Chapter 2: The Project Management in Context of Organization Environment - PowerPoint PPT Presentation

1 / 102
About This Presentation
Title:

Chapter 2: The Project Management in Context of Organization Environment

Description:

Chapter 2: The Project Management in Context of Organization Environment 303KM Project Management * 303KM Project management 4. Project Control Management by ... – PowerPoint PPT presentation

Number of Views:237
Avg rating:3.0/5.0
Slides: 103
Provided by: Cit5
Category:

less

Transcript and Presenter's Notes

Title: Chapter 2: The Project Management in Context of Organization Environment


1
Chapter 2The Project Management in Context of
Organization Environment
2
1 Systems View of Project Management
  • A systems approach emerged in the 1950s to
    describe a more analytical approach to management
    and problem solving
  • Three parts include
  • Systems philosophy View things as systems,
    interacting components working within an
    environment to fulfill some purpose
  • Systems analysis problem-solving approach
  • Systems management Address business,
    technological, and organizational issues before
    making changes to systems

3
Figure 2-1. Three Sphere Model for Systems
Management
4
2 Understanding Organizations
Structural frame Focuses on roles and
responsibilities, coordination and control.
Organizational charts help define this frame.
Human resources frame Focuses on providing
harmony between needs of the organization and
needs of people.
Political frame Assumes organizations are
coalitions composed of varied individuals and
interest groups. Conflict and power are key
issues.
Symbolic frame Focuses on symbols and meanings
related to events. Culture is important.
5
4 Recognize the Importance of Project Stakeholders
  • Recall that project stakeholders are the people
    involved in or affected by project activities
  • Project managers must take time to identify,
    understand, and manage relationships with all
    project stakeholders
  • Using the four frames of organizations can help
    meet stakeholder needs and expectations
  • Senior executives are very important stakeholders

6
Why Have Project Phases and Management Reviews?
  • A project should successfully pass through each
    of the project phases in order to continue on to
    the next
  • Management reviews (also called phase exits or
    kill points) should occur after each phase to
    evaluate the projects progress, likely success,
    and continued compatibility with organizational
    goals

7
6 Aligning Projects with Business Strategy
  • Most organizations cannot undertake most of the
    potential projects identified because of resource
    limitations and other constraints.
  • An organizations overall business strategy
    should guide the project selection process and
    management of those projects.

8
Strategic Planning
  • Strategic planning involves determining long-term
    objectives by analyzing the strengths and
    weaknesses of an organization, studying
    opportunities and threats in the business
    environment, predicting future trends, and
    projecting the need for new products and
    services.
  • Strategic planning provides important information
    to help organizations identify and then select
    potential projects.

9
SWOT Analysis
  • SWOT analysis involves analyzing Strengths,
    Weaknesses, Opportunities, and Threats.
  • It can help you identify potential projects, as
    is shown in the example about four people trying
    to start a new business.

10
7 Four-Stage Strategic Planning Process for
Project Selection
  • Organizations often follow a detailed planning
    process for project selection.
  • The figure shows a four-stage planning process
    for selecting projects.
  • It is very important to start at the top of the
    pyramid to select projects that support the
    organizations business strategy.

11
Methods for Selecting Projects
  • Discuss more on Integration management e.g.
  • Focus on competitive strategy and broad
    organizational needs.
  • Perform net present value analysis or other
    financial projections.
  • Use a weighted scoring model.
  • Implement a balanced scorecard.
  • Address problems, opportunities, and directives.
  • Consider project time frame.
  • Consider project priority.

12
Focusing on Competitive Strategy and Broad
Organizational Needs
  • Competitive strategies
  • Cost leadership Attract customers primarily
    because products or services are inexpensive.
    Examples include Wal-Mart and McDonald.
  • Focus Develop products and services for a
    particular market niche. Examples include
    Starbucks Coffee and most skin-care product
    shops.
  • Broad organizational needs People agree there is
    a need for a project, they will make funds
    available, and there is a strong will to make the
    project succeed.

