CPM 300 Principles of Earned Value Implementation CPM 300B Management Use of EV Data - PowerPoint PPT Presentation

1 / 48
About This Presentation
Title:

CPM 300 Principles of Earned Value Implementation CPM 300B Management Use of EV Data

Description:

Basic concepts of measuring performance. Examples. EVM guidelines for project execution ... basic contract information (target, ceiling, name of contractor, ... – PowerPoint PPT presentation

Number of Views:78
Avg rating:3.0/5.0
Slides: 49
Provided by: donnafit
Category:

less

Transcript and Presenter's Notes

Title: CPM 300 Principles of Earned Value Implementation CPM 300B Management Use of EV Data


1
CPM 300 Principles of Earned Value
ImplementationCPM 300B Management Use of EV
Data
  • Eleanor Haupt
  • Aeronautical Systems Center
  • eleanor.haupt_at_wpafb.af.mil
  • 1-937-656-5482

Lloyd Carter MTC AustralAsia Pty
Ltd llcarter_at_mtc.aust.com 61(0)3 5754
1010
2
Training Objectives
  • Basic concepts of measuring performance
  • Examples
  • EVM guidelines for project execution
  • Basic concepts of reporting progress
  • Basic concepts of analysis
  • Examples

3
Budgeted Cost for Work Performed (BCWP)
the EARNED VALUE concept
Were at the end of the second month, but only 1
section of track is complete. Earned value of
work completed 1,000
  • Assess progress on recurring basis
  • There are different methods of earning value
  • You earn value the same way as it was budgeted
    in baseline

4
General Principles of Measuring Performance (BCWP)
  • Establish valid metrics as you establish the time
    phased baseline
  • Relate true work status
  • Objective and quantifiable
  • Should be a quantitative and discrete way to
    measure the work
  • May tie in with success criteria or technical
    measure
  • Example successful completion of a specific
    test
  • Must be consistent in following established
    metric as work progresses
  • BCWP value drives both cost and schedule
    variances
  • If overstated or understated, it will distort
    variances
  • Can impact estimate at complete calculations

5
Three Basic Methods of Earning Value
  • Discrete
  • Physical, tangible end product
  • Common techniques milestone, complete, 0/100,
    50/50, units complete
  • Apportioned
  • Discrete, but dependent on another discrete work
    package
  • Example quality assurance (depends on assembly
    labor)
  • Planned as historical estimating factor (e.g.,
    7)
  • Level of Effort
  • No tangible end product
  • Basis of measurement time
  • When clock starts ticking, you automatically
    accumulate earned value
  • Results in no schedule variance (BCWP will always
    equal BCWS)
  • Example management personnel

6
Be Discrete!
  • Discrete EV Techniques
  • Method How Value is Earned
  • 0/100 no EV at opening, 100 EV at close of WP
  • 50/50 50 EV at opening, 50 EV at close of WP
  • Units Completed same budget value for identical
    units
  • Equivalent Units planned unit standards, allows
    partial credit
  • Weighted Milestone each milestone weighted based
    on planned resources
  • ideal to have a milestone each month
  • Percent Complete should be based on some
    quantitative assessment
  • may be somewhat subjective

7
Earning BCWP on Material
  • Material and Subcontracts
  • Earned Value taken no earlier than receipt or
    progress payments to subcontractors
  • define
  • order
  • receipt or progress
    payments
  • payment
  • to inventory
  • usage
  • accurate cost accumulation and assignment to
    contract
  • should perform price and usage variances
  • should plan earned value to match expected
    payment period
  • BCWP and ACWP should occur in same period to
    avoid artificial cost variance
  • option may report estimated actuals based on
    invoice

