Title: Constructability Reviews Minimize the Need for Drilled Shaft Remediation and Repair
1Constructability Reviews - Minimize the Need for
Drilled Shaft Remediation and Repair
Caltrans / ADSC CIDH Pile Workshop
ADSC The International Association of Foundation
Drilling Pacific Center 1 14180 Dallas
Parkway, Suite 510 Dallas, TX. 65254 Telephone
214-343-2091 Fax 214-343-2384 WWW.ADSC-IAFD.CO
M
PRESENTED BY JOHN J. ROE, P.E.
2Outline
- What Causes Problems with CIDH Piles?
- How Can We Reduce Anomalies and Defects in
CIDH Piles?
- Constructability Reviews Can Be a Win- Win
Solution for All !!!
3What Causes Problems in Drilled Shafts?
- Difficult Geologic Conditions / Insufficient
Soils Information
- Poor Construction Practices
4- Difficult Geologic Conditions
- Are the Easy Sites All Gone?
5- Project Soils Information (Cont.)
- Rock Strength Data (Not Ranges)
- Drill Logs Handwritten Logs
- Eliminate Exculpatory Clauses
6- Additional Exploratory Information (Cont.)
- Small Diameter Borings at Each Bent Location
- Large Diameter Test Shaft
- Bid Item / Contractor Investigation
7- Insufficient Rebar Spacing in Cages
- Multiple Layers of Reinforcing
- Insufficient Concrete Coverage
8Rebar Cage Couplers and Inspection Pipes Can
Restrict Flow of Concrete
Rebar Too Tightly Spaced !!!
9Sufficient Concrete Cover
Design Must Allow for Tolerances
10Socket Permanent Casing into Competent Rock Not
Caving Rock that Acts like Soil
11Seal Course
Use of Rock Sockets with Casing
12Best Practices / Pre-Bid Checklist
13Best Practices / Site Visit
14- Poor Construction Practices
- Inappropriate Concrete Mix Designs
- Inexperienced Drill Crews
- Faulty Slurry Management Techniques
15- Poor Construction Practices (Cont.)
- Inadequate Cleaning of the Bottom of Shaft
- Insufficient Wasting of Contaminated Concrete
at the Top of Shaft
- Constructing the Shaft Too Rapidly
- Problems Associated with the Tremie
16Concrete Mix Design Standardize Regionally
- 3/8 or 1/2 Max. Aggregate
- Restrict Early / Flash Set
17Shaft Drilling Considerations
- Drill Slowly Minimize Suction Created by the
Tool
- Minimize Over Drilling the Bottom
18Size the Equipment to Meet Job Requirements
Soilmech-825 Drill Unit
Medium Size Drill Unit
19Wet-Method Drilling Special Considerations
Exiting Shaft with Bucket
20Hydrate the Polymer Slurry
Baker Tanks
Proper Slurry Management
21Maintain Sufficient Head
Slurry Piping into Shaft
22Drilling Operations
23Four Tests Required
Slurry Testing Equipment
24pH Testing
25Mud Density
26Viscosity
27Sand Content
28Slurry Test Report (Per Specifications)
29Shaft Cleaning Considerations
- Silt/Clay Content (Exchange the Slurry)
30Rebar Cage Placement
- Record Rebar Splices and Significant
Concentrations
31Stabilization Rods
Install PVC Tubes with Rods
32Log Tube Coupler Locations
33Internally Braced
Engineered for Lifting
Lifting the Rebar Cage
34Rebar Cage Suspended Overhead
35Light-Weight Centralizers
Install Roller Spacer Assemblies (Centralizers)
36Centralizers
Template in Place
37Chain Binders
Tie-Off Rebar Cage
38Template
Rebar Cage Tied Off In Place to Template
39Tremie Considerations
- Check for Seal Leaks at Joints
- Maintain Tremie within the Concrete
4010 to 16 Diameter
Mobile Tremie Rack
41Sectional Tremie
Installation of Tremie Pipe
42Concrete Placement
- Check for Slump / Segregation
- Significant Interruption in Concrete Pour
Deliveries
43Concrete Chute
Check for Segregation of Paste from Aggregate
44Concrete Pump
Concrete Pumping
45Concrete Pump
Tremie Pipe
Concrete Pumping
46Baker Tank
Submersible Pump
Pump Slurry Back to Tank as Concrete is Placed
47Equal Level of Level of Concrete
Concrete Flowing Outside Cage
48Weighted Tape Measure
Measure Depth of Concrete
49Lift Casing During Concrete Pour
50Removal of Casing
51Remove Template
52Do Not Vibrate Top of Concrete
53Concrete Placement Log
54Fill Tubes with Water (Warm)
55Cleaning the Top of Shaft
- Fill PVC Tubes with Water
56How Can We Reduce Anomalies and Defects in
Drilled Shafts?
57Team Approach
ADSC and Caltrans
- Improved Construction Techniques
58Constructability Reviews Win-Win
59Team Approach Results
- Reduce Construction Claims
60QUESTIONS ???
QUESTIONS ???
COMMENTS ???