Pavement Type Selection and Alternate Pavement Type Bidding - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

Pavement Type Selection and Alternate Pavement Type Bidding

Description:

An Overview of MD's Experience. Presented at the AASHTO Joint Technical Committee on Pavements ... Why it changed in MD. Traditionally based on deterministic ... – PowerPoint PPT presentation

Number of Views:202
Avg rating:3.0/5.0
Slides: 32
Provided by: pstep
Category:

less

Transcript and Presenter's Notes

Title: Pavement Type Selection and Alternate Pavement Type Bidding


1
Pavement Type Selection andAlternate Pavement
Type Bidding
  • An Overview of MDs Experience

Presented at the AASHTO Joint Technical Committee
on Pavements December 7, 2006
Peter Stephanos, Maryland SHA
2
Presentation Outline
  • Use of Alternate Bids
  • Pavement Type Selection
  • Why it changed
  • How it changed
  • How well it is working
  • Alternate Bid Experience
  • Maryland, Ontario and Missouri
  • Summary

3
Use of Alternate Bidding
  • FHWA traditionally discouraged use of alternate
    bids for pavements
  • FHWA approved a Special Experimental Project for
    use of alternate bids in Missouri 1996.
  • AASHTO recognizes Alternate Bids as a contracting
    technique that will be utilized in the 21st
    century
  • Recommended when more than one alternate is
    judged equal by an agency and that the least
    costly design approach will result from a
    competitive bid.

4
Use of Alternate Bidding
  • Federal Aid policy suggests that alternative
    designs are considered for large projects
  • A life cycle cost economic analysis should be
    conducted to compare the total cost of each
    alternate.
  • Alternate bidding should be used when there is no
    clear cut choice between two alternates and have
    similar life cycle costs
  • If the alternates do not provide equivalent
    designs then an adjustment must be made to the
    bid to equate the alternates

5
Use of Alternate Bidding
  • The following States/Provinces have experience
    with alternative bidding
  • Alabama
  • Kentucky
  • Louisiana
  • Maryland
  • Michigan
  • Missouri
  • Ontario

6
Pavement Type SelectionWhy it changed in MD
  • Traditionally based on deterministic Life Cycle
    Cost process
  • Used on large new construction and reconstruction
    projects
  • Followed process to select concrete pavement
    alternate for 40 million new construction
    project
  • Contested by industry in Nov. 2002, 5 weeks
    before advertisement

7
Pavement Type SelectionWhy it changed in MD
  • Formed Pavement Type Review Team to evaluate
    design and alternate selection
  • Several areas of concern raised by industry
  • Pavement section
  • LCC inputs (future MR, unit costs, etc.)
  • Payment differences
  • User delay costs
  • Level of adjustment factor
  • Provided Final Report in Feb, 2003 with options

8
Pavement Type SelectionDevelopment of New
Process for MD
  • Formed new team in Feb, 2003 to develop new
    Pavement Type Selection Process
  • Team charged with development of new process by
    Feb, 2004
  • Team consisted of industry, FHWA, construction,
    design, planning, district and pavement SHA staff
  • Developed new process in Feb, 2004 and revised
    process in March, 2005

9
Pavement Type SelectionOverview of New Process
  • Policy on application of process
  • Three tiered approach
  • Life cycle cost comparison
  • Component analysis
  • Innovative contracting
  • Probabilistic approach to LCC
  • Weighting of component factors based on project
    priorities
  • SHA/FHWA project team formed to make final
    decision

10
Application Policy
  • Evaluated several factors to consider use of new
    policy including
  • Type of work (rehab vs. reconstruction)
  • Project costs
  • Projects that go through formal planning
  • Size of project
  • Staff resource levels was a limiting factor in
    the number of projects that could be identified

11
Application Policy
  • All projects developed through the Project
    Planning Division ready for design,
  • and
  • Any projects with a construction estimate gt 15
    million (with at least 5 million dedicated to
    pavement/MOT items)
  • Estimated to be 6 to 8 projects per year.

12
Three Tiered Approach
13
Life Cycle Cost Factors
  • Based on historical data and expert opinion
  • Material unit costs
  • Pavement service life
  • Construction sequencing
  • Construction duration
  • General analysis inputs
  • Variability represented by average and standard
    deviation

14
Life Cycle Costs Estimate
Alternate 1 value _at_ 80 probability 16 million
Alternate 2 value _at_ 80 probability 19 million
15
Example Input Material Costs
16
Example Input Service Life
17
Component Analysis
  • Cost Factors
  • Present worth Agency Costs Initial Future
  • Present worth User Delay Costs
  • Construction Factors
  • Duration of Construction
  • Maintenance of Traffic
  • Maintenance of Access
  • (utilities future maint, material sources,
    reliability of construction)
  • Design and Environment Factors
  • Traffic and Geometry
  • Adjacent Pavement and Structures
  • Environmental Impact
  • (community concerns, future planning)

18
Example Component Score
19
Component Matrix
20
Project Experience
21
Project Experience
22
Summary of Recent Projects
23
Industry Comments
  • Decision thresholds fixed or flexible?
  • Material price fluctuation effect on inputs
  • Frequency of Alt Bidding competitive?
  • Routine rehab strategies or new?
  • Approach to pavement design
  • Level of adjustment factor
  • Unit of payment for pavement items fair?

24
ICC Bid Process
  • 2 billion project advertised as 5 major
    projects
  • Design/build project
  • Best value selection process
  • Design/build contractor designing pavement
  • Design performance specifications developed

25
ICC Performance Specs
  • Requires either a flexible or jointed plain
    concrete pavement for mainline and ramps
  • Requires a 25 year initial structural design life
    no adjustment factor
  • Design constraints set in specification
  • Must meet 1993 AASHTO Design
  • Must comply with MDSHA Pavement Design Policies

26
Ontario Experience
  • Use alternate bidding on large projects
  • Generally pleased with outcome
  • Have advertised and awarded 6 projects to date
  • Adjustment factor based on future agency costs
  • All 6 projects awarded to concrete bidder
  • Adjustment factor was not a factor in any of the
    bids
  • Projects have gone well
  • Bids typically lower then conventional bids

27
Missouri Experience
  • Use alternate bids on all projects longer than 2
    lane-miles in length
  • Developed process to create adjustment with
    industry
  • Have advertised 50 projects
  • Adjustment factor based on future agency costs
    (45 yrs)
  • Adjustment factor deciding factor twice since
    2003
  • Use MEPDG as design methodology
  • Pleased with outcome

28
Missouri Experience
  • 50 Alternate Projects
  • 45 Full Depth (655.8 mill)
  • 5 Rehabilitation (49.2 mill)
  • Full Depth
  • 20 Asphalt Awards (296.7 mill)
  • 25 Concrete Awards (359.2 mill)
  • Rehabilitation
  • 1 Asphalt Award (2.6 mill)
  • 4 Concrete Awards (46.6 mill)

29
Missouri Experience
30
Missouri Experience
31
Missouri Experience
32
Thank You
  • Maryland State Highway Administration
  • Peter Stephanos Tim Smith
  • Director of Materials Technology Pave/Geotech
    Division Chief
  • Phone (410) 321-3100 Phone (410) 321-3110
  • Fax (410) 321-3099 Fax (410) 321-3099
  • pstephanos_at_sha.state.md.us tsmith2_at_sha.state.md.u
    s
Write a Comment
User Comments (0)
About PowerShow.com