixture assembly consists of
    three parts, 1) a force ring plate, 2) six
    multidimensional force transducers, 3) adapter
    test plate

28
Satellite Vibration Testing
  • Approx. 30 tri-axial accelerometers have been
    identified on the spacecraft and payload. These
    accelerometers were installed at the Swales
    cleanroom facility, prior to shipment to GSFC
  • The vibration test control instrumentation will
    consist of three tri-axial accelerometers mounted
    on the MAP adapter plate. The average in-axis
    response of these accelerometers will be used to
    control the test
  • Three additional accelerometers will also be used
    to limit the input acceleration level to the
    spacecraft, ALI HSA. A predetermined, Not To
    Exceed (NTE), level will be specified for each
    limiting accelerometer and the test input levels
    shall be automatically adjusted, by the control
    system, if the NTE level of any of the limiting
    accelerometers is reached

29
Satellite Vibration Testing
  • The following figures shows the proposed
    accelerometer placements

30
Satellite Vibration Testing
  • The test specification is derived from latest
    flight coupled loads analysis times a 1.25 factor
    to obtain the protoflight levels below
  • The sweep rates for the sustained oscillations
    have been selected to approximate the actual
    flight time it takes to sweep through the
    frequency bands shown

31
Satellite Vibration Testing
  • The following plots are expected responses for
    the S/C, ALI HSA

ltltlt Response Plots gtgtgt
32
Satellite Shock Testing
  • The satellite shock test procedure will be
    incorporated within the sine vibration test
    procedure
  • Two shock tests will be performed at the
    conclusion of the vibration test
  • The satellite will be lifted, by a crane, approx
    3 with the test PAF installed. A sheet of foam
    will be placed under the PAF and the clampband
    shall be released and allowed to drop onto the
    foam sheet
  • All accelerometer instrumentation used during the
    vibration test shall remain installed on the
    satellite and will be recorded during the shock
    test

33
Satellite Mass Properties
  • The satellite mass properties test plan,
    SAI-PLAN-319, will be created to provide the
    facility test requirements
  • The satellite center of gravity in the X-Y plane
    and the moment of inertia about the Z-axis will
    be measured and compared to the prediction from
    the CAD solid model
  • This test will be performed prior to vibration
    testing and again before acoustic test with a
    fully integrated satellite
  • The test will be preformed on the Miller mass
    properties table in building 15
  • The satellite will be placed on the thermal
    vacuum test fixture with the clampband installed

34
Satellite Acoustic Testing
  • The maximum acoustic environment for the EO-1
    satellite will occur during liftoff and transonic
    flight. Liftoff levels are typically higher than
    transonic levels at the payload location
  • A satellite acoustic test plan, SAI-PLAN-320,
    will be created to provide the facility test
    requirements
  • This test will be preformed on a fully integrated
    satellite in the GSFC acoustic test facility in
    Building 10
  • A reduced set of accelerometer instrumentation
    will be installed and recorded during the test
  • The satellite will be lifted off the
    transportation dolly and raised into the center
    of the microphones acoustic field

35
Satellite Acoustic Testing
  • The predicted EO-1 acoustic environment is a
    function of the configuration of the launch pad,
    the vehicle (e.g., 7320 Delta with 3 GEM solid
    motors), the payload fairing (10-ft. composite,
    with 3-in. acoustic blankets) and the fill effect
    due to the satellite and DPAF volume and radial
    gap to the fairing wall
  • The EO-1 protoflight acoustic levels are shown.
    The test duration is one minute for protoflight
    test. These estimated P95/50 probability levels
    are based on current McDonnell Douglas Aerospace
    Delta 7320-10 levels, with an adjustment for the
    EO-1 fill effect
Write a Comment
User Comments (0)
About PowerShow.com