Financing a CDM Project - PowerPoint PPT Presentation

1 / 24
About This Presentation
Title:

Financing a CDM Project

Description:

... WC is also involved in waste composting projects in Sri Lanka and ... Land use clearance obtained BOI registration obtained Third party ... – PowerPoint PPT presentation

Number of Views:101
Avg rating:3.0/5.0
Slides: 25
Provided by: Com3221
Learn more at: http://www.cd4cdm.org
Category:
Tags: cdm | financing | lanka | project

less

Transcript and Presenter's Notes

Title: Financing a CDM Project


1
  • Financing a CDM Project
  • DBBLs experience

Farhad Ahmed Khan Assistant Vice
President Syndication Structured Finance Credit
Division, Dutch-Bangla Bank Ltd
2
DBBLs Participation in Euro 12 Million Project
  • DBBL to provide to the extent of Taka eqvt. Euro
    2.00 million in part funding of implementation of
    WWR Bio Fertilizer Ltd, a municipal organic
    waste-to-bio-fertilizer plant
  • FMO to act as Arranger and DBBL to act as Agent
    and Security Trustee

3
Project Partners
Waste Concern Consultants (WCC) from Bangladesh.
It is working in the area of waste management in
Bangladesh since 1995. It is specialized in small
and medium scale waste management projects
especially composting. Waste Concern is involved
in design and implementation of 47
compost/recycling plants distributed in 26 cities
and towns of Bangladesh. Apart from Bangladesh,
WC is also involved in waste composting projects
in Sri Lanka and Vietnam. World Wide Recycling
BV from Netherlands. It is also working in the
areas of waste management. This company is
associated with VAR a large scale waste recycling
company. It is specialized in large scale waste
projects including composting
WWR Bangladesh Holding BV.
4
The Shareholders Structure
WBH holds 100 less legally required local
shareholding of one share of WWR Bio.
The shareholders of WBH are WWR (EUR 1.7m,
54.2), WCC (EUR 0.4m, 13.6), FMO (EUR 0.5m,
16.1) and Triodos (EUR 0.5m, 16.1).
5
About VAR/WWR
  • WWR is closely related to the VAR via Jan Boone,
    who is the founder of VAR, was director of VAR
    till July 2002, and still is main shareholder of
    VAR with 80 and he is chairman of the
    supervisory board of VAR. VAR was established in
    1981 by Jan Boone. VAR is one of the largest and
    most innovative companies in the area of
    sustainable waste treatment in the Netherlands.
    VAR and WWR have signed a Cooperation Agreement
    via which VAR is obliged to provide technological
    support to WWR.
  • At the end of 2006, VAR had a Balance Sheet
    total of EUR 83m, turnover of EUR 48m, net profit
    EUR 4.1m, solvency 32 and 140 staff. The
    following key figures of VAR in 2006
  • Balance sheet total EUR 79,992,817
  • Equity EUR 27,096,302
  • Turnover EUR 47,643,755
  • EBIDTA EUR 7,300,429
  • Net profit EUR 4,122,329

6
Financing Plan of WWR Bioin million Euro
Amounts x1m EUR Equity to WBH Loan to WBH Loan to WWR Bio Total
FMO 0.43 1.54 3.90 5.87
Triodos 0.43 0.43 1.50 2.36
WWR/WCC 1.80 - - 1.80
DBBL - - 2.00 2.00
Total 12.03
the amounts paid out to WBH are transferred to
WWR Bio as equity
7
Investment and Financing
 Investment Plan (in Euro) 2007 2008/2009 2009/2010
1 Investments in intangibles 690,000 0 0
2 Land 187,198 327,273 297,521
3 Buildings machines 1,304,035 3,899,706 3,806,134
4 Contingencies (activated) 167,903 502,112 490,064
5 Enrichment   550,000 413,223
6 One-off costs 225,000    
Total 2,574,136 5,279,091 5,006,942
Financing Plan (in Euro)      
7 Capital injection WWR/WC 840,000 804,900 155,100
8 Capital injection FMO 200,000 191,643 36,929
9 Capital injection Triodos 200,000 191,643 36,929
10 WBH subloan FMO 164,805 689,914 688,138
11 WBH subloan Triodos 79,305 191,643 157,623
12 WWR Bio subloan FMO 721,680 1,743,950 1,434,370
13 WWR Bio subloan Triodos 269,639 651,586 535,919
14 WWR Bio loan DBBL 372,736 900,721 740,829
Total 2,848,164 5,366,000 3,785,836
8
Projected Operating Results
Amounts in x1000 EUR 2008 2009 2010 2011 2012 2013 2014 2015
Turnover 1,537 6,323 6,178 11,293 10,986 9,367 8,852 8,365
EBITDA 412 2,541 2,447 4,550 4,584 3,313 3,122 2,942
Net profit -129 1114 1169 2692 1767 1117 1100 1137
Operational cash flow 220 1,416 2,477 3,484 4,648 3,650 3,230 3,043
Cash at end of year 240 999 1,177 2,804 4,704 6,257 6,151 5,993
 
Balance sheet total 7,989 9,502 13,941 16,018 16,902 17,158 16,163 15,200
Solvency () 26 34 33 42 48 53 61 71
Risk Bearing Capital as of TA 82 81 85 88 92 95 95 95
Debt/EBITDA 14.05 2.28 3.61 1.83 1.71 2.21 1.76 1.25
Current ratio 4.37 5.40 5.79 6.48 8.64 11.52 11.84 12.10
DSCR excl. investments 2.03 3.87 4.07 5.39 4.63 4.00 2.26 2.47
9
Tenor/Repayment Period
Tenor Tranche I IV for the loans, 10 years from the financial close, with a grace period of 6 years. Tranche V (6 years) from Financial Close with a grace period of 12 months. Repayment Period Tranche I-IV In 8 semi-annual equal installments with the first such installment due 78 months after the closing date. Tranche V In 20 quarterly installments with the first such installment due 15 months after the closing date.
10
Perceived Risk as assessed by DBBL
Construction risk
Feedstock risk
Off-take risk
Loan Structure Risk
11
  • Feedstock risk
  • Input of organic waste is guaranteed by a
    Concession Agreement with the municipality that
    allows WWR Bio to collect up to 700 ton/day waste
    from designated areas, like local markets.

