Onshore Oil - PowerPoint PPT Presentation

1 / 31
About This Presentation
Title:

Onshore Oil

Description:

Emergency Repairs. Geospatial Database. Master Development Plan ... Master development plan (MDP) for 2 or more APDs with common drilling plan, SUPO and POD. ... – PowerPoint PPT presentation

Number of Views:143
Avg rating:3.0/5.0
Slides: 32
Provided by: bder
Category:
Tags: oil | onshore

less

Transcript and Presenter's Notes

Title: Onshore Oil


1
Onshore Oil Gas Order 1
  • BLM/Forest Service Final Rule

2
Onshore Oil Gas Order 1
  • Ken McMurrough
  • NRS BLM, Colorado State Office
  • 303-239-3642 (x3799 fax)
  • hugh_mcmurrough_at_blm.gov
  • Hank Szymanski 303-239-3797
  • Hank_Szymanski_at_blm.gov

3
OverviewOnshore Oil Gas Order No. 1
  • Authority
  • This rule, effective April 6, 2007, revised the
    existing OO1 which supplemented primarily the
    federal regulations at 43 CFR 3162.3 and 3162.5.
  • Purpose - Approval of Operations of Federal and
    Indian Oil and Gas Leases
  • The purpose of OO1 is to state the application
    requirements for the approval of all proposed oil
    and gas and service wells, certain subsequent
    well operations, and abandonment.

4
OverviewOnshore Oil Gas Order No. 1
  • Defines terms
  • Components of APD
  • Time line
  • Approval requirements
  • Split estate
  • Indian leases
  • Reclamation/Abandonment
  • Appeals

5
BackgroundReasons for Revision of Previous Order
  • Leasing Reform Act of 1987
  • Energy Policy Act of 2005
  • Update for Current Practices
  • Split estate policy
  • Cultural wildlife inventory
  • Right of Way coordination
  • Master development plans, directional drilling
  • Best Management Practices

6
BackgroundStatus
  • Proposed rule Published July 2005
  • Energy Policy Act Signed August 2005
  • Further proposed rule Published March 2006
  • Public comments Received nearly 90 from
    industry, interest groups and the public at large
  • Final rule March 7, 2007

7
BackgroundMajor Revisions
  • Process time line
  • Section 366, Energy Policy Act of 2005
  • Requires compliance with applicable law
  • Define terms
  • Complete APD
  • Onsite inspection included
  • Cultural wildlife Inventories not included
  • Geo-referenced well plat

8
BackgroundMajor Revisions (continued)
  • Split estate
  • Operator provides SUPO COAs to surface owner
  • Bond compensation for loss or damages for access
    based on statutory requirements on patented lands
    (min 1000)
  • Onsite inspection
  • 15 day requirement eliminated
  • Onsite required for complete APD
  • Valid period for APD
  • Changed to 2 years with 2 year extension

9
BackgroundControversial Issues
  • Time line
  • Onsite inspection required
  • Required for complete APD
  • NEPA, NHPA, ESA compliance
  • Potential delays no definite time to process
  • APD may be deferred or denied within 30 day after
    complete APD submittal

10
BackgroundControversial Issues (continued)
  • Valid period for APD
  • 2 years with 2 year extension
  • Split estate
  • SUPO COAs provided to surface owner
  • Good Faith Effort vs mandatory notification
  • What is a good faith effort
  • Bonding for access
  • Compensation based on loss or damages or
  • as required by specific statutory authority

11
SpecificsDefinitions, New or Revised
  • Best Management Practices
  • Casual Use
  • COA
  • Complete APD
  • Days
  • Emergency Repairs
  • Geospatial Database
  • Master Development Plan
  • Onsite Inspection
  • Private Surface Owner
  • Reclamation
  • Surface Managing Agency

12
SpecificsGeneral
  • Read the preamble first if you have questions
  • Early notification is new (initial planning
    conference) is voluntary, precede NOS
  • Best Management Practices, something we have been
    doing for decades, are strongly recommended

13
SpecificsNotice Of Staking Option
  • Provides operator opportunity to gather
    information to address site-specific resource
    concerns while preparing the APD package.
  • 10 days after receiving NOS, an onsite inspection
    will be scheduled to take place as soon as
    weather conditions permit.
  • Minimum staking required 1) center stake for
    proposed well, 2) 2 reference stakes, 3) flagged
    access centerline.
  • BLM will invite surface managing agency (SMA) and
    surface owner, if applicable.

