The Network of Centres Flight Operations Coordination and Design Tool - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

The Network of Centres Flight Operations Coordination and Design Tool

Description:

SpaceOps 2004, May 17-21 2004, Montreal, Canada. Track T4. CDT ... SpaceOps 2004, May 17-21 2004, Montreal, Canada. Track T4. CDT. The Network of Technical Centres ... – PowerPoint PPT presentation

Number of Views:27
Avg rating:3.0/5.0
Slides: 25
Provided by: scornarade
Category:

less

Transcript and Presenter's Notes

Title: The Network of Centres Flight Operations Coordination and Design Tool


1
8th International Conference on Space Operations
The Network of Centres Flight Operations
Coordination and Design Tool
Stefania Cornara Sandra Negrín Fernando Pina
Howard Nye ESA/ESOC
Paul OShea Vega Group
DEIMOS Space
2
Presentation Overview
  • Overview The Network of Technical Centres (NofC)
  • NofC Pilot Study Concurrent Engineering
    Techniques
  • Concurrent Engineering NofC Prototype Facility
    (CENOC)
  • Main Results and Achievements of CENOC
  • Roadmap for Future Developments
  • The NofC Coordination and Design Tool (CDT)
  • Enhancements of the CENOC Prototype Capabilities
  • CDT Layout and Main Functionalities
  • Conclusions and Future Perspectives

3
The Network of Technical Centres
  • The European Network of Technical Centres (NofC)
    initiative has been established to seek benefits
    for ESA Member States through
  • cross-support in the conduct of missions
    operations
  • avoiding duplication maximising re-use of
    existing systems
  • cooperative management of investments, facilities
    and staff
  • sizing of overall capacities according to overall
    needs
  • distribution of works among the different centres
    through coordinated use of available spare
    capacity
  • The pilot network of Flight Operations Technical
    Centres is made up of the representatives of all
    major European national agencies involved in
    satellite flight operations ASI, BNSC, CDTI,
    CNES, DLR, NSC and SSC
  • ESA/ESOC acts as the overall coordinator of these
    activities

4
NofC for Flight Operations Pilot Phase
  • The first Pilot Phase of the NofC for Flight
    Operations, in 2000, pointed out that some form
    of tools would be required to manage and
    coordinate the activities between the different
    participating centres
  • In 2001, DEIMOS Space were tasked to develop the
    Concurrent Engineering NofC Prototype Facility
    (CENOC)
  • Identification of the enhancements for the
    follow-on implementation of a flight operations
    Coordination and Design Tool (CDT), which began
    at the end of 2003

5
CENOC Prototype
  • Concurrent Engineering Concepts and Approach
    implementation of a process integrating all
    functional disciplines associated with system
    design and development
  • by systematically simultaneously employing a
    teaming of these disciplines
  • in order to integrate concurrently apply all
    necessary processes required to produce an
    effective and efficient product/system design
    that satisfies all customer/mission requirements,
    at least cost, and within a significantly reduced
    time frame

6
CENOC Prototype (cont.)
  • Application of CE approach to the CENOC Prototype
  • Centralised management and remote maintenance of
    the NofC Databases
  • Model and parametric-driven design of the ground
    segment
  • CENOC Prototype design and development
    constraints
  • Three workstations to simulate the network of
    system components
  • Simulated remote access via internal network
  • Interface definition among the system components
    via database
  • System built on top of a well-known Office
    Automation Package

7
CENOC/CDT Functionalities
  • Execution of NofC Management and Coordination
    role
  • Centralised management of the existing and
    planned NofC DBs
  • Ground facility loading
  • Graphic representation of conflicts in ground
    segment utilisation
  • Tabular and graphical management reports
  • Remote maintenance of the NofC databases to allow
    orderly revision of input data by the respective
    technical centres/agencies
  • Analysis and high-level definition of the ground
    segment and utilisation scenario for a specific
    project
  • High level design of ground segment
    configurations (given mission)
  • Facility loading analysis
  • Resource availability across the different
    technical centres
  • System-level trade-off of ground segment options,
    based on functionality, availability, risk
    assessment and cost

