Title: Pavement Type Selection and Alternate Pavement Type Bidding
1Pavement Type Selection andAlternate Pavement
Type Bidding
- An Overview of MDs Experience
Presented at the AASHTO Joint Technical Committee
on Pavements December 7, 2006
Peter Stephanos, Maryland SHA
2Presentation Outline
- Use of Alternate Bids
- Pavement Type Selection
- Why it changed
- How it changed
- How well it is working
- Alternate Bid Experience
- Maryland, Ontario and Missouri
- Summary
3Use of Alternate Bidding
- FHWA traditionally discouraged use of alternate
bids for pavements - FHWA approved a Special Experimental Project for
use of alternate bids in Missouri 1996. - AASHTO recognizes Alternate Bids as a contracting
technique that will be utilized in the 21st
century - Recommended when more than one alternate is
judged equal by an agency and that the least
costly design approach will result from a
competitive bid.
4Use of Alternate Bidding
- Federal Aid policy suggests that alternative
designs are considered for large projects - A life cycle cost economic analysis should be
conducted to compare the total cost of each
alternate. - Alternate bidding should be used when there is no
clear cut choice between two alternates and have
similar life cycle costs - If the alternates do not provide equivalent
designs then an adjustment must be made to the
bid to equate the alternates
5Use of Alternate Bidding
- The following States/Provinces have experience
with alternative bidding - Alabama
- Kentucky
- Louisiana
- Maryland
- Michigan
- Missouri
- Ontario
6Pavement Type SelectionWhy it changed in MD
- Traditionally based on deterministic Life Cycle
Cost process - Used on large new construction and reconstruction
projects - Followed process to select concrete pavement
alternate for 40 million new construction
project - Contested by industry in Nov. 2002, 5 weeks
before advertisement
7Pavement Type SelectionWhy it changed in MD
- Formed Pavement Type Review Team to evaluate
design and alternate selection - Several areas of concern raised by industry
- Pavement section
- LCC inputs (future MR, unit costs, etc.)
- Payment differences
- User delay costs
- Level of adjustment factor
- Provided Final Report in Feb, 2003 with options
8Pavement Type SelectionDevelopment of New
Process for MD
- Formed new team in Feb, 2003 to develop new
Pavement Type Selection Process - Team charged with development of new process by
Feb, 2004 - Team consisted of industry, FHWA, construction,
design, planning, district and pavement SHA staff - Developed new process in Feb, 2004 and revised
process in March, 2005
9Pavement Type SelectionOverview of New Process
- Policy on application of process
- Three tiered approach
- Life cycle cost comparison
- Component analysis
- Innovative contracting
- Probabilistic approach to LCC
- Weighting of component factors based on project
priorities - SHA/FHWA project team formed to make final
decision
10Application Policy
- Evaluated several factors to consider use of new
policy including - Type of work (rehab vs. reconstruction)
- Project costs
- Projects that go through formal planning
- Size of project
- Staff resource levels was a limiting factor in
the number of projects that could be identified
11Application Policy
- All projects developed through the Project
Planning Division ready for design, - and
- Any projects with a construction estimate gt 15
million (with at least 5 million dedicated to
pavement/MOT items) - Estimated to be 6 to 8 projects per year.
12Three Tiered Approach
13Life Cycle Cost Factors
- Based on historical data and expert opinion
- Material unit costs
- Pavement service life
- Construction sequencing
- Construction duration
- General analysis inputs
- Variability represented by average and standard
deviation
14Life Cycle Costs Estimate
Alternate 1 value _at_ 80 probability 16 million
Alternate 2 value _at_ 80 probability 19 million
15Example Input Material Costs
16Example Input Service Life
17Component Analysis
- Cost Factors
- Present worth Agency Costs Initial Future
- Present worth User Delay Costs
- Construction Factors
- Duration of Construction
- Maintenance of Traffic
- Maintenance of Access
- (utilities future maint, material sources,
reliability of construction) - Design and Environment Factors
- Traffic and Geometry
- Adjacent Pavement and Structures
- Environmental Impact
- (community concerns, future planning)
18Example Component Score
19Component Matrix
20Project Experience
21Project Experience
22Summary of Recent Projects
23Industry Comments
- Decision thresholds fixed or flexible?
- Material price fluctuation effect on inputs
- Frequency of Alt Bidding competitive?
- Routine rehab strategies or new?
- Approach to pavement design
- Level of adjustment factor
- Unit of payment for pavement items fair?
24ICC Bid Process
- 2 billion project advertised as 5 major
projects - Design/build project
- Best value selection process
- Design/build contractor designing pavement
- Design performance specifications developed
25ICC Performance Specs
- Requires either a flexible or jointed plain
concrete pavement for mainline and ramps - Requires a 25 year initial structural design life
no adjustment factor - Design constraints set in specification
- Must meet 1993 AASHTO Design
- Must comply with MDSHA Pavement Design Policies
26Ontario Experience
- Use alternate bidding on large projects
- Generally pleased with outcome
- Have advertised and awarded 6 projects to date
- Adjustment factor based on future agency costs
- All 6 projects awarded to concrete bidder
- Adjustment factor was not a factor in any of the
bids - Projects have gone well
- Bids typically lower then conventional bids
27Missouri Experience
- Use alternate bids on all projects longer than 2
lane-miles in length - Developed process to create adjustment with
industry - Have advertised 50 projects
- Adjustment factor based on future agency costs
(45 yrs) - Adjustment factor deciding factor twice since
2003 - Use MEPDG as design methodology
- Pleased with outcome
28Missouri Experience
- 50 Alternate Projects
- 45 Full Depth (655.8 mill)
- 5 Rehabilitation (49.2 mill)
- Full Depth
- 20 Asphalt Awards (296.7 mill)
- 25 Concrete Awards (359.2 mill)
- Rehabilitation
- 1 Asphalt Award (2.6 mill)
- 4 Concrete Awards (46.6 mill)
29Missouri Experience
30Missouri Experience
31Missouri Experience
32Thank You
- Maryland State Highway Administration
- Peter Stephanos Tim Smith
- Director of Materials Technology Pave/Geotech
Division Chief - Phone (410) 321-3100 Phone (410) 321-3110
- Fax (410) 321-3099 Fax (410) 321-3099
- pstephanos_at_sha.state.md.us tsmith2_at_sha.state.md.u
s