13
Chapter 4 Project Integration Management
14
Project Integration Management Processes
  1. Develop the project charter. (3)
  2. Develop the preliminary project scope statement
    (4)
  3. Develop the project management plan (5)
  4. Direct and manage project execution (6)
  5. Monitor and control the project work (7)
  6. Perform integrated change control (8)
  7. Close the project (9)

15
2.1 Financial Analysis of Projects
  • Financial considerations are often an important
    aspect of the project selection process.
  • Three primary methods for determining the
    projected financial value of projects
  • Net present value (NPV) analysis
  • Return on investment (ROI)
  • Payback analysis

16
3 Project Charters
  • After deciding what project to work on, it is
    important to let the rest of the organization
    know.
  • A project charter is a document that formally
    recognizes the existence of a project and
    provides direction on the projects objectives
    and management.
  • Key project stakeholders should sign a project
    charter to acknowledge agreement on the need and
    intent of the project a signed charter is a key
    output of project integration management.

17
4 Preliminary Scope Statements
  • A scope statement is a document used to develop
    and confirm a common understanding of the project
    scope.
  • It is an important tool for preventing scope
    creep
  • The tendency for project scope to keep getting
    bigger.
  • A good practice is to develop a preliminary or
    initial scope statement during project initiation
    and a more detailed scope statement as the
    project progresses.

18
5 Project Management Plans
  • A project management plan is a document used to
    coordinate all project planning documents and
    help guide a projects execution and control.
  • Plans created in the other knowledge areas are
    subsidiary parts of the overall project
    management plan.

19
6 Project Execution
  • Project execution involves managing and
    performing the work described in the project
    management plan.
  • The majority of time and money is usually spent
    on execution.
  • The application area of the project directly
    affects project execution because the products of
    the project are produced during project
    execution.

20
7 Monitoring and Controlling Project Work
  • Changes are inevitable on most projects, so its
    important to develop and follow a process to
    monitor and control changes.
  • Monitoring project work includes collecting,
    measuring, and disseminating performance
    information.
  • Two important outputs of monitoring and
    controlling project work include recommended
    corrective and preventive actions.

21
8 Integrated Change Control
  • Three main objectives are
  • Influence the factors that create changes to
    ensure that changes are beneficial.
  • Determine that a change has occurred.
  • Manage actual changes as they occur.
  • A baseline is the approved project management
    plan plus approved changes.

22
9 Closing Projects
  • To close a project, you must finalize all
    activities and transfer the completed or
    cancelled work to the appropriate people.
  • Main outputs include
  • Administrative closure procedures.
  • Contract closure procedures.
  • Final products, services, or results.
  • Organizational process asset updates.

23
Chapter 5 Project Scope Management
24
Table 5.1. Sample Project Charter
25
Table 5.1. Sample Project Charter (contd)
26
3 Scope Definition and theProject Scope Statement
  • The preliminary scope statement, project charter,
    organizational process assets, and approved
    change requests provide a basis for creating the
    project scope statement.
  • As time progresses, the scope of a project should
    become clearer and more specific.

27
Creating the Work Breakdown Structure (WBS)
  • A WBS is a deliverable-oriented grouping of the
    work involved in a project that defines the total
    scope of the project.
  • A WBS is a foundation document that provides the
    basis for planning and managing project
    schedules, costs, resources, and changes.
  • Decomposition is subdividing project deliverables
    into smaller pieces.

28
The WBS Dictionary and Scope Baseline
  • Many WBS tasks are vague and must be explained in
    more detail so people know what to do and can
    estimate how long the work will take and what it
    will cost.
  • A WBS dictionary is a document that describes
    detailed information about each WBS item.
  • The approved project scope statement and its WBS
    and WBS dictionary form the scope baseline, which
    is used to measure performance in meeting project
    scope goals.

