Project Nexus - PowerPoint PPT Presentation

About This Presentation
Title:

Project Nexus

Description:

Project Nexus Requirements Definition Phase Steve Nunnington – PowerPoint PPT presentation

Number of Views:79
Avg rating:3.0/5.0
Slides: 21
Provided by: nick2208
Category:

less

Transcript and Presenter's Notes

Title: Project Nexus


1
Project Nexus Requirements DefinitionPhase
Steve Nunnington
2
UNC Project Nexus Workstream Proposals
  • Project Nexus UNC Workstream formed to debate and
    develop the UNC Topics which support the delivery
    of Project Nexus.
  • 21 Topics in scope within the Initial
    Requirements Register
  • 9 major Topics
  • 12 Others
  • Topics to be raised formally as per normal UNC
    Workstream governance
  • Any new Topics to be raised in this way
  • Proposal to employ Topic Workgroups similar in
    structure to UNC Development Workgroups
  • Workstream to review Topics and decide which
    Topics should be debated within a workgroup.

3
Project Nexus Interactions
  • Responsibilities of UNC Project Nexus Workstream
  • Prioritisation grouping of Topics and issues
  • Recommend approval or rejection of proposals
  • Provide guidance to Topic Workgroups
  • Review Topic Workgroup update reports
  • Refer back to the Workgroup where further
    analysis or information is required
  • Review details of any new topics raised within
    the Workgroups and carry out an impact assessment
    to decide if a new Workgroup is required
  • Ensure adequate publicity is given to proposals,
    as appropriate
  • Seek views of the Authority or affected bodies
    (E.G. BERR, IGT UNC, SPAA etc.) on matters
    connected to any proposal
  • Define assumptions and principles to support the
    business rule development
  • Track cross Topic Workgroup inter-dependencies
  • Workstream to initiate legal drafting
  • Manage change control

4
Topics In-Scope of xoserves Prevailing Services
  • Initial Requirements Register within scope of
    Workstream
  • Supplier Switching
  • Market Differentiation
  • Connection and Registration
  • Increased reads for Energy Allocation, Balancing
    and Transportation Charging
  • Reconciliation
  • AQ Management
  • Volume Capture
  • Invoicing Rules
  • Treatment of Retrospective Updates

5
Other In-Scope Topics cont.
  • Governance of SPA
  • Fuel Poor
  • Incentive and Liability regime review
  • Review Of Reporting Requirements
  • Central Register of Emergency Contacts
  • Multiple shippers per legal entity
  • SSP IC supply points
  • Demand Allocation data
  • Inclusion of Unique Sites within Nexus
  • New EUC for SSPs
  • WAR calculation review
  • Review SOQ process for DM NDM

6
Topics Currently Out-of-Scope of xoserves
Prevailing Services
  • Initial Requirements Register currently out of
    the scope of Workstream
  • Data Management Data Hub
  • Data Management Quality Assurance
  • Data Management Exchange Flows of Data
  • Data Management Central Data Store for Smart
    Metering Data
  • iGT Services
  • xoserve will look to build on the discussions
    being facilitated by Ofgem and SPAA in respect of
    iGT services and DECC in respect of Smart Meters.
  • xoserve will organise and facilitate separate
    workgroups for Data Management.
  • The outputs from the above Workgroups will
    contribute to the Topic Workgroup discussions

7
Resources Available
  • Requirements Register
  • xoserves Review of Topics
  • List of relevant Mods (Live and closed)
  • Interdependencies of Topic Workgroups
  • Contractual Obligation Impacts
  • Outline Terms Of Reference for Topic Workgroups
  • Industry participant benefit matrix
  • Impacts/Dependencies analysis from Data
    Management iGT Topics
  • xoserve existing BPMs

8
Proposed Topic Grouping and Priorities
  • 1 Market Differentiation Workgroup
  • 2. Market Differentiation
  • 2 Connection Registration Workgroup
  • 3. Connection Registration
  • 3 SPA Workgroup
  • 1. Supplier Switching (Dual Fuel Switching
    Timescales)
  • 10.1 Governance Of Industry SPA process
  • 10.2 Identification of Fuel Poor
  • 10.5 Register of Emergency Contact Details
  • 10.6 Multiple Suppliers/Shippers per legal entity
  • 10.9 Single database for all supply points (E.G.
    Unique Sites)

9
Proposed Topic Grouping and Priorities cont.
  • 4 Volume Workgroup
  • 7. Volume Capture
  • 5 Meter Reading Workgroup
  • 4. Increased Reads for Energy
  • 6 Retrospective Update Workgroup
  • 9. Treatment of Retrospective
  • 7 AQ Allocation Energy Workgroup
  • 6. AQ Management
  • 10.7 IC status / profile in SSP market sector
  • 10.8 Demand Allocation data split by SSP and LSP
    market
  • 10.10 Review Winter Annual Ratio calculation and
    allocation of EUC
  • 10.12 Review treatment of SOQs in DM and NDM
    arenas

