Title: Anthony Creek Soil Bioengineering Demonstration Project


1
Anthony CreekSoil Bioengineering Demonstration
Project
  • Dennis Burns Adam Merritt, WVCA
  • Curtis Kincaid, Landowner

2
Site 1
  • Sloped Banks 21
  • Install Tree Revetment
  • Install ArmorMax System
  • Plant Trees

3
Before Construction
4
Excavating the Stream Banks to a 21 Slope
5
(No Transcript)
6
No Wildlife was Harmed During the Implementation
of this Project
7
Natural Occurring 21 Slope
8
Tree Revetment Anchored into the Stream Bank to
Protect the Toe and Trap Sediment
9
Duckbill Anchors, Rocks, and Post Used to Secure
Tree Revetment
10
Turf Reinforcement Mats Covered the Slope
11
TRMs are Pinned Down and Secured in Place
12
Duckbill Earth Anchors and Trees are Installed
13
Fill is Placed on Tree to Create a Bench for
Sediment Deposition and to Anchor the Toe of the
TRM
14
TRM is Trenched in and Folded Over on the Up
Stream End
15
Silky Dogwood Planted in the TRM
16
Grass Seed was Planted Under and Over Top of the
TRM. Compost was Spread Over the Top to Insure
Seed to Soil Contact
17
Compost Spread over the TRM
18
Before and After
19
Site 2
  • Slope Banks 21
  • Install Cocoanut Blankets
  • Plant Trees

20
BeforeConstruction
21
Severity of the Erosion
22
Excavating the Banks to a 21 Slope Stream
23
Coconut Fiber Erosion Control Blankets Applied to
the Sloped Stream Bank
24
Trees Planted in the Erosion Control Blankets
25
Wildlife Protected in the Stream
26
Before and After
27
Site 3
  • Removed Debris
  • Install Root Wad With Footers
  • Plant Trees

28
Root Wads with Footers Installed in the Stream
Bank
29
Rock and Fill Used to Anchor the Root Wads
30
Fill was Applied above the Root Wads to Bring the
Stream Bank to a 21 Slope
31
Trees, Grass Seed, and Compost was Applied to
Stabilize with Root Structure
32
Before and After