Title: The Islamic University of Gaza Faculty of Engineering Civil Engineering Department Hydraulics - ECIV 3322
1The Islamic University of GazaFaculty of
EngineeringCivil Engineering Department
Hydraulics - ECIV 3322
Chapter 4
Water Distribution Systems
2Introduction
- To deliver water to individual consumers with
appropriate - quality, quantity, and pressure in a community
setting requires - an extensive system of
- Pipes.
- Storage reservoirs.
- Pumps.
- Other related accessories.
Distribution system is used to describe
collectively the facilities used to supply water
from its source to the point of usage .
3Methods of Supplying Water
- Depending on the topography relationship between
the source of supply and the consumer, water can
be transported by - Canals.
- Tunnels.
- Pipelines.
- The most common methods are
- Gravity supply
- Pumped supply
- Combined supply
4Gravity Supply
- The source of supply is at a sufficient elevation
above the distribution area (consumers). - so that the desired pressure can be maintained
-
HGL or EGL
Source (Reservoir)
(Consumers)
Gravity-Supply System
5Advantages of Gravity supply
HGL or EGL
Source
- No energy costs.
- Simple operation (fewer mechanical parts,
independence of power supply, .) - Low maintenance costs.
- No sudden pressure changes
6Pumped Supply
- ? Used whenever
- The source of water is lower than the area to
which we need to distribute water to (consumers) - The source cannot maintain minimum pressure
required. - ? pumps are used to develop the necessary head
(pressure) to distribute water to the consumer
and storage reservoirs.
HGL or EGL
(Consumers)
Source (River/Reservoir)
Pumped-Supply System
7Disadvantages of pumped supply
- Complicated operation and maintenance.
- Dependent on reliable power supply.
- Precautions have to be taken in order to enable
permanent supply - Stock with spare parts
- Alternative source of power supply .
HGL or EGL
(Consumers)
Source (River/Reservoir)
8Combined Supply(pumped-storage supply)
- Both pumps and storage reservoirs are used.
- This system is usually used in the following
cases - 1) When two sources of water are used to supply
water
Pumping
Source (1)
Gravity
HGL
HGL
Pumping station
City
Source (2)
9Combined Supply (Continue)
- 2) In the pumped system sometimes a storage
(elevated) tank is connected to the system.
- When the water consumption is low, the residual
water is pumped to the tank. - When the consumption is high the water flows
back to the consumer area by gravity.
Low consumption
High consumption
Elevated tank
Pumping station
Pipeline
City
Source
10Combined Supply (Continue)
- 3) When the source is lower than the consumer area
- A tank is constructed above the highest point in
the area, - Then the water is pumped from the source to the
storage tank (reservoir). - And the hence the water is distributed from the
reservoir by gravity.
Pumping
HGL
Gravity
HGL
Reservoir
Pumping Station
City
Source
11??? ???? ?????
- ???? ?? ?????? ????? ??? ??? ?? ??? ????
12Distribution Systems (Network Configurations )
- In laying the pipes through the distribution
area, the following configuration can be
distinguished - Branching system (Tree)
- Grid system (Looped)
- Combined system
13Branching System (tree system)
Branching System
- Advantages
- Simple to design and build.
- Less expensive than other systems.
14Disadvantages
- The large number of dead ends which results in
sedimentation and bacterial growths. - When repairs must be made to an individual line,
service connections beyond the point of repair
will be without water until the repairs are made.
- The pressure at the end of the line may become
undesirably low as additional extensions are
made.
15Grid System (Looped system)
Grid System
- Advantages
- The grid system overcomes all of the
difficulties of the branching system discussed
before. - No dead ends. (All of the pipes are
interconnected). - Water can reach a given point of withdrawal from
several directions.
16Disadvantages
- Hydraulically far more complicated than branching
system (Determination of the pipe sizes is
somewhat more complicated) . - Expensive (consists of a large number of loops).
But, it is the most reliable and used system.