8
Examples of BCWP Calculations
9
Different EV Methodology Yields Different Results!
WBS 1.1.2 (Workpackage) MONTH Jan Feb Mar
Total BCWS (Original Budget) 100 120 100
320 BCWP (Earned Value) ACWP (Actual
Cost) 50 120 180
350
Assume that costs overran and work was completed
behind schedule for all methods
10
Example Milestone Technique
Jan Feb Mar BCWS (Original
Budget) 100 120 100 320 BCWP (Earned
Value) 0 100 220 320 Milestone 1
Planned 100 Milestone 2 Planned 120 Milestone 3
Planned 100 SCHEDULE VARIANCE -100 -20
120 0 ACWP (Actual Cost) 50
120 180 350 COST VARIANCE
-50 -20 40 -30
100
120
100
11
Example Level of Effort Technique
Jan Feb Mar BCWS (Original
Budget) 100 120 100 320 BCWP (Earned
Value) 100 120 100 320 SCHEDULE
VARIANCE 0 0 0
0 ACWP (Actual Cost) 50 120 180
350 COST VARIANCE 50 0
-80 -30
12
Example 50/50 Technique
Jan Feb Mar BCWS (Original
Budget) 160 160 320 BCWP (Earned
Value) 160 0 160 320 Task
Baseline Task - Actual SCHEDULE VARIANCE 0
-160 160 0 ACWP (Actual
Cost) 50 120 180 350 COST VARIANCE
110 -120 -20 -30
50
50
50
50
13
Example Percent Complete Technique
Jan Feb Mar BCWS (Original
Budget) 100 120 100 320 BCWP (Earned
Value) 60 100 160 320 Task 1
(100) Task 2 (120) Task 3 (100) SCHEDULE
VARIANCE -40 -20 60
0 ACWP (Actual Cost) 50 120 180
350 COST VARIANCE 10 -20
-20 -30
60
40
50
50
100
14
Which Technique Accurately Reflects Work Progress?
Jan Feb Mar Total
  • Milestone SV -100 -20 120 0
  • CV -50 -20 40 -30
  • LOE SV 0 0 0 0
  • CV 50 0 -80 -30
  • 50/50 SV 0 -160 160 0
  • CV 110 -120 -20 -30
  • Compl SV -40 -20 60 0
  • CV 10 -20 -20 -30

15
EVM Guidelines for Project Execution
16
Work Packages
Work Package (closed)
Work Package (open)
Work Package (open)
Work Package (open)
Work Package (not open)
Time Now
17
Authorizing the Work
  • Can only work on work package if it has been
    opened
  • Charge costs to open work packages only
  • Contractor system sets procedure
  • Contractor maintains baseline log which tracks
  • Distribution of budget
  • Additions of authorized work
  • Total equals value of contract at cost
  • Contract changes incorporated in disciplined
    manner
  • Cannot start work without authorization and
    budget
  • Baseline changes are controlled

18
  • more rules of the road...
  • cannot move budget and work independently
  • cannot use management reserve budget to cover
    overruns
  • may replan open work packages as necessary
  • contractor sets internal policy
  • maintain valid performance information
  • cannot change budgets or costs for completed
    work
  • except to fix errors

19
Project Control
  • So, your project has been baselined and work has
    started
  • Is everything going according to plan?
  • Next step in the process
  • figure out your status
  • figure out the problems
  • figure out what you need to do to fix them
  • figure out what the impact might be

20
Status Reporting
  • Report on periodic basic
  • weekly
  • monthly
  • Tailor the data to match how youre managing
  • Provide performance reports to
  • Senior management
  • Customer
  • Based on contract terms
  • Use data in reports and variance analysis to
    manage and control project

21
Contractor Reports
(Example of data item from U.S. Department of
Defense)
  • Cost Performance Report (CPR)
  • Format 1 cost and schedule progress by WBS
  • (specified reporting level usually at
    level 3)
  • Format 2 cost and schedule progress by
    organization
  • Format 3 changes to performance measurement
    baseline
  • Format 4 manpower forecast
  • Format 5 variance analysis

current and cum data
22
Formats 1 and 2
  • Contents
  • header
  • basic contract information (target, ceiling, name
    of contractor, etc.)
  • range of final estimates
  • body
  • performance data
  • variances
  • budget at completion, estimate at completion

WBS or ORGANIZATION
23
Variance Explanations
  • Format 5 variance analysis should address
  • separate discussion of CV, SV (current and cum)
    and VAC
  • clear description of reason for variance
  • quantity variances (e.g., price vs. usage)
  • be specific
  • discuss needed corrective action
  • technical, schedule, and cost impacts
  • impact to estimate at completion
  • should be written by CAM!