29
Advice for Creating a WBS and WBS Dictionary
  • A unit of work should appear in only one place in
    the WBS.
  • The work content of a WBS item is the sum of the
    WBS items below it.
  • A WBS item is the responsibility of only one
    individual, even though many people may be
    working on it.
  • The WBS must be consistent with the way in which
    work is actually going to be performed it should
    serve the project team first, and other purposes
    only if practical.
  • Project team members should be involved in
    developing the WBS to ensure consistency and
    buy-in.
  • Each WBS item must be documented in a WBS
    dictionary to ensure accurate understanding of
    the scope of work that is included and not
    included in that item.
  • The WBS must be a flexible tool to accommodate
    inevitable changes while properly maintaining
    control of the work content in the project
    according to the scope statement

30
5 Scope Verification
  • It is very difficult to create a good scope
    statement and WBS for a project.
  • It is even more difficult to verify project scope
    and minimize scope changes.
  • Many IT projects suffer from scope creep and poor
    scope verification (see What Went Wrong?).

31
6 Scope Control
  • Scope control involves controlling changes to the
    project scope.
  • Goals of scope control are to
  • Influence the factors that cause scope changes.
  • Ensure changes are processed according to
    procedures developed as part of integrated change
    control.
  • Manage changes when they occur.
  • Variance is the difference between planned and
    actual performance.

32
Suggestions for Reducing Incomplete and Changing
Requirements
  • Develop and follow a requirements management
    process.
  • Use techniques such as prototyping, use case
    modeling, and JAD to get more user involvement.
  • Put requirements in writing and keep them
    current.
  • Create a requirements management database for
    documenting and controlling requirements. Conduct
    adequate testing throughout the project life
    cycle.
  • Review changes from a systems perspective.
  • Emphasize completion dates to help focus on
    whats most important.
  • Allocate resources specifically for handling
    change requests and enhancements.

33
Chapter 6Project Time Management
34
Critical Path Method (CPM)
  • CPM is a network diagramming technique used to
    predict total project duration.
  • A critical path for a project is the series of
    activities that determines the earliest time by
    which the project can be completed.
  • The critical path is the longest path through the
    network diagram and has the least amount of slack
    or float.
  • Slack or float is the amount of time an activity
    can be delayed without delaying a succeeding
    activity or the project finish date.

35
Calculating the Critical Path
  • Develop a good network diagram.
  • Add the duration estimates for all activities on
    each path through the network diagram.
  • The longest path is the critical path.
  • If one or more of the activities on the critical
    path takes longer than planned, the whole project
    schedule will slip unless the project manager
    takes corrective action.

36
3 Network Diagrams
  • Network diagrams are the preferred technique for
    showing activity sequencing.
  • A network diagram is a schematic display of the
    logical relationships among, or sequencing of,
    project activities.
  • Two main formats are the arrow and precedence
    diagramming methods.

37
Figure 6-2. Sample Activity-on-Arrow (AOA)
Network Diagram for Project X
38
Calculating the Critical Path
  • Develop a good network diagram.
  • Add the duration estimates for all activities on
    each path through the network diagram.
  • The longest path is the critical path.
  • If one or more of the activities on the critical
    path takes longer than planned, the whole project
    schedule will slip unless the project manager
    takes corrective action.

39
Figure 6-8. Determining the Critical Path for
Project X
40
Using Critical Path Analysis to Make Schedule
Trade-offs
  • Free slack or free float is the amount of time an
    activity can be delayed without delaying the
    early start of any immediately following
    activities.
  • Total slack or total float is the amount of time
    an activity can be delayed from its early start
    without delaying the planned project finish date.
  • A forward pass through the network diagram
    determines the early start and finish dates.
  • A backward pass determines the late start and
    finish dates.

41
Chapter 7Project Cost Management
42
Basic Principles of Cost Management
  • Tangible costs or benefits are those costs or
    benefits that an organization can easily measure
    in dollars.
  • Intangible costs or benefits are costs or
    benefits that are difficult to measure in
    monetary terms.
  • Direct costs are costs that can be directly
    related to producing the products and services of
    the project.
  • Indirect costs are costs that are not directly
    related to the products or services of the
    project, but are indirectly related to performing
    the project.
  • Sunk cost is money that has been spent in the
    past when deciding what projects to invest in or
    continue, you should not include sunk costs.

43
Basic Principles of Cost Management
  • Learning curve theory states that when many items
    are produced repetitively, the unit cost of those
    items decreases in a regular pattern as more
    units are produced.
  • Reserves are dollars included in a cost estimate
    to mitigate cost risk by allowing for future
    situations that are difficult to predict.
  • Contingency reserves allow for future situations
    that may be partially planned for (sometimes
    called known unknowns) and are included in the
    project cost baseline.
  • Management reserves allow for future situations
    that are unpredictable (sometimes called unknown
    unknowns).