17Combined System
Combined System
- It is a combination of both Grid and Branching
systems - This type is widely used all over the world.
18?? ??????
- ???? ???
- ???? ????? ?? ???? ??????
- ????? ????? ?? ???? ???????
- ????? ?????? ?? ?????
?????? - ?????? ????? ??
??? ?????? - ????
????? ?? ??? ?????? -
???? ????? ?? ?? ??????? -
??? ?????? ??? ?? ?????.
19Design of Water Distribution Systems
A properly designed water distribution system
should fulfill the following requirements
- Main requirements
- Satisfied quality and quantity standards
- Additional requirements
- To enable reliable operation during irregular
situations (power failure, fires..) - To be economically and financially viable,
ensuring income for operation, maintenance and
extension. - To be flexible with respect to the future
extensions.
20- The design of water distribution systems must
undergo through different studies and steps - Design Phases
Preliminary Studies
Network Layout
Hydraulic Analysis
21Preliminary Studies
Must be performed before starting the actual
design
- 4.3.A.1 Topographical Studies
- Contour lines (or controlling elevations).
- Digital maps showing present (and future) houses,
streets, lots, and so on.. - Location of water sources so to help locating
distribution reservoirs.
22Water Demand Studies
- Water consumption is ordinarily divided into
the following categories - Domestic demand.
- Industrial and Commercial demand.
-
- Agricultural demand.
- Fire demand.
- Leakage and Losses.
23Domestic demand
- It is the amount of water used for Drinking,
Cocking, Gardening, Car Washing, Bathing,
Laundry, Dish Washing, and Toilet Flushing. - The average water consumption is different from
one population to another. In Gaza strip the
average consumption is 70 L/capita/day which is
very low compared with other countries. For
example, it is 250 L/c/day in United States, and
it is 180 L/c/day for population live in Cairo
(Egypt). - The average consumption may increase with the
increase in standard of living. - The water consumption varies hourly, daily, and
monthly
24The total amount of water for domestic use is a
function of
Population increase
- How to predict the increase of population?
Geometric-increase model
Use
P0 recent population r rate of population
growth n design period in years P
population at the end of the design period.
The total domestic demand can be estimated using
Qdomestic Qavg P
25Industrial and Commercial demand
- It is the amount of water needed for factories,
offices, and stores. - Varies from one city to another and from one
country to another - Hence should be studied for each case separately.
- However, it is sometimes taken as a percentage of
the domestic demand.
26Agricultural demand
- It depends on the type of crops, soil, climate
Fire demand
- To resist fire, the network should save a certain
amount of water. - Many formulas can be used to estimate the amount
of water needed for fire.
27Fire demand Formulas
QF fire demand l/s P population in
thousands
QF fire demand l/s P population in
thousands
QF fire demand flow m3/d A areas of all
stories of the building under
consideration (m2 ) C constant depending on
the type of construction
The above formulas can be replaced with local
ones (Amounts of water needed for fire in these
formulas are high).
28Leakage and Losses
- This is unaccounted for water (UFW)
- It is attributable to
Errors in meter readings
Unauthorized connections
Leaks in the distribution system
29?????? ??????
?? ???? ??????? ??? ??? ????? ??????? ??????
???? ?? ?????
30Design Criteria
- Are the design limitations required to get
the most efficient and economical
water-distribution network
Pressure
Pipe Sizes
Design Period
Velocity
Head Losses
Average Water Consumption
31Velocity
- Not be lower than 0.6 m/s to prevent
sedimentation - Not be more than 3 m/s to prevent erosion and
high head losses. - Commonly used values are 1 - 1.5 m/sec.
