Title: The Network of Centres Flight Operations Coordination and Design Tool
18th International Conference on Space Operations
The Network of Centres Flight Operations
Coordination and Design Tool
Stefania Cornara Sandra NegrÃn Fernando Pina
Howard Nye ESA/ESOC
Paul OShea Vega Group
DEIMOS Space
2Presentation Overview
- Overview The Network of Technical Centres (NofC)
- NofC Pilot Study Concurrent Engineering
Techniques - Concurrent Engineering NofC Prototype Facility
(CENOC) - Main Results and Achievements of CENOC
- Roadmap for Future Developments
- The NofC Coordination and Design Tool (CDT)
- Enhancements of the CENOC Prototype Capabilities
- CDT Layout and Main Functionalities
- Conclusions and Future Perspectives
3The Network of Technical Centres
- The European Network of Technical Centres (NofC)
initiative has been established to seek benefits
for ESA Member States through - cross-support in the conduct of missions
operations - avoiding duplication maximising re-use of
existing systems - cooperative management of investments, facilities
and staff - sizing of overall capacities according to overall
needs - distribution of works among the different centres
through coordinated use of available spare
capacity
- The pilot network of Flight Operations Technical
Centres is made up of the representatives of all
major European national agencies involved in
satellite flight operations ASI, BNSC, CDTI,
CNES, DLR, NSC and SSC - ESA/ESOC acts as the overall coordinator of these
activities
4NofC for Flight Operations Pilot Phase
- The first Pilot Phase of the NofC for Flight
Operations, in 2000, pointed out that some form
of tools would be required to manage and
coordinate the activities between the different
participating centres - In 2001, DEIMOS Space were tasked to develop the
Concurrent Engineering NofC Prototype Facility
(CENOC) - Identification of the enhancements for the
follow-on implementation of a flight operations
Coordination and Design Tool (CDT), which began
at the end of 2003
5CENOC Prototype
- Concurrent Engineering Concepts and Approach
implementation of a process integrating all
functional disciplines associated with system
design and development - by systematically simultaneously employing a
teaming of these disciplines - in order to integrate concurrently apply all
necessary processes required to produce an
effective and efficient product/system design
that satisfies all customer/mission requirements,
at least cost, and within a significantly reduced
time frame
6CENOC Prototype (cont.)
- Application of CE approach to the CENOC Prototype
- Centralised management and remote maintenance of
the NofC Databases - Model and parametric-driven design of the ground
segment
- CENOC Prototype design and development
constraints - Three workstations to simulate the network of
system components - Simulated remote access via internal network
- Interface definition among the system components
via database - System built on top of a well-known Office
Automation Package
7CENOC/CDT Functionalities
- Execution of NofC Management and Coordination
role - Centralised management of the existing and
planned NofC DBs - Ground facility loading
- Graphic representation of conflicts in ground
segment utilisation - Tabular and graphical management reports
- Remote maintenance of the NofC databases to allow
orderly revision of input data by the respective
technical centres/agencies
- Analysis and high-level definition of the ground
segment and utilisation scenario for a specific
project - High level design of ground segment
configurations (given mission) - Facility loading analysis
- Resource availability across the different
technical centres - System-level trade-off of ground segment options,
based on functionality, availability, risk
assessment and cost
8CENOC/CDT Application Scenarios
Analysis of What-if Situations
9CENOC/CDT Application Scenarios (cont.)
Support Co-located Group of Representatives
- Definition of multi-agency network of facilities
(ground stations, antennas, control centres,
etc.) - Ground segment concept and satellite operations
scenario (potentially involving more than one
agency) - Cost estimations and optimisation of the
different scenarios
10CENOC/CDT Design Process Modelling
- Ground segment design process is model-driven
- Involves disciplines that progress in parallel
with their estimations - Level of interdependency within the system
modelling is very low and affects resource
availability and utilisation
Design activity coordinated by a System Engineer
11CENOC/CDT Design Process Models
12CENOC/CDT Ground Segment Design Scope
13CENOC/CDT Ground Segment Design Process
14CENOC Prototype Implementation
Visualisation Graphs and Reports
15CENOC Prototype Implementation (cont.)
Design Process Models
16CENOC Prototype Implementation (cont.)
What-if Analysis
17Main Results and Achievements of CENOC
- Usable local database maintenance controlled
data exchange - Concurrent Engineering techniques analysed
process to provide a coherent framework for
Ground Segment design (ESOC-specific) - High-level ground segment design with cost and
risk outputs - Enables preparation of management reports for
facility utilisation - Fast development time and fast response to
requested changes
- Prepared for extension to remote administration
and maintenance - Straightforward to maintain
- Initial feedback from ESOC users was very
positive - Promising basis for future system enhancements
and developments
18CENOC Demonstration Campaign Findings
- The results have a general scope, since the
missions considered cover a wide spectrum of
possible mission objectives and scenarios - Possibility to draw most of the input
requirements and assumptions relevant to the
ground segment design process from the expertise
of the NofC representatives involved in the
demonstration sessions - The demonstration phase allowed to completely
validate the parametric formulation of the design
process - Fairly positive results and useful guidelines to
proceed with the follow-on implementation the
Coordination and Design Tool (CDT)
19Roadmap for Future Developments
- Implementation of distributed Network of Centres
capabilities - Snapshots of the NofC configuration database
- Private / public areas for each technical
centre/agency - Central repository of project designs
- Possibility to access restricted
information/databases outside the boundary of the
Network of Centres
- Database and database management improvements
- Check consistency of data entered by each
technical centre - Enhance data exchange capability and coordination
functions, including sending/receiving data over
a remote connection
20Roadmap for Future Developments (cont.)
- Extension of the facility to cover other parts of
the ground segment design process that have not
been modelled yet
- Development of additional functionalities in the
existing tools - Generation of additional reports and charts
- Improvement to the Control Centre and Antenna
Load Analysis - Enhancement of the Database query capabilities
- More breakdown on Expert Output for costs and
manpower levels - On-line Help with explicit units/restrictions on
data entry, hints for the decision-making
process, tool usage guidelines, etc.
- Implement cross-relationships among models, if
and when needed
21Roadmap for Future Developments (cont.)
- Assessment of the compliance of a design with
input requirements - System security issues
- Finer access control
- Approval/rejection procedures for data ingestion
into the database
- Assessment of potential changes on the technology
used - Other database managers
- Other web server technologies
- Porting most of the facility to web
- Faster data retrieval and storage through the
models-database interface
22CDT Context for Ground Segment Modelling
23CDT High-Level Context
Centralised Design Process
- Design process run at a TC, where an
instantiation of the NofC DB is made available
- After finishing the design, data can be sent to
the central database (at ESOC)
ESOC
- Private data (e.g. costs and risks) can be
retained at each TC
TC
24Conclusions and Future Perspectives
CENOC Prototype proved the feasibility of
implementing a tool to support the application of
CE techniques to ground segment design CDT
development is on-going, based on the
requirements agreed with ESA