44
5 Earned Value Management (EVM)
  • EVM is a project performance measurement
    technique that integrates scope, time, and cost
    data.
  • Given a baseline (original plan plus approved
    changes), you can determine how well the project
    is meeting its goals.
  • You must enter actual information periodically to
    use EVM.
  • More and more organizations around the world are
    using EVM to help control project costs.

45
Earned Value Management Terms
  • The planned value (PV), formerly called the
    budgeted cost of work scheduled (BCWS), also
    called the budget, is that portion of the
    approved total cost estimate planned to be spent
    on an activity during a given period.
  • Actual cost (AC), formerly called actual cost of
    work performed (ACWP), is the total of direct and
    indirect costs incurred in accomplishing work on
    an activity during a given period.
  • The earned value (EV), formerly called the
    budgeted cost of work performed (BCWP), is an
    estimate of the value of the physical work
    actually completed.
  • EV is based on the original planned costs for the
    project or activity and the rate at which the
    team is completing work on the project or
    activity to date.

46
Rate of Performance
  • Rate of performance (RP) is the ratio of actual
    work completed to the percentage of work planned
    to have been completed at any given time during
    the life of the project or activity.
  • Brenda Taylor, Senior Project Manager in South
    Africa, suggests using this approach for
    estimating earned value.
  • For example, suppose the server installation was
    halfway completed by the end of week 1. The rate
    of performance would be 50 percent (50/100)
    because by the end of week 1, the planned
    schedule reflects that the task should be 100
    percent complete and only 50 percent of that work
    has been completed.

47
Earned Value Calculations for One Activity After
Week One
Activity Week 1
Earned Value (EV) 10K 50 5K
Planned Value (PV) 10K
Actual Cost (AC) 15K
Cost Variance EV-AC -10K
Schedule Variance (SV) EV-PV -5K
Cost Performance Index (CPI) EV/AC 33
Schedule Performance Index (SPI) EV/PV 50

48
Table 7-5. Earned Value Formulas
49
Rules of Thumb for Earned Value Numbers
  • Negative numbers for cost and schedule variance
    indicate problems in those areas.
  • A CPI or SPI that is less than 100 percent
    indicates problems.
  • Problems mean the project is costing more than
    planned (over budget) or taking longer than
    planned (behind schedule).

50
Figure 7-4. Earned Value Calculations for a
One-Year Project After Five Months



8K756K
6K/12K 50
RP50 / 75 67
8K 67 5,333
Plot Graph
51
Figure 7-5. Earned Value Chart for Project after
Five Months
If the EV line is below the AC or PV line, there
are problems in those areas.
52
Chapter 8Project Quality Management
53
2 What Is Project Quality Management?
  • Project quality management ensures that the
    project will satisfy the needs for which it was
    undertaken.
  • Processes include
  • Quality planning Identifying which quality
    standards are relevant to the project and how to
    satisfy them.
  • Quality assurance Periodically evaluating
    overall project performance to ensure the project
    will satisfy the relevant quality standards.
  • Quality control Monitoring specific project
    results to ensure that they comply with the
    relevant quality standards.

54
4 Quality Assurance
  • Quality assurance includes all the activities
    related to satisfying the relevant quality
    standards for a project.
  • Another goal of quality assurance is continuous
    quality improvement.
  • Benchmarking generates ideas for quality
    improvements by comparing specific project
    practices or product characteristics to those of
    other projects or products within or outside the
    performing organization.
  • A quality audit is a structured review of
    specific quality management activities that help
    identify lessons learned that could improve
    performance on current or future projects.

55
5 Quality Control
  • The main outputs of quality control are
  • Acceptance decisions
  • Rework
  • Process adjustments
  • Some tools and techniques include
  • Pareto analysis
  • Statistical sampling
  • Six Sigma
  • Quality control charts

56
6.1 Pareto Analysis
  • Pareto analysis involves identifying the vital
    few contributors that account for the most
    quality problems in a system.
  • Also called the 80-20 rule, meaning that 80
    percent of problems are often due to 20 percent
    of the causes.
  • Pareto diagrams are histograms, or column charts
    representing a frequency distribution, that help
    identify and prioritize problem areas.