A big hammer for a big variance!
24
Sample of Variance Analysis
25
Basic Concepts of Analysis
  • or
  • figuring out where the problems are

26
Looking Forward
PAST PRESENT
FUTURE
Are we on schedule? Are we on cost? What are the
significant variances? Why do we have
variances? Who is responsible? What is the trend
to date? What risks have been reduced or
added?
What is the to go plan? How is it
resourced? When will we
finish? What will it cost at the end?
How can we control the trend?
How do we adjust for risk?
We analyze the past performanceto help us
control the future
27
Basic Analysis Techniques
  • Find significant variances
  • eliminate almost complete, just starting, etc.
  • Graph and analyze trends
  • Look at comparative data
  • e.g. cumulative performance vs. projected
    performance
  • Examine written analysis by contractor
  • does it answer why?
  • adequacy of corrective action plans
  • Analysis of schedule trends, critical path
  • Analysis of EAC realism

what are the drivers? what can we do about them?
28
Types of Variances
  • Values can be expressed as either current period
    or cumulative
  • current tends to be more volatile
  • use cum data to show trends
  • Easy rule of thumb
  • negative value BAD positive value GOOD
  • index lt 1.0 BAD index gt 1.0 GOOD
  • Absolute
  • expressed in terms of dollars or hours (e.g.,
    -1,000)
  • may not be able to tell significance from this
    amount
  • Percent
  • relates absolute variance to a base (e.g., -35)
  • shows significance
  • Index
  • compares one value to another in a simple ratio
  • if you are on plan, index 1.00

29
Where are the significant problems?
sorted by CV
30
Graphing Techniques
Overall cost and schedule trend
EAC realism
graphs show overall trend... are you getting
better, or worse?
31
Analysis of Variances
  • CURRENT OR CUM TO DATE
  • Schedule Variance SV () BCWP - BCWS
  • SV () BCWP - BCWS x 100
  • BCWS
  • Cost Variance CV () BCWP - ACWP
  • CV () BCWP - ACWP x 100

  • BCWP

32
Performance Indices
COST PERF INDEX (CPI) BCWP
ACWP SCHED PERF INDEX (SPI) BCWP
BCWS
1.2
GOOD
1.1
TIME
1.0
CPI
.9
SPI
BAD
.8
33
Past and Present Cost Efficiency
  • IS THE CONTRACTOR'S EAC REASONABLE?
  • Compare the CPI to the TCPI-LRE
  • TCPI-EAC Efficiency necessary to complete at
    the contractors estimate
  • WORK
    5000 - 1000 4000
  • BAC-BCWP REMAINING 6400 - 2400
    4000 1.00
  • EAC-ACWP ESTIMATE
  • REMAINING
  • Cumulative performance to date (CPI)
    .42
  • Contractor has been performing at 42 efficiency,
    but expects to
  • complete remaining work at 100 efficiency!

reasonable?
34
Schedule Status
scheduled BCWS x 100
BAC completed BCWP x 100
BAC
compare
example I should have completed 60 of the work
( scheduled), but I only
completed 42
35
Budget Status
budget status spent ACWP x 100
BAC
compare spent vs. complete
example 60 spent vs. 50 complete
36
Mutual Goal Effective Variance Analysis
  • Make it meaningful
  • avoid routine explanations
  • Make it timely
  • Make it streamlined
  • significant variances
  • Make it right
  • work with contractor to get the information we
    need
  • Get the information to the managers
  • Use the information to control the project

make this a mutual goal between
contractor and customer
37
What will be the final cost?
  • Estimate at Completion (EAC)
  • defined as actual cost to date estimate to
    complete
  • contractor develops comprehensive EAC at least
    annually
  • reported by WBS in cost performance report
  • should examine on monthly basis
  • consider the following in EAC generation
  • performance to date
  • impact of approved corrective action plans
  • known/anticipated downstream problems
  • best estimate of the cost to complete remaining
    work