32Pressure
- Pressure in municipal distribution systems ranges
from 150-300 kPa in residential districts with
structures of four stories or less and 400-500
kPa in commercial districts. - Also, for fire hydrants the pressure should not
be less than 150 kPa (15 m of water). -
- In general for any node in the network the
pressure should not be less than 25 m of water. -
- Moreover, the maximum pressure should be limited
to 70 m of water
33Pipe sizes
- Lines which provide only domestic flow may be as
small as 100 mm (4 in) but should not exceed 400
m in length (if dead-ended) or 600 m if connected
to the system at both ends. - Lines as small as 50-75 mm (2-3 in) are sometimes
used in small communities with length not to
exceed 100 m (if dead-ended) or 200 m if
connected at both ends. -
- The size of the small distribution mains is
seldom less than 150 mm (6 in) with cross mains
located at intervals not more than 180 m. - In high-value districts the minimum size is 200
mm (8 in) with cross-mains at the same maximum
spacing. Major streets are provided with lines
not less than 305 mm (12 in) in diameter.
34Head Losses
- Optimum range is 1-4 m/km.
- Maximum head loss should not exceed 10 m/km.
35Design Period for Water supply Components
- The economic design period of the components of a
distribution system depends on - Their life.
- First cost.
- And the ease of expandability.
36Average Water Consumption
- From the water demand (preliminary) studies,
estimate the average and peak water consumption
for the area.
37Network Layout
- Next step is to estimate pipe sizes on the basis
of water demand and local code requirements. - The pipes are then drawn on a digital map (using
AutoCAD, for example) starting from the water
source. - All the components (pipes, valves, fire hydrants)
of the water network should be shown on the
lines.
38Pipe Networks
- A hydraulic model is useful for examining the
impact of design and operation decisions. - Simple systems, such as those discussed in last
chapters can be solved using a hand calculator. - However, more complex systems require more effort
even for steady state conditions, but, as in
simple systems, the flow and pressure-head
distribution through a water distribution system
must satisfy the laws of conservation of mass and
energy.
39Pipe Networks
- The equations to solve Pipe network must satisfy
the following condition - The net flow into any junction must be zero
- The net head loss a round any closed loop must be
zero. The HGL at each junction must have one and
only one elevation - All head losses must satisfy the Moody and
minor-loss friction correlation
40Node, Loop, and Pipes
Pipe
Node
Loop
41Hydraulic Analysis
- After completing all preliminary studies and
layout drawing of the network, one of the methods
of hydraulic analysis is used to - Size the pipes and
- Assign the pressures and velocities required.
42Hydraulic Analysis of Water Networks
- The solution to the problem is based on the same
basic hydraulic principles that govern simple and
compound pipes that were discussed previously. - The following are the most common methods used to
analyze the Grid-system networks - Hardy Cross method.
- Sections method.
- Circle method.
- Computer programs (Epanet,Loop, Alied...)
43Hardy Cross Method
- This method is applicable to closed-loop pipe
networks (a complex set of pipes in parallel).
- It depends on the idea of head balance method
- Was originally devised by professor Hardy Cross.
44Assumptions / Steps of this method
- Assume that the water is withdrawn from nodes
only not directly from pipes. - The discharge, Q , entering the system will have
() value, and the discharge, Q , leaving the
system will have (-) value. - Usually neglect minor losses since these will be
small with respect to those in long pipes, i.e.
Or could be included as equivalent lengths in
each pipe. - Assume flows for each individual pipe in the
network. - At any junction (node), as done for pipes in
parallel,
or
45- Around any loop in the grid, the sum of head
losses must equal to zero - Conventionally, clockwise flows in a loop are
considered () and produce positive head losses
counterclockwise flows are then (-) and produce
negative head losses. - This fact is called the head balance of each
loop, and this can be valid only if the assumed Q
for each pipe, within the loop, is correct. - The probability of initially guessing all flow
rates correctly is virtually null. - Therefore, to balance the head around each loop,
a flow rate correction ( ) for each loop in
the network should be computed, and hence some
iteration scheme is needed.
46- After finding the discharge correction, (one
for each loop) , the assumed discharges Q0 are
adjusted and another iteration is carried out
until all corrections (values of ) become
zero or negligible. At this point the condition
of - is satisfied.
