Title: Electric Grid Modernization Working Group Kick-Off Workshop
1Electric Grid ModernizationWorking Group
Kick-Off Workshop
Larry Gelbien, Vice President of Engineering,
NSTAR Jennifer Schilling, Director of Asset
Management, Western Massachusetts Electric
Company November 14, 2012
2Agenda
1
Introduction
2
NSTAR Grid Modernization Activities
3
WMECo Grid Modernization Activities
3NU Grid Modernization Principles
- NU customers are front and center when making
grid modernization decisions by focusing
investments on enhancing grid infrastructure to
provide a safer, more reliable, and cost
effective service for our customers - Deployment of grid modernization programs must be
conducted with a focus on capturing efficiencies
and long-term value for customers - Excellent communication and shared objectives
among all stakeholders is critical to the success
of grid modernization programs - Pilots of new technologies represent a valuable
opportunity to quantify costs and identify
potential benefits in order to inform
implementation decisions - NSTAR, WMECO and other NU operating companies
will work together to identify and implement best
practices in system planning and grid
modernization, leveraging synergies to lower unit
costs - Each company will continue to make independent
investment decisions based on geography, system
characteristics, customer demographics and
regulatory construct - As part of the grid modernization working group,
MA utilities can leverage experiences without
duplicating efforts
4Agenda
1
Introduction
2
NSTAR Grid Modernization Activities
3
WMECo Grid Modernization Activities
5Grid Modernization Investments
NSTAR has made significant investments in
Distribution Automation and other Grid-Facing
Smart Grid Equipment
- Distribution Automation Present and Future
- 4 kV Modernization Using Advance Technology
- Boston Secondary Network Monitoring
- Transmission Sensors and Switches
- High Speed Fiber-optic Rings for Reliability,
Monitoring, and Control - Distribution Generation Interconnections using
Advance Technology - Digital Voice Radio Provides Interoperability
of all crew communications - Web-based Outage Reporting
- AMR-Based Dynamic Pricing
- Outage Management System Evaluation
6Distribution Automation reduces outage duration
and the number of customers affected
- Electric delivery network using modern sensing,
communications, and information processing based
on digital technologies - Circuit self-healing implementation
(Auto-Restoration) - Supervisory controlled overhead and underground
switches with voltage and current sensors
7Significant Distribution Automation Investment
- NSTAR has installed more than 2,000 switches
throughout our service territory and has over
5,000 sensors monitoring the electric grid. - 80 of NSTAR customers benefit from Distribution
Automation. - NSTAR is expanding this program and capabilities
as part of our 20MM US DOE ARRA Project.
8Distribution Automation NSTAR South locations
9Distribution Automation NSTAR North locations
10NSTAR is moving towards full Auto-Restoration as
part of our DOE ARRA Grant project
- Mode 1 Supervisory mode
- Leverages remote control of switches
- Operator controlled sequences
- Mode 2 Operational Acknowledgement mode
- Computer-simulated restoration sequences
- Operator validation and execution
- Mode 3 Self-Healing mode
- Computer-determined restoration sequences
- No human intervention
11More than 600,000 Customer Outages Avoided Due to
Automated Sectionalization
Cumulative Number of Averted Sustained Customer
Outages Due to ASU Operations (through 9/30/12)
12Customers see the benefits in shorter outage
durations and fewer customers affected
- 2012 YTD through September
- 71,000 customer sustained outages avoided
- 163,000 restored in 5 minutes or less
- DA improves response time during major system
events
Tropical Storm Irene October 2011 Noreaster
Total Customer Interruptions 506,000 227,000
Customer Restored lt 1hour (included in line above) 232,000 16,000
13Automated Vacuum Fault Interrupters (VFI)
- Allows for automation on underground switches
which are otherwise difficult to access and
operate. - Switching can be done locally (from above the
manhole) or remotely (via SCADA).