12
  • Construction risk
  • A compost facility is a relatively easy concept.
    Also, the construction is done under supervision
    of the VAR with extensive experience and
    knowledge

13
  • Operational risk
  • Employees will be trained, partly at the VAR in
    the Netherlands. If major problems occur the VAR
    will give technical assistance. Management of the
    companies will come from WCC and WWR and thus
    have experience with waste management

14
  • Off-take risk (demand, competition and
    distribution)
  • Compost can be used as a substitute for or
    additional to more expensive fertilizers. The
    compost market is only marginally developed,
    while the domestic fertilizer market can not
    foresee in total demand. So (potential) demand is
    high, while competition is low. Because the
    compost will be tailor made for different crops
    it can be sold during the whole year. WWR Bio
    negotiates on agreements with end-users directly
    and off-take agreements with wholesalers/distribut
    ors. Own distribution will then be considered
    later

15
  • Land
  • For the first 100-130 ton/day capacity land is
    acquired under a lease contract, which might not
    be sustainable. DBBLs investment is however
    limited to EUR 0.372 m in the first phase and for
    subsequent phases it is required that land is
    obtained in ownership.

16
  • Revenue from CERs
  • The used methodologies are approved as CDM
    projects and thus CERs will be generated as soon
    as the compost facility is operational. The price
    of CERs stays, nevertheless, very insecure, but
    profits of the project are mainly generated by
    selling (enriched) compost
  • DBBL assumed a fixed selling price of Euro 8 per
    unit CER

17
  • Environmental and social risks
  • The project has significant environmental and
    social positive impacts, the most important being
    the reduction of greenhouse gas emissions, the
    production of soil improving compost and the
    offering of livelihood opportunities and
    improvements for poor and marginalized people.
    Potential adverse impacts do exist, but are
    limited and manageable and they can be mitigated.

18
  • Key Man Risk
  • The Directors of WWR Bio are A.H. Md. Maqsood
    Sinha of WCC and a representative of WWR,
    currently Jan Boone. A.H. Md. Maqsood Sinha has
    experience with waste management in Bangladesh.
    A.H. Md. Maqsood Sinha and Jan Boone seem very
    capable of running WWR Bio. Nevertheless, if Jan
    Boone or any other key person should fall away,
    an important financial and business partner is
    lost (key man risk), especially during
    construction phase.

19
  • Loan Structure Risk
  • The tenor for the DBBLs loans is 6 year, with a
    grace period of 1 year. DBBL (senior loans)
    receives security over all fixed and floating
    assets of WWR Bio.
  • Another mitigant is that disbursements of the
    loans to expand capacity from 100 to 700 ton/day,
    will be considered only if the project at phase 1
    has proven to be a success.

20
Milestones Achieved
  • Concession Agreement with DCC has been signed
    to collect and transport waste
  • National CDM Board Approval has been obtained
  • Land lease agreement for 22 years has been
    signed
  • Trade licensee obtained
  • Land use clearance obtained
  • BOI registration obtained
  • Third party verification of Environmental and
    Social Compliance has been done
  • Environmental clearance obtained from DOE
  • Work permit for the WWR engineer has been
    obtained
  • Import permit has been obtained
  • Land development completed
  • Detailed Engineering design completed
  • Major construction works for phase 1 completed
    by March 2008
  • The project has gone into trial operation end of
    March 2008
  • Pending Registration of compost/enriched
    compost

21
DBBL to finance First CDM project in Bangladesh
  • Commercial lenders are cautious in providing new
    loans particularly to projects involving
    unfamiliar technologies.
  • Technologies, equipment processes relevant for
    CDM are available commercially, many of which
    offer viable economic returns yet, not many of
    such projects are being implemented in Asia
    compared to what can be potentially achieved.
  • Bangladesh is yet to see any lender, other than
    DBBL, to finance CDM project.
  • DBBL wishes to extend thanks to FMO for involving
    it with the countrys first ever CDM project.

22
Summing up DBBLs Feeling
  • An adequate risk-sharing structure is often
    difficult to put in place and almost always
    creates unanticipated delays in achieving
    financial closing.
  • Risk should be allocated, by contract, to the
    party that is best able to mitigate or control.
  • Completion risk could be avoided by implementing
    such project in phases.
  • There should be transfer of technical know-how
    from Annex I country.
  • Carbon Credit market development needs
    accelerators. Action by participating players
    needed advisors, buyers, FIs, government to put
    in place the necessary accelerators.
  • Regulatory support needed.
  • Lenders should have greater oversight of the
    project. They should have control the application
    of cash flows.

23
Summing up - DBBLs Feeling (Contd.)
  • First time lenders for projects like CDM should
    be in the senior loan category. Equity and quasi
    equity should be invested first.
  • Banks need assets to back-up however, CDM
    project is often not asset based but idea based.
  • Documentation is lengthy and complex, and costs a
    great deal to put into place.
  • Success of WWR Bio is crucial for other lenders
    to finance CDM project.
  • Bangladesh is an attractive market for CDM.
  • DBBL will embark on the lessons learned to take
    on more such viable CDM projects. Journey has
    just begun.

24
The End
  • Thank You
Write a Comment
User Comments (0)
About PowerShow.com