Title: Project Organization and Budget Issues U'S' CMS Software and Computing Project Lothar A T Bauerdick,
1Project Organization and Budget IssuesU.S. CMS
Software and Computing ProjectLothar A T
Bauerdick, FermilabProject Manager
- DOE/NSF Review Nov 27-30, 2001
2Project Organization
JOG LHC Program Office LHC Project Office
DOE/NSF Review Chair Glen Crawford
Project Management Group (PMG) Chair Ken
Stanfield PMG for SC Chair Mike Shaevitz
Fermilab Project Oversight
Software and Computing Project L1 Project
Manager LATBauerdick/Fermilab L.Taylor/NEU deputy
SCOP Chair Ed Blucher
U.S. CMS Advisory Software and Computing
Board (USASCB)chair I.Gaines/Fermilab
Core Applications Software Project L2
Manager I.Fisk/UCSD
User FacilitiesProject L2 Manager V.ODell/Fermi
lab
Physics Reconstruction and Selection Detector
Software Groups
3Project Organization
- All the Managers are on board
- latest addition Project Engineer Bakul Banerjee
- All the committees are working
- ASCB for contact with CMS collaboration entities
- PMG for project oversight
- We are reporting regularly on progress and status
- successful metric reporting effort in FTE vs the
WBS - more work on milestones to even more closely
track the project - We are going for the first MOU/SOW to
sub-contract CAS effort to Universities - Drafts for SOW exist
4Managerial Issues w/ NSF Proposal
- NSF Funds are directed at Project(s)
- U.S. CMS SC Project and U.S. CMS Construction
Project - Project Management allocates Funds
- Funds being administered by a NSF Lead
Institution (PI) - U.S. CMS recommends that Northeastern University
should do that - Northeastern has considerable NSF experience
- Do already have a working administration for NSF
funds for U.S. CMS - handles all NSF funds for the Construction
Project - handles NSF software (supplementary) funds (in
SC project) - a lot of accumulated group experience
- 1 FTE of administrative support (on-project)
- NEU already has key managerial and technical
roles in SC - Will use Northeastern administrative service for
new NSF proposal - MO and SC Projects have very similar
administrative needs to Construction Project - Procedure can be fine-tuned as required
5Existing Northeastern Admin.
FNAL US-CMS project office PMG oversight
US-CMS Institutes
DOE
SOWs
North- eastern
NSF
- All funds allocated by US-CMS project
- Only then are they released by NEU
- Tracking data to US-CMS project office
- Valuable cross-check for NSF (NEU and FNAL)
- N.B. a lot of bureaucratic details in all these
connections
6Administration of NSF Funds
- NSF Funds will be received by lead institution
of PI - NSF Funds are allocated to U.S. CMS institutions
by project management - following the procedures as outlined in the PMP
- including SOW to be signed by the U.S. CMS
groups - NSF Funds are being released by subcontracting,
via invoicing - invoices need signature by project management
- accounting is done by WBS,
- The administrative organization to support this
is part of the Project Office(s) - Separate dedicated account for project
fundsespecially with part of the funds being
transferred to CERN - Administrative Assistant at lead inst. to support
accounting, invoicing, reporting - There is also a role for the PI in the
administration of fundse.g. negotiations with
Universities, interaction with NSF,
support for reports and reviews
7Scope Preparation for the LHC Research Program
- Defined Scope and Worked Out Budget ? WBS
- Build the software systems for CMS
- Fulfill commitments towards CMS support U.S.