14Secondary Network Monitoring SystemsBoston
Cambridge
- DigitalGrid Network Reporting Using Power Line
Carrier Communications - Monitors 100 of the transformers (1,500 total)
on our underground secondary network in Boston
Cambridge to provide near real-time data for our
SCADA system. - Technology is installed and enabled at every
network transformer in our secondary network.
Urban Grid Monitoring Renewables Integration
Minor Node
- Urban Grid Monitoring Renewables Integration
DOE Pilot - Enhances visibility into status of underground
secondary network in downtown Boston - Improves reliability and ultimately allows for
testing the integration of inverter-based
renewable generation onto the secondary network
grid - 10MM project, 50 funded by US DOE ARRA Grant
15Transmission Sensors and SEECO Switches
- Enhances ability to monitor and control our
Transmission system by adding sensing and
switching technology. - Near real-time monitoring allows us to reduce
outage duration, or avoid outages altogether. - 2012 YTD 19,800 outages avoided due to
Transmission switching - 2011
- 35,715 outages avoided
- 71,745 restored in 5 minutes or less
16Distributed Generation Interconnection Using
Advanced Technology
Distributed Generation Interconnection Projects
On-line by Year
- Improves safety, response time, and decreases
costs by allowing NSTAR to easily and safely
connect solar and wind generation to the electric
grid.
17Digital Communication System
- Provides field crews with voice, data, and phone
during emergency operations. - Enables Interoperability of all field crews
communications. - Voice Radio that can be used for communications,
particularly during major system events when
commercial cellular service is not available or
is unreliable. - Improves safety via
- Emergency alert and GPS location features
- Improved reliability and coverage
- Increases effectiveness of recovery and
restoration as well as mutual aid, improving
overall response times
18High speed Fiber-optic Rings for Reliability,
Monitoring, and Control
19Web-based Outage Reporting
- Enables NSTAR customers to report and track the
status of power outages from their desktop
computer or mobile device.
Outage Map contains up-to-date information by town
Outages can be reported on a mobile device
20AMR-Based Dynamic Pricing
- Overview
- Compliant with Massachusetts Green Communities
Act - Will include 2,870 total NSTAR customers
- Integrates two way communications and near real
time measurement of consumption data via Tendril
Networks Home Area Network system - Utilizes Time of Use Pricing by integrating
interval data from Tendril to NSTAR back office
systems - Low-cost solution utilizing existing
infrastructure - Compatible with existing meters and existing
billing system - Utilizes Internet for communications back-haul
20
21Pilot Evaluation Timeline
Metrics Benefits Report
Metrics Benefits Report
End of PilotOfficial DOE
Pilot Kick-offSoft Launch
Technical Performance Report 1
Technical Performance Report 2
24 months
Summer 2010
January 2012
September 2012
Summer 2013
Winter 2013
December 2013
Spring 2014
22Initial interest was strong, but many customers
have dropped out of the pilot over time.
- 6.7 overall response rate to marketing
- Email response 7
- Direct Mail response 3.7
- 3,200 customers enrolled and 2,700 followed
through to installation - 850 customers (30 of installed) have de-enrolled
after installation - This number is going up, as customers equipment
is going off-line.
23Some customers love the increased information
others expect more.
It was very helpful and made me conscious on
what I used for electricity and made me think of
when to do laundry.
The In Home Display is useless and the data is
not actionable. You need to have a mobile app.
The thermostat and its connectivity to the web
portal were very helpful. While it was neat to
have the in-home display to see what is going on,
I dont think it impacted our decisions about
energy usage.
I have found the program both informative and
educational from a best practice standpoint as
well as helpful from a financial incentive
perspective. Thank you all, especially for the
responsive customer service.
All it really told me was that my A/C and
electric dryer use a lot of energy, which I
already knew.
24There are many open questions on the benefits of
the program.
- While there are several pros to this approach vs.
AMI deployment (namely cost), there are many
challenges and uncertainties - Billing complexities
- Customer acceptance and participation
- Overall energy savings resulting from each
treatment group and the persistence of these
savings over time - This emphasizes the importance of carefully
analyzing the results to identify trends, areas
for improvement and best practices. By
undertaking this exercise, NSTAR will ensure that
future grid modernization strategies provide real
benefits to customers.
