1Alignment of theInfrastructure Delivery
Cyclewith the Budget Cycle(Abridged Version
for
Prepared by the Infrastructure Delivery
Improvement Programme (IDIP)
2The Infrastructure Delivery Improvement Programme
(IDIP)
- IDIP is a continuous improvement programme which
guides capacitates to improve infrastructure
delivery - IDIP is coordinated by National Treasury in
partnership with DBSA, DPW CIDB - IDIP provides flexible tools that can be adapted
to the province sector - IDIP is a key strategy of government to address
inadequate capacity and skills in the
infrastructure sector
3Problem Statement
- Continuing under expenditure of infrastructure
budgets. - Inappropriate expenditure patterns characterized
by the 4th Quarter expenditure spike. - Currently there appears to be very little
alignment between the Infrastructure Delivery
Cycle and either the Budget Cycle or the
Strategic Planning Cycle. - Currently the budget for large multi-year
projects is committed to 1 financial year instead
apportioning the budget across the MTEF.
43 Year MTEF Period
MTEF Budget Cycle
These are all the concurrent budget activities
that need to be undertaken in any 1 year
Closure Processes
Budget Day
Currently it would appear that annual budgets are
prepared by updating last years budget with a
factor for inflation The annual budgets
submitted to treasury do not appear to be
informed by actual projects to be implemented in
the following year.
5Infrastructure Delivery Cycle
3 Year MTEF Period
Current Infrastructure Delivery Cycle
Infrastructure Planning
Project Design
Project Tender
Project Implementation
Implement Rolled Over Unspent Budget
100
President Thabo Mbeki in his 2006 State of the
Nation Address said, Better supervision of
infrastructure projects undertaken by government
will be introduced, to ensure that capital
budgets are spent without roll-overs
With the current Infrastructure Delivery Cycle,
expenditure during the 1st half of the year is
virtually impossible since most projects are
still in the tender phase. The result is the 4th
quarter expenditure spike and overall
under-expenditure.
6Improved Infrastructure Delivery Cycle
3 Year MTEF Period
Current Infrastructure Delivery Cycle
Project Design
Project Tender
Project Implementation
Rolled Over Unspent Budget
Infrastructure Planning
Improved Infrastructure Delivery Cycle
Infrastructure Planning
The Infrastructure Plan sets out the
infrastructure priorities for the next 10 years.
It is updated annually by the Client Department.
7Infrastructure Programme Management
Implementation Plans (IPMP IPIP)
Client Department (CD)
- FUNCTIONS OF CD
- Planning
- Procurement
- Programme Management
- Monitoring Reporting
Infrastructure Plan Update
SDA with IA 1
IPMP Update
SDA with IA 2
IPMP issued to IAs
Implementing Agent IA 1
Implementing Agent IA 2
IPIP for IA 2
IPIP for IA 1
IPIPs respond to IPMP
FUNCTIONS of IAs
- Programme Management
- Project Initiation
- Procurement
4. Project Implementation 5. Project
Completion 6. Monitoring Reporting
8Improved Infrastructure Delivery Cycle
3 Year MTEF Period
Current Infrastructure Delivery Cycle
Project Design
Project Tender
Project Implementation
Rolled Over Unspent Budget
Infrastructure Planning
Improved Infrastructure Delivery Cycle
Project Design
Project Tender
Project Implementation
Planned Multi-year Commitments
IPMP
IPIP
Infrastructure Planning
Monitoring Reporting
IPIP Infrastructure Programme Implementation
Plan Prepared by Implementing Agent and submitted
to Client Department for approval. Contains the
details of how the list of projects issued by the
Client Department will be implemented.
The Infrastructure Plan sets out the
infrastructure priorities for the next 10 years.
It is updated annually by the Client Department.
IPMP Infrastructure Programme Management
Plan Prepared by Client Department and given to
Implementing Agent. Contains list of projects for
the next 3 years and where they are located.
9Alignment of the Infrastructure Delivery Cycle
the Budget Cycle
The improved Infrastructure Delivery Cycle now
facilitates the alignment of the Infrastructure
Delivery Cycle with the Budget Cycle. The budget
preparation process can now be strengthened by
actual projects identified during Infrastructure
Planning.
Currently Infrastructure Planning is undertaken
too late to facilitate effective alignment of the
Infrastructure Delivery Cycle with the Budget
Cycle.
10Required Capacity for Departmental Infrastructure
Units
These are all the concurrent infrastructure
delivery activities that need to be undertaken in
any 1 year.
Departments therefore need to have the capacity
to undertake all these concurrent activities.
Improved Infrastructure Delivery Cycle
Project Design
Project Tender
Project Implementation
Planned Multi-year Commitments
IPMP
IPIP
Infrastructure Planning
Monitoring Reporting
LEGEND IPMP Infrastructure Programme
Management Plan IPIP Infrastructure Programme
Implementation Plan
11Example of a Programme Budget to commit the
entire Annual Budget
12Managing Cashflows Across Years
In reality the neat chunks of work shown on the
earlier slides are actually individual projects
or clusters of projects with different start
end dates
Some projects or clusters of projects in the
current year can be delayed causing potential
under expenditure
Planned Multi-year Commitments
Project Implementation
Project Implementation
Project Design Tender
Planned Multi-year Commitments
Project Implementation
Project Design Tender
IPIP
IPMP
But here we have clusters of projects that have
been designed and are ready to go to tender
Infr. Plan update
IPMP
IPIP
NB The total value of the work in this year
equals the Annual Budget for this year
13Managing Cashflows Across Years
Planned Multi-year Commitments
Project Implementation
Project Implementation
Project Design Tender
Planned Multi-year Commitments
Project Implementation
Project Design Tender
IPIP
IPMP
We need to tender these projects earlier and
start implementation in Year 1 to offset the
potential under expenditure caused by the delayed
projects
Infr. Plan update
IPMP
IPIP
14Identified Benefits
- Better linkage with Strategic Planning is
achieved - Better alignment of the budget with the targets
set out in the Strategic Plan - Project planning design is properly done
resulting in achievable realistic cashflows - Multi-Year commitments are planned and budgeted
for thereby reducing rollovers - Improved clarity of roles responsibilities
between client departments and implementing agents
15STATEMENT ON THE CABINET MEETING OF 21st February
2007.
- Cabinet approved a framework to align
infrastructure delivery cycles with the MTEF
budget cycle in order to improve planning,
implementation and better cash-flow management
that would, among other things, deal with the
fourth quarter expenditure spike. This framework
accommodates the long lead time before
infrastructure projects reach the construction
stage. The infrastructure delivery cycle will be
amended to include an Infrastructure Programme
Management Plan (IPMP) and an Infrastructure
Programme Implementation Plan (IPIP) which will
be mandatory for all departments. Best practice
approaches will be adopted to include budget
cycles that commit funds for the duration of the
project without leading to the so-called
roll-overs. This framework will require the
appointment of appropriately skilled
built-environment professionals across all
relevant departments, provinces and local
government.
16THANK YOU