specific needs - Build a strong Tier-1 center at Fermilab RD,
Equipment, Staff - As part of our obligation towards building the
CMS computing infrastructure - To enable full U.S. access to LHC physics
dataand to provide sufficient resources to do
physics analysis in the U.S. - Empower Universities to be full participants in
the LHC Research Program - Tier-2 centers equipment and operations
- Support Distributed Infrastructure Grid Services
and related RD - Education and Outreach as part of the NSF
proposal - Project Office, Management Reserve
- Defined Schedule ? Major Milestones
- DAQ TDR and HLT studies/PRS groups now to 2002
- 5 Data Challenge and CCS TDR end of 2003,
Physics TDR end of 2004 - 20 Data Challenge and start of facility
deployment end of 2004 - Start of Physics in 2006
8Installed Capacity Tier-1 Facility
5 DC RD Tier-1 System
20 DC Prototype Tier-1 System
Fully Functional Facilities At 40 Capacity
for Physics
9Tier-1/2 RD Systems SC TDR
- Milestones CCS TDR U.S. CMS UF RD Systems
(FY2002/3)
10Prototype Tier-1/2 20 Data Challenge
- Milestone 20 DC, U.S. CMS UF pTier-1/2 System
(5 system)
1140 Capacity Tier1/2 LHC Pilot/Physics Run
- U.S. CMS UF Milestones fully functional Tier-1/2
Systems
12NSF Proposal
- CMS and ATLAS have submitted a proposal to the
NSF - Empowering Universities Preparation of LHC
Research Program - Means to get NSF funding of SC (and MO) to CMS
- Scope SC and MO/upgrade RD, 8M in 2006
- Unclear to which program we will be submitting
- Time table unclear (start of funding supposed to
be in 2002) - DOE/NSF review in November part of the reviewing
process (of the SC part) - Split CMS/ATLAS assumed to be 50/50, also for MO
- Unclear funding profile, but use existing advise,
scaled to 8M in 2006 - Putting SC and MO into one proposal gives has
two projects addressing - Includes Education and Outreach, Broad impact
- This is a big step forward for CMS, thanks to
the people at the NSF
13NSF Funding through Grid Projects
- Budget for the GriPhyN and iVDGL projects funded
by the NSF. Shown is the total project budget and
the part that is going directly to Universities
involved in CMS. - GriPhyN (NSF-ITR) and iVDGL (NSF-MPS)
14Tier-2 Equipment Costs
- Deployment cost of U.S. CMS Tier-2 centers over
time. The RD phase occurs until 2003, and the
pilot starts in 2004. The underlined figures show
the beginning of real Tier-2 operations, which
occur in different years as the Tier-2 centers
are phased in.
15Tier-2 Labor Effort
- Cost of support personnel (in FY2002k) for the
Tier-2 centers over time. Part of the personnel
costs for the RD and prototyping phase (two
prototype centers) is funded out of iVDGL. The
cost for central staff is also shown.
16CAS Labor Effort
- Estimated personnel requirements for the U.S. CMS
Core Application Software efforts, including
U.S.-specific support. Shown is the total U.S.
CMS SC effort, the part requested from the NSF,
and the corresponding cost for the NSF part,
including personnel cost and associated support,
such as travel, desktops, training and software
licenses
17NSF Proposal Budget
- All numbers are given in thousand FY2002 dollars,
except the grand total, which contains an
escalation of 3 per year. Total costs are 22.8M
18NSF Proposal Funding Profile
- Numbers for each category are in FY2002k, an
escalation of 3 per year is shown separately.
Total costs are 22.8M
19UF Equipment Costs
- Detailed Information on Tier-1 Facility Costing
- See Document in Your Handouts!
- All numbers in FY2002k
20Installed Capacity Tier-1 Facility
5 DC RD Tier-1 System
20 DC Prototype Tier-1 System
Fully Functional Facilities At 40 Capacity
for Physics
21UF Manpower Needs
- Detailed Information see UF WBS document in your
Handouts - These numbers come from the resource-loaded WBS
22UF Manpower Profile
23Total Project Costs
24Budget and DOE/NSF Guidance Profile
25Budget and DOE/NSF Proposal Profile
26DOE and NSF Profiles
27Total Integrated Project Costs
28Cost Variance vs Guidance
29Variance vs DOE Guidance, NSF Proposal
30Funding Status FY2001
- Received 1500k from DOE in April
- 500k labeled as Equipment funds
- Tier-1 upgrade, see V.ODells talk
- 500k Loan from Construction Project
- Charge PPD budget code by reporting CAS
engineering efforts - Received additional 285k from DOE in August
- Allocated to Tier-1 equipment procurements
- Received funding from NSF for 3rd engineer in
October 2001
31Total FTE Spent on UF in FY2001
- Total FTE funded in FY2001 was 4.05!
- see Quarterly Reports
32Total FTE on CAS in FY2001
- Total FTE funded was 7.75
- see Quarterly Reports
33Allocation of DOE Funds in FY2002
- Total budget from the DOE in FY2002 2.5M
- partly out of a line item, partly out of PKs
funds, and the rest out of OFallons reserve - Continue the (DOE) CAS effort at the same level
as this year. - keep the staff of 6 FTE
- 2 FTE at Caltech, 1 FTE at UCDavis, 1 FTE at
Princeton, 2 FTE at Fermilab - In addition we are increasing the NSF funded CAS
effort - 2 FTE at Northeastern 1 more to be hired at NEU
(job advertised!) - New proposal has one additional FTE in 2002
- Ramp up the User Facility FTEs by 1 FTE
- One more hire will bring us to 5 CPs at Fermilab.