57
Sample Pareto Diagram
58
Figure 8-2. Normal Distribution and Standard
Deviation
59
6.4 Quality Control Charts and the Seven Run Rule
  • A control chart is a graphic display of data that
    illustrates the results of a process over time.
    It helps prevent defects and allows you to
    determine whether a process is in control or out
    of control.
  • The seven run rule states that if seven data
    points in a row are all below the mean, above the
    mean, or are all increasing or decreasing, then
    the process needs to be examined for non-random
    problems.

60
Quality Control Charts
  • A control chart is a graphic display of data that
    illustrates the results of a process over time.
  • The main use of control charts is to prevent
    defects, rather than to detect or reject them.
  • Quality control charts allow you to determine
    whether a process is in control or out of
    control.
  • When a process is in control, any variations in
    the results of the process are created by random
    events processes that are in control do not need
    to be adjusted.
  • When a process is out of control, variations in
    the results of the process are caused by
    non-random events you need to identify the
    causes of those non-random events and adjust the
    process to correct or eliminate them.

61
The Seven Run Rule
  • You can use quality control charts and the seven
    run rule to look for patterns in data.
  • The seven run rule states that if seven data
    points in a row are all below the mean, above the
    mean, or are all increasing or decreasing, then
    the process needs to be examined for non-random
    problems.

62
Figure 8-3. Sample Quality Control Chart
63
Chapter 9Project Human Resource Management
Information Technology Project Management,Fourth
Edition
64
Figure 9-1. Maslows Hierarchy of Needs
65
Herzbergs Motivational and Hygiene Factors
  • Frederick Herzberg wrote several famous books and
    articles about worker motivation. He
    distinguished between
  • Motivational factors Achievement, recognition,
    the work itself, responsibility, advancement, and
    growth. These factors produce job satisfaction.
  • Hygiene factors Larger salaries, more
    supervision, and a more attractive work
    environment. These factors cause dissatisfaction
    if not present, but do not motivate workers to do
    more.

66
McClellands Acquired-Needs Theory
  • Specific needs are acquired or learned over time
    and are shaped by life experiences. The following
    are the main categories of acquired needs
  • Achievement (nAch) People with a high need for
    achievement like challenging projects with
    attainable goals and lots of feedback.
  • Affiliation (nAff) People with high need for
    affiliation desire harmonious relationships and
    need to feel accepted by others, so managers
    should try to create a cooperative work
    environment for them.
  • Power (nPow) People with a need for power desire
    either personal power (not good) or institutional
    power (good for the organization). Provide
    institutional power seekers with management
    opportunities.

67
Myers-Briggs Type Indicator (MBTI)
  • MBTI is a popular tool for determining
    personality preferences and helping teammates
    understand each other.
  • Four dimensions include
  • Extrovert/Introvert (E/I)
  • Sensation/Intuition (S/N)
  • Thinking/Feeling (T/F)
  • Judgment/Perception (J/P)
  • NTs, or rationals, are attracted to technology
    fields.
  • IT people vary most from the general population
    in their tendency to not be extroverted or
    sensing.

68
Figure 9-6. Sample Resource Histogram
69
Resource Loading
  • Resource loading refers to the amount of
    individual resources an existing schedule
    requires during specific time periods.
  • Helps project managers develop a general
    understanding of the demands a project will make
    on the organizations resources and individual
    peoples schedules.
  • Overallocation means more resources than are
    available are assigned to perform work at a given
    time.

70
Resource Leveling
  • Resource leveling is a technique for resolving
    resource conflicts by delaying tasks.
  • The main purpose of resource leveling is to
    create a smoother distribution of resource use
    and reduce overallocation.

71
Figure 9-8. Resource Leveling Example
72
Benefits of Resource Leveling
  • When resources are used on a more constant basis,
    they require less management.
  • It may enable project managers to use a
    just-in-time inventory type of policy for using
    subcontractors or other expensive resources.
  • It results in fewer problems for project
    personnel and the accounting department.
  • It often improves morale.