- Notes
- The flows in pipes common to two loops are
positive in one loop and negative in the other. - When calculated corrections are applied, with
careful attention to sign, pipes common to two
loops receive both corrections.
47How to find the correction value ( )
Neglect terms contains
For each loop
48- Note that if Hazen Williams (which is generally
used in this method) is used to find the head
losses, then
(n 1.85) , then
- If Darcy-Wiesbach is used to find the head
losses, then
(n 2) , then
49Example
Solve the following pipe network using Hazen
William Method CHW 100
24
12.6
11.4
39
D L pipe
150mm 305m 1
150mm 305m 2
200mm 610m 3
150mm 457m 4
200mm 153m 5
25.2
50(No Transcript)
51(No Transcript)
52Example
Solve the following pipe network using Hazen
William Method CHW 120
53Iteration 1
54(No Transcript)
55Iteration 2
56Iteration 3
57Example
- The figure below represents a simplified pipe
network. - Flows for the area have been disaggregated to the
nodes, and a major fire flow has been added at
node G. - The water enters the system at node A.
- Pipe diameters and lengths are shown on the
figure. - Find the flow rate of water in each pipe using
the Hazen-Williams equation with CHW 100. - Carry out calculations until the corrections are
less then 0.2 m3/min.
58- ???? ???? ????? ?? ????
- ??? ??? ???? ???? ?? ?????? ?????? ?? ??? ??
?????
59(No Transcript)
60(No Transcript)
61(No Transcript)
62(No Transcript)
63(No Transcript)
64(No Transcript)
65(No Transcript)
66(No Transcript)
67(No Transcript)
68General Notes
- Occasionally the assumed direction of flow will
be incorrect. In such cases the method will
produce corrections larger than the original flow
and in subsequent calculations the direction will
be reversed. - Even when the initial flow assumptions are poor,
the convergence will usually be rapid. Only in
unusual cases will more than three iterations be
necessary. - The method is applicable to the design of new
system or to evaluation of proposed changes in an
existing system. - The pressure calculation in the above example
assumes points are at equal elevations. If they
are not, the elevation difference must be
includes in the calculation. - The balanced network must then be reviewed to
assure that the velocity and pressure criteria
are satisfied. If some lines do not meet the
suggested criteria, it would be necessary to
increase the diameters of these pipes and repeat
the calculations.
69Summary
- Assigning clockwise flows and their associated
head losses are positive, the procedure is as
follows - Assume values of Q to satisfy ?Q 0.
- Calculate HL from Q using hf K1Q2 .
- If ?hf 0, then the solution is correct.
- If ?hf ? 0, then apply a correction factor, ?Q,
to all Q and repeat from step (2). - For practical purposes, the calculation is
usually terminated when ?hf lt 0.01 m or ?Q lt 1
L/s. - A reasonably efficient value of ?Q for rapid
convergence is given by
70Example
- The following example contains nodes with
different elevations and pressure heads. - Neglecting minor loses in the pipes, determine
- The flows in the pipes.
- The pressure heads at the nodes.