14
SpecificsGeneral
  • Geospatial database, required for well plat
  • Operator must make a Good Faith Effort 1)
    notify the private surface owner for access, 2)
    provide operator with SUPO COA, 3) obtain
    surface access agreement
  • Casual Use further explained, includes surveying
    and staking

15
Specifics9-point Drilling Plan
  • More complete casing and cementing information
  • Added language for directional drilling

16
Specifics12-point Surface Use Plan
  • Geospatial data optional
  • Additional staking required over that used for an
    NOS
  • Certify or Good Faith Effort made to get the SUPO
    to the private surface owner (11)
  • Moved Certification out of SUPO, it now stands
    alone as a required APD component

17
SpecificsBonding
  • Bond increase and phased release (lease bond
    only) are now in the Order
  • BLM requires sufficient bond to restore surface
    adversely affected by lease operations after
    abandonment
  • Authority to require additional bond to be
    applied to off-lease facilities required to
    develop a lease

18
SpecificsNOS Processing Time Line
  • Onsite scheduled within 10 days
  • List of Concerns provided at onsite or within 7
    days
  • Submit APD within 60 days or NOS may be returned

19
SpecificsAPD Processing Time Line
  • 10-Day letter for APD completeness notification
  • Onsite scheduled within 10 days (unless NOS
    onsite conducted)
  • Additional Deficiencies provided at onsite
  • 45 days to submit additional information
  • 30 days for BLM decision after complete APD
    submitted
  • Decision to Approve, Defer, or Deny APD

20
SpecificsAPD Permit Deferral
  • BLM will provide the operator a list of pending
    actions and a schedule for completion before
    final APD approval can be granted
  • BLM will inform the operator of the actions they
    could take to assist
  • The operator has 2 years to take the specified
    actions
  • BLM will approve the APD within 10 days after all
    actions are complete

21
SpecificsAPD Approval
  • FS has NEPA responsibility on the Forest
  • On the Forest, BLM should be a cooperating agency
    (Co-lead) and adopt the NEPA analysis as a basis
    for its decision
  • On Indian lands, BLM may be a cooperating agency
    (Co-lead) OR may adopt the NEPA analysis prepared
    by the BIA

22
SpecificsMaster Development Plans
  • Eliminated Master Drilling Plans
  • Master development plan (MDP) for 2 or more APDs
    with common drilling plan, SUPO and POD.
  • Subsequent APDs can reference the MDP for NEPA
    analysis
  • Each subsequent proposed well must have a survey
    plat and an APD Form (3160-3)

23
SpecificsOperator Responsibilities
  • Section IV, General Operating Requirements
    Operator responsibilities discussed - includes
    requirements for
  • NEPA
  • General operations
  • Protecting cultural historic resources
  • Protecting endangered species their habitat
  • Surface protection
  • Safety
  • Completion reports

24
SpecificsCompletion Reports
  • Well logs submitted in electronic format
  • For directional wells be sure to report the
    bottom hole lat/long locations (at top of
    production interval and at total depth)

25
SpecificsPrivate Surface
  • Certify to BLM that a Good Faith Effort has been
    made to notify the private surface owner before
    entry
  • Certify to BLM that a surface use or access
    agreement has been reached or a Good Faith Effort
    made
  • Certify copy of SUPO COA provided to private
    surface owner or a Good Faith Effort made

26
SpecificsSubsequent Operations
  • NOI required for new construction,
    re-construction, or alterations that result in
    new disturbance.
  • If no existing approved plan exists, an NOI must
    be filed approved by the BLM. New field
    inspection may be required additional cultural
    or biological inventories may be required.
  • Split Estate - Operator must certify that good
    faith effort made to provide private surface
    owner a copy of any proposal for new surface
    disturbance.

27
SpecificsWell Conversions
  • Order includes a more complete explanation of
    well conversions
  • Added a section on conversion to an injection well

28
SpecificsWaivers, Exceptions, Modifications
  • Waiver Permanent removal of lease stipulation.
  • Exception Case-by-case exemption from lease
    stipulation.
  • Modify Permanent change to lease stipulation
  • Request should also include information to
    support that the stipulation no longer justified
    or the proposed operation would not cause
    unacceptable impacts.

29
SpecificsAbandonment
  • 6 months to complete earthwork (weather
    permitting) after well completion/plugging
  • May be difficult on multi-well pad
  • An agreement between the SMA or private surface
    owner and the operator necessary before assuming
    improvements (roads, pads, other)

30
SpecificsAppeals
  • FS SUPO subject to FS appeal requirements
  • BIA decisions subject to BIA appeal requirements

31
Thoughts, Comments?
  • Onshore Oil and Gas Order Number 1, Approval of
    Operations
  • Federal Register, Volume 72, Page 10308-10338
    (72FR10308), Wednesday, March 7, 2007
  • Effective May 7, 2007
Write a Comment
User Comments (0)
About PowerShow.com