73
Chapter 10Project Communications Management
Information Technology Project Management,Fourth
Edition
74
Determining the Number of Communications Channels
  • As the number of people involved increases, the
    complexity of communications increases because
    there are more communications channels or
    pathways through which people can communicate.
  • Number of communications channels n(n-1)
  • 2 where n is the number of
    people involved.
  • e.g. if six people involved, number of
    communications channels 6( 6-1)/2 15

75
Figure 10-1. The Impact of the Number of People
on Communications Channels
76
4. Performance Reporting
  • Performance reporting keeps stakeholders informed
    about how resources are being used to achieve
    project objectives.
  • Status reports describe where the project stands
    at a specific point in time.
  • Progress reports describe what the project team
    has accomplished during a certain period of time.
  • Forecasts predict future project status and
    progress based on past information and trends.

77
Chapter 11Project Risk Management
Information Technology Project Management,Fourth
Edition
78
5. Quantitative Risk Analysis
  • Assess the likelihood and impact of identified
    risks to determine their magnitude and priority.
  • Risk quantification tools and techniques include
  • Probability/impact matrixes
  • The Top Ten Risk Item Tracking
  • Expert judgment

79
Probability/Impact Matrix
  • A probability/impact matrix or chart lists the
    relative probability of a risk occurring on one
    side of a matrix or axis on a chart and the
    relative impact of the risk occurring on the
    other.
  • List the risks and then label each one as high,
    medium, or low in terms of its probability of
    occurrence and its impact if it did occur.
  • Can also calculate risk factors
  • Numbers that represent the overall risk of
    specific events based on their probability of
    occurring and the consequences to the project if
    they do occur.

80
6. Quantitative Risk Analysis
  • Often follows qualitative risk analysis, but both
    can be done together.
  • Large, complex projects involving leading edge
    technologies often require extensive quantitative
    risk analysis.
  • Main techniques include
  • Decision tree analysis
  • Simulation
  • Sensitivity analysis

81
Decision Trees and Expected Monetary Value (EMV)
  • A decision tree is a diagramming analysis
    technique used to help select the best course of
    action in situations in which future outcomes are
    uncertain.
  • Estimated monetary value (EMV) is the product of
    a risk event probability and the risk events
    monetary value.
  • You can draw a decision tree to help find the
    EMV.

82
Figure 11-6. Expected Monetary Value (EMV) Example
83
7. Risk Response Planning
  • After identifying and quantifying risks, you must
    decide how to respond to them.
  • Four main response strategies for negative risks
  • Risk avoidance
  • Risk acceptance
  • Risk transference
  • Risk mitigation

84
Residual and Secondary Risks
  • Its also important to identify residual and
    secondary risks.
  • Residual risks are risks that remain after all of
    the response strategies have been implemented.
  • Secondary risks are a direct result of
    implementing a risk response.

85
Chapter 12Project Procurement Management
Information Technology Project Management,Fourth
Edition
86
Why Outsource?
  • To reduce both fixed and recurrent costs.
  • To allow the client organization to focus on its
    core business.
  • To access skills and technologies.
  • To provide flexibility.
  • To increase accountability.

87
Types of Contracts
  • Different types of contracts can be used in
    different situations
  • Fixed price or lump sum contracts Involve a
    fixed total price for a well-defined product or
    service.
  • Cost reimbursable contracts Involve payment to
    the seller for direct and indirect costs.
  • Time and material contracts Hybrid of both fixed
    price and cost reimbursable contracts, often used
    by consultants.
  • Unit price contracts Require the buyer to pay
    the seller a predetermined amount per unit of
    service.
  • A single contract can actually include all four
    of these categories, if it makes sense for that
    particular procurement.

88
Cost Reimbursable Contracts
  • Cost plus incentive fee (CPIF) The buyer pays
    the supplier for allowable performance costs plus
    a predetermined fee and an incentive bonus.(P.500
    text)
  • Cost plus fixed fee (CPFF) The buyer pays the
    supplier for allowable performance costs plus a
    fixed fee payment usually based on a percentage
    of estimated costs.
  • Cost plus percentage of costs (CPPC) The buyer
    pays the supplier for allowable performance costs
    plus a predetermined percentage based on total
    costs.