10
Proposed Topic Grouping and Priorities cont.
  • 8 Invoicing Workgroup
  • 8. Invoicing Rules
  • 10.3 Review of Incentives Liabilities
  • 9 Reconciliation Workgroup
  • Reconciliation
  • 10 Non-Functional Workgroup
  • This workgroup would discuss all non-functional
    areas, e.g. file formats and interfaces. The
    workgroup may require a representative from each
    of the other workgroups as the method and process
    for delivery of each topic will have to be
    considered

11
Proposed Topic Management
  • Governance
  • TOR for each Workgroup/Topic
  • All documentation available on JO website
  • JO to chair meetings
  • Minutes to be produced within 5 days
  • Agenda available at least 5 days prior to meeting
  • Monthly report to be sent to Workstream charting
    progress
  • Any new Topics to be approved by Workstream and
    allocated to a Workgroup
  • 1st Workgroup (per Topic area)
  • Decide on attendees
  • Venue
  • Dates and times of meetings (10AM 3PM)
  • Sponsor to introduce Topic
  • TOR signed off
  • Creation of Workplan

12
Proposed Topic Management cont.
  • 2nd Meeting
  • xoserve produce As Is Process Model
  • Baseline current process and obtain consensus
  • Outside the meeting stakeholders will identify
    issues
  • This could take more than one meeting dependent
    on complexity
  • Subsequent Meetings
  • Further opportunity for consultation respondents
    to air their views and develop their ideas into a
    tangible proposition
  • Other stakeholders to present their issues
    Improvement Opportunities
  • Group to examine and discuss these proposals and
    discuss which ones should be taken forward
  • Consider impacts of in-flight mods
  • Consider determinations made to closed
    modifications (Joint Office)
  • Costs Benefits should be the main driver to
    take issues forward

13
Proposed Workgroup Outputs
  • Re-draw Process Models after the discussions have
    concluded to give To Be Maps
  • xoserve will maintain a register to ensure that
    all Topic areas are discussed and ensure
    traceability
  • Produce a Report for every Topic investigated
    including a justification for their outcome
  • Raise any UNC Mod as appropriate pass to
    Workstream
  • Capture Requirements in a tool to be defined by
    xoserve
  • Produce a set of business rules sufficient to aid
    design
  • Where consensus cannot be reached escalation will
    be
  • Workstream
  • Modification Panel
  • If consensus cannot be reached the status quo
    remains

14
.
Project Nexus Requirements DefinitionPhase
Strawman Plan Assumptions 30th April 2009
Shirley Wheeler
15
UNC Project Nexus Planning Assumptions
  • Several principles need to be agreed by industry
    before commencement of workgroup workshops
  • Funding Principles
  • Change Control Mechanism
  • Approach proposal is accepted by UNC Workstream
  • 10 Workgroups
  • Overarching Workstream
  • 10 Topic areas determined as S, M or L
  • Determines the number of workshops per category

Scene Setting Current Processes To be Processes Finalisation Sub Total No. of Scenarios Total
S 1 1 2 2 6 3 18
M 1 3 5 2 11 5 55
L 1 4 12 2 19 2 38
Makes a total of 111 workgroup meetings,
excluding Workstream Meetings !
16
UNC Project Nexus Planning Assumptions
  • Workgroups cannot all be worked concurrently
  • Resources
  • Dependencies
  • If one workshop planned every three/four weeks
    timescale of 2010 cannot be achieved, therefore-
  • 2 day workshops have been planned for Current
    Process Verification
  • 3 day workshops have been planned for To be
    processes
  • Consistency of approach/attendees
  • Less recapping on previous meetings
  • Longer days less travelling
  • Less Administration for all parties
  • Work content does not include any impact on
    accepting any iGT, Data Management/Smart Metering
    requirements
  • On smaller non-related topics
    Modifications/legal drafting raised as soon as
    possible, but will still need to be included in
    final consistency check
  • Review of Requirements to ensure that they are
    all still relevant

17
UNC Project Nexus Proposed High-level Plan
18
UNC Project Nexus Proposed Workgroup
Preparation Plan
19
UNC Project Nexus Proposed Workgroup Plan
20
UNC Project Nexus Planning Next Steps
What Who When
Feedback to approach plan Workstream 13th May 2009
Update approach, assumptions plan. xoserve 21st May 2009
Approach, assumptions plan agreed at Workstream Workstream 28th May 2009
Actual dates for all workshops,venues published xoserve 12th June 2009
Plan baselined Workstream 25th June 2009
Progress monitoring commences All Ongoing