71Assume T 150C
72Assume flows magnitude and direction
73First Iteration
Pipe L (m) D (m) Q (m3/s) f hf (m) hf/Q (m/m3/s)
AB 600 0.25 0.12 0.0157 11.48 95.64
BE 200 0.10 0.01 0.0205 3.38 338.06
EF 600 0.15 -0.06 0.0171 -40.25 670.77
FA 200 0.20 -0.10 0.0162 -8.34 83.42
S -33.73 1187.89
74First Iteration
Pipe L (m) D (m) Q (m3/s) f hf (m) hf/Q (m/m3/s)
BC 600 0.15 0.05 0.0173 28.29 565.81
CD 200 0.10 0.01 0.0205 3.38 338.05
DE 600 0.15 -0.02 0.0189 -4.94 246.78
EB 200 0.10 -0.01 0.0205 -3.38 338.05
S 23.35 1488.7
75Second Iteration
14.20
14.20
7.84
14.20
14.20
Pipe L (m) D (m) Q (m3/s) f hf (m) hf/Q (m/m3/s)
AB 600 0.25 0.1342 0.0156 14.27 106.08
BE 200 0.10 0.03204 0.0186 31.48 982.60
EF 600 0.15 -0.0458 0.0174 -23.89 521.61
FA 200 0.20 -0.0858 0.0163 -6.21 72.33
S 15.65 1682.62
76Second Iteration
7.84
14.20
7.84
7.84
7.84
Pipe L (m) D (m) Q (m3/s) f hf (m) hf/Q (m/m3/s)
BC 600 0.15 0.04216 0.0176 20.37 483.24
CD 200 0.10 0.00216 0.0261 0.20 93.23
DE 600 0.15 -0.02784 0.0182 -9.22 331.23
EB 200 0.10 -0.03204 0.0186 -31.48 982.60
S -20.13 1890.60
77Third Iteration
Pipe L (m) D (m) Q (m3/s) f hf (m) hf/Q (m/m3/s)
AB 600 0.25 0.1296 0.0156 13.30 102.67
BE 200 0.10 0.02207 0.0190 15.30 693.08
EF 600 0.15 -0.05045 0.0173 -28.78 570.54
FA 200 0.20 -0.09045 0.0163 -6.87 75.97
S -7.05 1442.26
78Third Iteration
Pipe L (m) D (m) Q (m3/s) f hf (m) hf/Q (m/m3/s)
BC 600 0.15 0.04748 0.0174 25.61 539.30
CD 200 0.10 0.00748 0.0212 1.96 262.11
DE 600 0.15 -0.02252 0.0186 -6.17 274.07
EB 200 0.10 -0.02207 0.0190 -15.30 693.08
S 6.1 1768.56
79After applying Third correction
80Velocity and Pressure Heads
pipe Q (l/s) V (m/s) hf (m)
AB 131.99 2.689 13.79
BE 26.23 3.340 21.35
FE 48.01 2.717 26.16
AF 88.01 2.801 6.52
BC 45.76 2.589 23.85
CD 5.76 0.733 1.21
ED 24.24 1.372 7.09
13.79
23.85
1.21
21.35
6.52
26.16
7.09
81Velocity and Pressure Heads
Node p/gZ (m) Z (m) P/g (m)
A 70 30 40
B 56.21 25 31.21
C 32.36 20 12.36
D 31.15 20 11.15
E 37.32 22 15.32
F 63.48 25 38.48
13.79
23.85
21.35
1.21
6.52
7.09
26.16
82- Example
- For the square loop shown, find the discharge in
all the pipes. - All pipes are 1 km long and 300 mm in diameter,
with a friction - factor of 0.0163. Assume that minor losses can
be neglected.
83- Solution
- Assume values of Q to satisfy continuity
equations all at nodes. - The head loss is calculated using HL K1Q2
- HL hf hLm
- But minor losses can be neglected ? hLm 0
- Thus HL hf
- Head loss can be calculated using the
Darcy-Weisbach equation
84First trial Since ?HL gt 0.01 m,
then correction has to be applied.
Pipe Q (L/s) HL (m) HL/Q
AB 60 2.0 0.033
BC 40 0.886 0.0222
CD 0 0 0
AD -40 -0.886 0.0222
? 2.00 0.0774
85Second trial Since ?HL 0.01 m, then it is
OK. Thus, the discharge in each pipe is as
follows (to the nearest integer).
Pipe Q (L/s) HL (m) HL/Q
AB 47.08 1.23 0.0261
BC 27.08 0.407 0.015
CD -12.92 -0.092 0.007
AD -52.92 -1.555 0.0294
? -0.0107 0.07775
Pipe Discharge (L/s)
AB 47
BC 27
CD -13
AD -53