Drawing the AON network - PowerPoint PPT Presentation

About This Presentation
Title:

Drawing the AON network

Description:

Project Management (lecture) Elements of ... Examples of activity combinations Graphical representation Representation of dependency time: ... Document presentation ... – PowerPoint PPT presentation

Number of Views:58
Avg rating:3.0/5.0
Slides: 14
Provided by: ktk6
Category:

less

Transcript and Presenter's Notes

Title: Drawing the AON network


1
Drawing the AON network
  • Project Management
  • (lecture)

2
Elements of an AoN diagram
  • Activity (node)
  • Work element or task
  • Name or identification of the tasks must be added
  • No need for dummy (unreal) activities
  • Dependency or sequence arrow
  • Shows the interrelationship between activities

3
Conventions
  • Time flows from left to right
  • Arrows direction
  • Labels increase
  • Head nodes always have a greater/higher label
    (letter) that of the tail node.
  • A complete network has only one starting and only
    one ending event.

4
Examples of activity combinations
5
Graphical representation
  • Representation of dependency time lags
  • Activity duration times finish to start
    dependency
  • Representation of milestones/deadlines (external
    constraints) Identified by an inverted triangle
    over the activity node (occasionally with an
    imposed time for the event)

6
Overlapping activities
  • If the activities are not fully discrete
  • The second activity can start before the first is
    completed but not before it is at least partly
    completed.
  • Breaking activities into components

7
Interfacing
  • When an activity is common to two or more
    subnetworks it is said to be an interface
    activity between those subnetworks and is
    represented by a pair of concentric circles or
    rectangles.

8
Two errors in logic
  • Looping underlying logic must be at fault
  • Dangling an activity is undertaken with no result

9
Hammock activities
  • Artificial activities created for the
    representation of the overhead cost with the aim
    of cost control.
  • Embrace activities belong to the same cost centre
  • Zero duration time (not taking part in the time
    analysis)
  • Overhead cost rate is assumed to be constant over
    the life of the hammock.

10
Multiple starts and finishes
  • Only used in computer programs
  • All starting activities can occur at the start
    and all finish activities will occur at the end
    of the project.

11
CPA, CPM and PERT
  • Critical Path Analysis (CPA), Critical Path
    Method (CPM)
  • deterministic with only one estimation
  • Program Evaluation and Review Technique (PERT)
  • probabilistic with three estimated durations

12
Readings
  • Lockyer Gordon (2005) Chapter 12

13
Thanks for the attention!
Write a Comment
User Comments (0)
About PowerShow.com