25Automated Outage Reporting Pilots
- Piloting low cost solutions to mitigate nested
outages by monitoring the overhead distribution
system. - Hardware solution
- Software solution
- Third party
partnerships
26Agenda
1
Introduction
2
NSTAR Grid Modernization Activities
3
WMECo Grid Modernization Activities
27Investment Decision Balance
Investment decisions in reliability and
improvements in customer experience are based on
relative cost benefit analysis
Customers ability to support total investment
cost
LESSEN IMPACT OF EVENTS
PREVENT EVENTS
28Overhead Distribution Automation
- Overhead System Automation via Reclosers and
Recloser Loop Schemes - Isolate faulted circuit backbone section
automatically and independently in under 60
seconds - Early loop schemes had limited DSCADA due to poor
radio coverage - New radio infrastructure in 2008 allowed for wide
spread DSCADA deployment - 19 of reclosers are DSCADA equipped
- All new reclosers are DSCADA equipped
- Approximately 53 of customers served by the
overhead system are a part of a loop scheme - Opportunities remain to increase loop scheme
penetration and reduce size of zones
29WMECO Smart Zone
- Motor operated switches with advanced remote
terminal units (RTUs) - Smart zone isolates fault within timing sequence
of recloser loop scheme - DSCADA equipped
- 1 accuracy sensors to provide quality circuit
information to engineers and other potential
future smart grid applications - RTUs can be reconfigured to take commands from a
DMS if desired in future - New Packet Radio System
- Provides peer-to-peer communication between
devices - Required for quick data transfer needed to fit in
loop scheme timing sequence
30Integration of Distributed Generation
- WMECO has installed 4.1 MW of utility owned solar
generation at two facilities in Pittsfield and
Springfield - Projects provide opportunity to study the impact
of distributed generation on the utility grid
- Power Tag pilot project underway to test the
feasibility of a lower cost solution to detect an
islanding condition - Signal sent from the substation via power line
carrier to the DG facility - In the event the signal is interrupted at the
facility, the recloser will automatically open
disconnecting the facility from the distribution
system
31Customer Facing Technologies
- WMECO has not yet identified a cost effective
business case for widespread deployment of
customer facing technologies on the distribution
grid - Enabling time of use pricing and customer access
to real time usage information via AMI has a high
fixed cost that must be spread over a relatively
small customer base - Communications infrastructure would need to cover
15 of the state land area to reach fewer than
210,000 customers - Benefits should be quantifiable and sustainable
- Customers response to technology must be
maintained over life of investment - Incremental benefits relative to AMR systems have
yet to be proven
GREEN COMMUNITIES ACT SMART GRID PILOT ON
HOLD WMECO proposed a six-month pilot for 1,750
customers at a cost of 7.1 million Settlement
agreement calls for waiting to achieve cost
savings with upgrade of NU meter data management
system and gathering lessons learned from other
Massachusetts utility pilots
32WMECo and NSTAR support the Green Button
initiative
- The Green Button is a response to a national
challenge to utilities from President Barrack
Obamas Chief Technology Officer - With a click of the button customers can view
their electricity usage quickly and easily from
our web site
- The goal is to encourage awareness of energy use
and allow third parties to develop tools that
help our customers more effectively manage energy
costs.
33NU Grid Modernization Policy Issues
- Investment decisions should be informed by robust
risk adjusted cost benefit analysis targeted to
each companys operating characteristics - Pilot programs represent a valuable opportunity
to assess costs and benefits of technology
applications prior to widespread deployment - Performance measurement and reporting is an
important part of the implementation of grid
modernization programs - Distribution automation is a proven approach to
limiting the duration and number of customers
affected by outage events - Advanced Meter Infrastructure (AMI) may be
difficult to justify in many situations based on
operational benefits, particularly given prior
investment in Automated Meter Reading (AMR).
Investments of these types must be justified on a
cost benefit basis.