There will be continued additional effort of
about 2 FTE from guest scientists and engineers,
bringing the total effort to about 7 FTE (5th CP
Bill Tanenbaum started last month). - This leaves us short of 4.5 FTE from the total
11.5 FTE needed according to Nov WBS. This is
accommodated by stretching the necessary RD.
34Allocation of DOE Funds in FY2002 contd
- Ramp up the User Facility Equipment at Fermilab
with a FY2002 allocation of 445k. - The project has spent the FY2001 allocation of
410k, after that in FY2002 we are investing
in total 630 at the Tier-1 - There is a quite detailed hardware plan, which is
documented in the WBS, see V.ODells talk in the
UF breakout session - Staff project office with 1 FTE
- Bakul Banerjee started last week as our Project
Engineer - Leave a management reserve of nominal 10.
- Short fallings are already identified,also
reserve for Construction Project request for
pay-back,in case DOE fails to identify the funds
to pay back last years shortcomings
35Allocation of DOE Funds
- All DOE funds are to be allocated to
FermilabFTEs at Caltech, UC Davis, Princeton
will get sub-contracted from Fermilab. - In the process of writing the SOW to support that
(Princeton U. first) - The "baseline" costs for a DOE CAS CP this year
is set to 150k - we have input from the institutes what is
actually needed - small differences between the institutes
- fine adjustments acc. to the actual needs will be
done - Procedures as described in the PMP
- The subcontract needs to be supported by an MOU
and a yearly SOW - The CAS L2 will start negotiating those
- DOE and Project Oversight is completely on board
with this
36FY2002 Allocation Request to DOE
- FY2002 DOE Funding Allocation Request Break Out
- UF Labor costs 795k
- CAS labor costs 870k
- PO labor costs 150k
- Management Reserve 240k
- UF Equipment 445k
- Total 2500k to be allocated to Fermilab
- The first DOE FinPlan will have half of this sum,
i.e. 1.25M. - this should be used as operations money, mostly
to take care of labor costs, - the equipment part of 445 should be part of the
next batch.
37NSF Funds in FY2002
- No clear time table for NSF proposal exist yet
- Our expectation are
- 3 FTE for CAS at NEU
- the iVDGL funding to run Tier-2 prototypes
- The 500k to pay for the Tier-2 prototype
equipment - the rest as requested in the proposal
- One more CAS FTE
- Some funds for pT2 support personnel (300k)
- In total 2M from the NSF
- We also NEED to cover 1st pT2 center at
Caltech/UCSD
38Request for NSF Funds for pTier2 2000/2001
- Equipment Costs for the prototype Tier-2
installations at Caltech and UCSD unfortunately
still for the funding from the NSF - Following guidance from NSF, CMS requested a
total of 500K for the Californian prototype
Tier2 facility in FY2001 - 300k for initial equipment
- 50k for maintenance and upgrades in 2001
- 150k for personnel
- Actually committed/spent are
- 189k for equipment at Caltech
- 175k for equipment at UCSD
- 36 for effort at Caltech
- 18k for effort at UCSD this totals to 418,
and more funds for equipment and personnel needed - BTW currently unbalance in NSF funding for ATLAS
vs CMS
39FY2003 Allocation
40Budget Issue in FY2003
- Shortfall of 1M in FY2003
- Not fully covered by the reserve, as we have to
pay back 500k loan - Request to get this from DOE to help with the RD
phase! - Or advance from NSF (original guidance was
2M!) - Otherwise need to delay some of the hiring for UF
some more
41Conclusions
- Self-Consistent baseline Project Plan
- Scope CAS UF, Tier-1 Tier-2
- CAS provides 25 of software engineering effort
towards CCS (total 13 FTE) - Functional Prototypes ? Fully Functional Software
- Checkpoints CCS TDR 2003 and Physics TDR in 2004
- UF 40 capacity computing facilities for physics
in 2006, 100 in 2007 - ready for physics in low-lumi run for 2006
- Get there by a series of milestones
- Prototypes, Data Challenges and Technical Design
Reports - RD Systems for Tier-1 and Tier-2 ? 5 Data
Challenge ? CCS TDR - Prototype Tier-1 and pilot Tier-2 ? 20 Data
Challenge ? UF TDR - Budget is very tight, contingency is in the Scope
? Build to Cost - Need some flexibility early 1M in FY2003
- additional funding for 20 data challenge in
FY2004 extremely valuable - This plan should be the baseline to a successful
LHC Research Phase