EAC ACWP ETC
38
Need to Estimate Costs for Remaining Work
  • Budgeted Cost for Work Remaining (BCWR)
  • Budgeted, baseline value for remaining work
  • Update estimate of costs for BCWR
  • Can be detailed estimate
  • Can calculate with performance factors (CPI or
    SPI)
  • Assumes performance will continue at same level
    of efficiency
  • Basic formula BCWR / performance factor
  • Example
  • CPI .9
  • BCWR 1,000
  • Estimate to complete 1,000 / .9 1,111

39
Common EAC Formulas
  • Common EAC Formulas
  • EAC BAC
  • CPI
  • ACWPcum Budgeted Cost
    of Work Remaining
  • CPI3
  • ACWPcum Budgeted Cost of Work
    Remaining

  • .5(CPI) .5(SPI)
  • ACWPcum
    Budgeted Cost of Work Remaining

  • CPI SPI

40
Other methods of EAC calculation
  • Grass Roots or formal EAC
  • detailed build-up from the lowest level detail
  • hours, rates, bill of material, etc.
  • Average of statistical formulae
  • Statistical regression
  • Complete schedule risk analysis for remaining
    work, estimate work remaining

41
Past vs. Projected Efficiency
Efficiency needed to achieve EAC
1.0
CPIcum .42
42
Earned Value Enables Realistic Forecasts
CONTRACT BUDGET BASE
24M
COST VARIANCE AT COMPLETE
FORECASTED ACTUALS
BUDGET
20M
SCHEDULE VARIANCE
FORECAST SCHEDULE SLIP
Cost Var
16M
PMB
12M
FORECASTED EARNED VALUE
8M
4M
2
4
6
8
10
12
14
16
18
20
22
TIME PERIODS
TIME
NOW
PROGRAM IS BEHIND SCHEDULE AND OVERRUNNING COST
43
The Box of Uncertainty(courtesy Swedish
Defense Material Administration)
24M
POTENTIAL COST OVERRUN
20M
POTENTIAL SCHEDULE SLIP
16M
PMB
12M
8M
4M
2
4
6
8
10
12
14
16
18
20
22
TIME PERIODS
TIME
NOW
BOX OF UNCERTAINTY SHOWS POTENTIAL RANGE OF COST
OVERRUN AND SCHEDULE SLIP
44
Managing with Earned Value Data
45
Program Manager Responsibilities
  • Assign integrated responsibility to teams
  • Demand accountability
  • Ask tough questions
  • project office
  • contractor
  • Look ahead manage the risks
  • Integrated analysis and reviews
  • EVMS
  • Integrated Master Schedule
  • Risk Plan
  • Manage to the baseline
  • Control statement of work growth
  • Lead assessment of baseline realism
  • Integrated Baseline Review (IBR)
  • Call for realistic estimates

46
Quotes from Project Managers
Are we looking good, or are we in trouble? And,
how do we know?
CAPT Joe Dyer, US Navy F/A-18E/F Program Manager
It forces you to plan, and then to manage to the
plan.
Lt Col Paul Vancheri, US Air Force JSTARS
Production Program Manager
47
Additional Referenceshttp//www.cpm-pmi.orghtt
p//www.acq.osd.mil/pm
48
Summary
  • Be careful to establish correct value for
    reported BCWP (earned value)
  • Set up and maintain system discipline
  • Maintain a realistic baseline
  • Analyze earned value data
  • Calculate a realistic estimate at completion
  • Manage with earned value data
Write a Comment
User Comments (0)
About PowerShow.com