Project Management 406: Implementing and Managing Projects - PowerPoint PPT Presentation

1 / 16
About This Presentation
Title:

Project Management 406: Implementing and Managing Projects

Description:

LEHIGH U N I V E R S I T Y College of Education & College of Business and Economics Project Management 406: Implementing and Managing Projects – PowerPoint PPT presentation

Number of Views:690
Avg rating:3.0/5.0
Slides: 17
Provided by: SamGr
Category:

less

Transcript and Presenter's Notes

Title: Project Management 406: Implementing and Managing Projects


1
LEHIGH U N I V E R S I T Y
College of Education College of Business and
Economics
  • Project Management 406 Implementing and Managing
    Projects
  • Module 13 Procurement Solicitation Overview

2
Agenda
  • Overview of Procurement Process
  • Understanding the PMBOK Model 12.3 Solicitation
  • Advertising and Bidder Conferences
  • Solicitation Considerations
  • Summary

3
Overview of Procurement Cycle
4
Procurement Common Principles
  • Acquisition of goods and or services
  • Complexity can vary greatly
  • office supplies
  • Proprietary offering consulting, software,
    Turnkey
  • Key concept is balancing risk between buyer and
    supplier
  • uniqueness of product
  • Product/service definition
  • Contract type
  • Buyer may pursue corporate, project, or
    combination procurement strategy
  • Corporate or project policies define specific
    work process but should follow a fairly typical
    cycle

5
Procurement Cycle Terminology
Kerzner PMBOK
Requirement Cycle 12.1 Procurement Planning
Requisition Cycle 12.2 Solicitation Planning
Solicitation Cycle 12.3 Solicitation
Award Cycle 12.4 Source Selection
Contract Administration Cycle 12.5 Contract Administration
6
PMBOK Model of 12.3 Solicitation
7
PMBOK Executing Processes
Core Processes
Facilitating Processes
8
12.3 Inputs
  • Procurement Documents
  • IFB, RFP, RFQ
  • Statement of Work
  • Describe form of Response
  • Required Contractual provisions
  • Qualified Sellers lists
  • Company standard list
  • Project may have to qualify considering
    statement of qualifications, financials,
    references, facility visit, customer visits

9
12.3 Outputs
  • Proposals
  • Supplier documents describing ability to provide
    requested product/service
  • Might include presentations or demonstrations

10
12.3 Tools and Techniques
  • Advertising
  • Bidder Conferences

11
Advertising and Bidder Conferences
12
Advertising
  • Most common in Government/Public Projects
  • Often sealed bids
  • Advertise package available to interested parties
  • Provide brief description, timelines, process
  • Might advise potential suppliers

13
Bidder Conferences
  • Contractor or pre-bid conference
  • Meeting to clarify meaning of work
  • All suppliers maintain equal footing Could
    include site visit/inspection
  • May require issuance of additional information

14
Solicitation Considerations
15
Solicitation Considerations
  • Make SOW as specific as possible minimize
    changes
  • Include requirements (operational definitions)
  • May invite alternate bids
  • Ensure clear understanding of risk ownership
  • Might request two packages technical and
    commercial
  • Rarely find perfect solutions

16
Summary
  • Reviewed Project Procurement Process
  • Understand the PMBOK Model of 12.3 Solicitation
    Process including tools
  • Reviewed Advertising and Bidder Conferences
  • Discussed solicitation considerations
Write a Comment
User Comments (0)
About PowerShow.com