Title: ACTT WORKSHOP
1MDOT
I-94 Acclerated Construction Technology Detroit,
Michigan April 17-19, 2007
ACTT WORKSHOP
2MDOT ACTT WORKSHOP
- UTILITIES/ RAILROAD
- COORDINATION
- Final Presentation
3Utilities/Railroad Coordination
- Team Members
- Marion Leaphart, Utility Director, Coleman-Snow
Consultants, (Retired Utilities Manager, SC DOT) - Veena Jasuja, MDOT, Detroit TSC
- Nick Lefke, MDOT, Lansing, Real Estate
- Bill Stonebrook, MDOT, Lansing, Design
- Steve Rapp, MDOT, Lansing, Design
- Facilitator
- Anu Taneja, MDOT, Lansing, Contract Services
- Notes
- Lynn Venturino, MDOT, Lansing, Design Support
4Utilities
5Designate a full time MDOT utilities coordinator
- Oversee all aspects of utility coordination,
communication, and cooperation during design and
construction - Act as go to person for MDOT, utilities, and
vendors
6Utilize Subsurface Utility Engineering (SUE)
- Have SUE provider available during design and
construction - Update current SUE data
- Utilize SUE deliverables effectively with
stakeholders - Expedites conflict resolution
7Identify and resolve municipal utility issues
- Early and often involvement of municipal
utilities - Early identification of potential show stoppers
- Identify all relocation and proposed new work
- Coordination with stakeholders
8 Identify and resolve private/public utility
issues
- Early and often involvement of private/public
utilities - Early identification of potential show stoppers
- Identify all relocation and proposed new work
- Identify reimbursable relocations
- Advanced utility relocations
- Coordination with stakeholders
9Participate in preliminary engineering costs for
private/public utilities
- Provides incentive to private/public utilities to
cooperate in a timely manner - Increases cooperation during design phase
10Railroads
11 Form Steering Committee of officials from MDOT
and Railroads (RR)
- Authority to make high level decisions
- Expedite RR decision making (i.e. trackage
rights, union work rules, etc.)
12Form a Design Engineering Committee
- Early and often involvement of railroads
- Early identification of design constraints
- Early identification of potential show stoppers
13Provide adequate time for RR coordination in
the MDOT process
- Two year minimum coordination time
- Coordination time begins from submittal of
preliminary plans from MDOT to RR
14Contract with qualified vendor to perform RR
coordination
- Vendor must be knowledgeable in RR operations
- Effective in obtaining RR approvals
- Involve MDOT RR experts in vendor selection
process
15Coordinate at-grade crossings with service roads
- Diagnostic Team Review (DTR) meeting should take
place well in advance of construction, if
required
16Maintenance of RR traffic
- Early and often involvement of RR
- Construct temporary runaround shoo-fly tracks
- Part width bridge construction
- Roll-in/lift-in superstructure
- Build new permanent bridges parallel to existing
RR - Trackage rights agreements between RR during
construction
17Possible elimination of two RR structures over
I-75
18Questions