8
CENOC/CDT Application Scenarios
Analysis of What-if Situations
9
CENOC/CDT Application Scenarios (cont.)
Support Co-located Group of Representatives
  • Definition of multi-agency network of facilities
    (ground stations, antennas, control centres,
    etc.)
  • Ground segment concept and satellite operations
    scenario (potentially involving more than one
    agency)
  • Cost estimations and optimisation of the
    different scenarios

10
CENOC/CDT Design Process Modelling
  • Ground segment design process is model-driven
  • Involves disciplines that progress in parallel
    with their estimations
  • Level of interdependency within the system
    modelling is very low and affects resource
    availability and utilisation

Design activity coordinated by a System Engineer
11
CENOC/CDT Design Process Models
12
CENOC/CDT Ground Segment Design Scope
13
CENOC/CDT Ground Segment Design Process
14
CENOC Prototype Implementation
Visualisation Graphs and Reports
15
CENOC Prototype Implementation (cont.)
Design Process Models
16
CENOC Prototype Implementation (cont.)
What-if Analysis
17
Main Results and Achievements of CENOC
  • Usable local database maintenance controlled
    data exchange
  • Concurrent Engineering techniques analysed
    process to provide a coherent framework for
    Ground Segment design (ESOC-specific)
  • High-level ground segment design with cost and
    risk outputs
  • Enables preparation of management reports for
    facility utilisation
  • Fast development time and fast response to
    requested changes
  • Prepared for extension to remote administration
    and maintenance
  • Straightforward to maintain
  • Initial feedback from ESOC users was very
    positive
  • Promising basis for future system enhancements
    and developments

18
CENOC Demonstration Campaign Findings
  • The results have a general scope, since the
    missions considered cover a wide spectrum of
    possible mission objectives and scenarios
  • Possibility to draw most of the input
    requirements and assumptions relevant to the
    ground segment design process from the expertise
    of the NofC representatives involved in the
    demonstration sessions
  • The demonstration phase allowed to completely
    validate the parametric formulation of the design
    process
  • Fairly positive results and useful guidelines to
    proceed with the follow-on implementation the
    Coordination and Design Tool (CDT)

19
Roadmap for Future Developments
  • Implementation of distributed Network of Centres
    capabilities
  • Snapshots of the NofC configuration database
  • Private / public areas for each technical
    centre/agency
  • Central repository of project designs
  • Possibility to access restricted
    information/databases outside the boundary of the
    Network of Centres
  • Database and database management improvements
  • Check consistency of data entered by each
    technical centre
  • Enhance data exchange capability and coordination
    functions, including sending/receiving data over
    a remote connection

20
Roadmap for Future Developments (cont.)
  • Extension of the facility to cover other parts of
    the ground segment design process that have not
    been modelled yet
  • Development of additional functionalities in the
    existing tools
  • Generation of additional reports and charts
  • Improvement to the Control Centre and Antenna
    Load Analysis
  • Enhancement of the Database query capabilities
  • More breakdown on Expert Output for costs and
    manpower levels
  • On-line Help with explicit units/restrictions on
    data entry, hints for the decision-making
    process, tool usage guidelines, etc.
  • Implement cross-relationships among models, if
    and when needed

21
Roadmap for Future Developments (cont.)
  • Assessment of the compliance of a design with
    input requirements
  • System security issues
  • Finer access control
  • Approval/rejection procedures for data ingestion
    into the database
  • Assessment of potential changes on the technology
    used
  • Other database managers
  • Other web server technologies
  • Porting most of the facility to web
  • Faster data retrieval and storage through the
    models-database interface

22
CDT Context for Ground Segment Modelling
23
CDT High-Level Context
Centralised Design Process
  • Design process run at a TC, where an
    instantiation of the NofC DB is made available
  • After finishing the design, data can be sent to
    the central database (at ESOC)

ESOC
  • Private data (e.g. costs and risks) can be
    retained at each TC

TC
24
Conclusions and Future Perspectives
CENOC Prototype proved the feasibility of
implementing a tool to support the application of
CE techniques to ground segment design CDT
development is on-going, based on the
requirements agreed with ESA
Write a Comment
User Comments (0)
About PowerShow.com