Title: Topics in Capital Budgeting
1Topics in Capital Budgeting
2Objectives
- Study how to determine cash flows for capital
budgeting analysis - Study capital budgeting under uncertainty
- Study how to incorporate risk in capital
budgeting decisions.
3Guidelines for Capital Budgeting
- Use cash flows rather than accounting profits
- Cash flows correctly reflect the timing of
benefits and costs - Examine cash flows on an after-tax basis
- Only include incremental after-tax cash flows
- Cash flows with the new project versus cash flows
without the new project
4Guidelines for Capital Budgeting
- Beware of cash flows diverted from existing
products - Decide if overhead costs are truly incremental
cash flows - Ignore interest payments and financing flows as
they are accounted for when the cash flows are
discounted back to present
5Inflation Capital Budgeting
- Increased inflation will cause the required rate
of return on project to rise. - Both anticipated cash inflows and outflows could
be affected by inflation. - The salvage value of the project could be
affected by inflation. - The fact that depreciation charges do not change
with inflation also distorts capital-budgeting
decisions.
6Measuring The Cash Flows
- A projects cash flows can be classified as
- Initial outlay
- Differential cash flows
- Terminal cash flow
7Example
8Initial Outlays
- The installed cost of the asset
- In case of a replacement decision, the after-tax
cash flow associated with the sale of the old
machine - Additional non-expense outlays incurred, e.g.,
Working capital investments - Additional expenses on an after tax basis, e.g.,
Training
9Initial Outlays
The tax savings is the marginal tax rate times
the difference 15,000 - 10,000, i.e.,
depreciated value minus salvage value.
10Differential Cash Flows
- Incremental after-tax cash flows resulting from
increased revenue from the proposal - Any labor and/or material savings incurred
- Increases in overhead incurred
- Do not include any financing charges as they are
implicitly taken care of in the discounting
process
11Differential Cash Flows
The increased depreciation charges are
calculated as 12,000 - 3,000.
12Terminal Cash Flows
- The projects salvage value plus any taxable
gains or losses associated with the project - Any terminal cash flows needed, perhaps for
disposal of obsolete equipment - Recovery of any non-expense cash outlays
associated with the project, such as recovery of
increased working-capital needs associated with
the proposal
13Terminal Cash Flows
- The salvage value of the new machine is zero and
so there is no terminal cash flow in this example - The cash flows for the proposed project are as
shown
14Risk and Investment Decisions
- The risk of an investment project is defined as
the variability of its cash flows from the
expected cash flows. - In capital budgeting, projects risk can be
looked at in the following three levels - Project Risk
- Firm Risk
- Systematic Risk
15What measure of risk is relevant for capital
budgeting?
- According to CAPM, systematic risk is the only
relevant risk for capital budgeting purposes. - For undiversified shareholders including owners
of small corporations the relevant measure of
risk may be the projects contribution-to-firm
risk. This measure is more appropriate if there
are cost associated with bankruptcy.
16Methods for Incorporating Risk into
Capital-Budgeting
- Certainty Equivalent Approach
- In this method the financial manager substitutes
the certain dollar amount that he or she feels is
equivalent to the expected but risky cash flows
offered by the project. - In effect, the manager is indifferent between
both a safe set of cash flows and the original
set of risky cash flows.
17Methods for Incorporating Risk into
Capital-Budgeting
- Risk Adjusted Discount Rates
- In this method if the risk associated with the
project is more then the discount rate is
adjusted upwards to compensate for the risk. - The expected cash flows are then discounted back
to present at the risk-adjusted discount rate.
18Certainty Equivalent versus Risk Adjusted
Discount Rate
- In the certainty equivalent approach, the
expected cash flows are adjusted downwards to
incorporate risk of the project. - In the risk adjusted discount rate approach, the
expected cash flows are unchanged but the
required rate of return is adjusted upwards to
incorporate risk of the project. - In either case the net result is a decrease in
the NPV of the investment proposal.
19The Systematic Risk of a Project
- In order to determine the risk adjusted discount
rate for a project we need to estimate the
systematic risk, i.e., the project beta. - Beta can be estimated using
- Accounting Return Data Method
- Pure Play Method
20The Capital Budgeting Decision
m
rf b (ERm rf)
b
21Other Sources and Measures of Risk
- Time Dependence of Cash Flows
- Many times, especially with the introduction of a
new product the cash flows experienced in the
early years affect the size of the cash flows
experienced in later years. This is called time
dependence of cash flows. - Skewness
- A distribution that is not symmetric is said to
be skewed. - When distributions are skewed, the expected value
and standard deviation alone may not be enough to
differentiate between two distributions or risks.
22Methods for Evaluating Risk in Capital Budgeting
- CAPM
- Simulation
- Sensitivity Analysis
- Probability Trees
23Summary
- Measured cash flows
- Incorporated risk
- Considered capital budgeting methods