89
CPIF example (p.500 of text)
  • Expected cost on the contract (agreed by buyer
    supplier base on past experience) 100K
  • Share formula on contract for buyer supplier
    85/15
  • Predetermined fee to supplier 10K
  • If final cost is 800K,
  • then cost saving expected cost final cost
    20K
  • Incentive bonus of supplier (cost
    saving15)3K
  • Buyer paid predetermine fee incentive bonus
    final cost
  • 10K 3K 800K
  • 93K (saving of 7K
    compare with expected cost)
  • Supplier receive predetermine fee incentive
    bonus
  • 10K 3K 13K
  • If final cost is less then expected cost, both
    the buyer and the supplier benefit from a CPIF
    plan.

90
Figure 12-2. Contract Types Versus Risk
91
Evaluation Criteria
  • Its important to prepare some form of evaluation
    criteria, preferably before issuing a formal RFP
    or RFQ.
  • Beware of proposals that look good on paper be
    sure to evaluate factors, such as past
    performance and management approach.
  • Can require a technical presentation as part of a
    proposal.

92
2. PROJECT ORGANIZATION
93
3. PROJECT PLANNING
  • Planning
  • Product Based Planning focus attention on goal
    rather than on process
  • Staging
  • breaking a project into stages enables more
    effective management and control of project

94
3.1 Techniques for Product Based Planning
  • Product Breakdown Structure (PBS)
  • Product Flow Diagrams (PFD)
  • Product Descriptions
  • Product Transformation,

95
3.2 Benefit of Staging
  • ESA provide discrete packages of work to be
    review by senior management and make objective
    assessments of the progress to date
  • ESA facilitate control against project momentum
    to progress regardless of cost by reappraisal of
    business case
  • More realistic estimation and monitoring before
    the commencement of next stage.
  • Monitor of project is enabled within and at the
    end of each stage.

96
3.3 Staging Guidelines
  • Each Stage should define
  • Start finish dates
  • end-products to be produced
  • resource needed to produce the end-product
  • Stage setting should consider
  • stage upon the completion of major end-product
    (not divide a maj. end-product)
  • stage at decision about the ongoing viability of
    project
  • stage at critical points where visible tight
    control is necessary.

97
3.4 Plans for decision making and control
  • Project level
  • Technical Plans
  • Resource Plans
  • Stage level
  • Technical Plans
  • Resource Plans

98
4. Project Control
  • Management by Exception
  • Quality Control
  • Control Meeting
  • Formal Assessment Meeting(PSC)
  • Checkpoint Meetings/Reviews(PM)
  • Management of Risk
  • Configuration Management

99
4.3 Control Meetings
  • Formal assessment Meetings Event driven meeting
    with necessary info. for decision making is
    circulated well in advance and Chairmen ensures
    the discussion is confined to real management
    issues.
  • Project Initiating Meeting
  • End-stage Assessment
  • Project Closure Meeting
  • Checkpoint Meeting regular time driven meeting
    held by PM

100
5. Project Activities
  • Project Initiation
  • Project Initiation Meeting
  • Project Initiation Document (PID)
  • Project Stages
  • Checkpoint Review
  • Highlight Reports (monthly) PM to PSC
  • End-Stage Assessments (ESA)
  • Project Closure
  • Project Evaluation Report

101
6. Summary - Why PRINCE?
  • Standard Project Management Method staff move
    from one project to another can still aware of
    the roles, procedures, processes and reporting
    formats.
  • Standard training materials, courses available,
    no need to redevelopment.
  • Enable refinement over years of practice.

102
6. Summary - Why PRINCE ? (conti)
  • It is a flexible method, suitable to many shape
    and size of project. Its particular strengths
    are
  • Definition of the roles in a project
  • involvement of user at all level in all aspects
    from beginning to end.
  • insistence on establishing a business case before
    any major expenditure.
Write a Comment
User Comments (0)
About PowerShow.com