Title: FIRE Vacuum Vessel FY 03 Status and Plans
1FIRE Vacuum VesselFY 03 Status and Plans
- B. Nelson
- FIRE project meeting
- November 7, 2002
- PPPL
2(No Transcript)
3Presentation outline
- Status of vacuum vessel task area
- Geometry
- Design concept and features
- Analysis to date
- FY03 Plans
- Address open technical issues using the 2 m
design - Develop / define requirements and model VV for
2.14 m geometry - Prepare for PVR
4FIRE vacuum vessel
5VV parameters 2.14 m (2 m) design
- Configuration Double wall torus
- Shielding water steel with 60 packing
factor - Volume of torus interior 53 m3 (was 35)
- Surface Area of torus interior 112 m2 (was 89)
- Facesheet thickness 15 mm
- Rib thickness 15 - 30 mm
- Weight of structure, incl ports 65 tonnes (was
50) - Weight of torus shielding 100 tonnes (was 80)
- Coolant
- Normal Operation Water, lt 100C, lt 1 Mpa
- Bake-out Water 150C, lt 1 Mpa
- Materials
- Torus, ports and structure 316LN ss
- Shielding 304L ss (tentative)
6Active and passive stabilizing sys.
- passive plates 25 mm thick copper with integral
cooling
RWM coils?
Active control coils, segmented into octants
IB and OB passive stabilizing conductor
7VV octant subassy w/passive structure
Outboard passive conductor
Inboard passive cond.
Vessel octant prior to welding outer skin between
ribs
8Passive conductor is also heat sink
- Copper layer required to prevent large
temperature gradients in VV due to nuclear
heating, PFCs - Passive plates are required in most locations
anyway - PFCs are conduction cooled to copper layer
- Reduces gradient in stainless skin
- Extends pulse length
9Vessel analysis to date
- Vessel subjected to numerous loading conditions
- Normal operation (gravity, coolant pressure,
thermal loads, etc.) - Disruption (including induced and conductive
(halo) loads - Other loads (TF current ramp, seismic, etc.)
- Preliminary FEA analysis performed on 2.0 m
geometry - Linear, static stress analysis
- Linear, transient and static thermal analyses
- Main issues are disruption loads, thermal
stresses
10Vacuum vessel mechanical loads
11TSC runs confirm induced currents will
concentrate in passive structures
- Several TSC disruption simulations prepared by C.
Kessel - Centered disruption induces 5 MA in passive
plates (out of 6.5, now 7.7)
- VDE simulation used as basis for further analysis
12VDE analysis based on TSC runs
- TSC output used to create drivers for Eddycuff
model of VV - Peak loads applied to ANSYS model of VV
- Halo loads from TSC mapped directly onto VV model
Inner Face Sheet
Outer Face Sheet
Copper Plates
EDDYCUFF EM Model
ANSYS Structural Model
13Plasma Evolution (TSC)
14Current vs Time
Plasma Current
Induced Vessel Current
15Induced Eddy Currents at Time 302-ms (end of
plasma current quench)
Constant Current Vectors
Proportional Current Vectors
16EM Pressure due to Induced Tor. Current
- Max force -1.4-MN radial, 1.2-MN vertical per
1/16 sector (19 MN tot)
17EM Forces due to Halo Current
- Mapped directly from TSC to ANSYS, Halo current
16 Ip - Max force -0.24-MN radial, 0.48-MN vert. per
1/16 sector (8MN tot.)
18Divertor loads from current loop
- Loads based on PC-Opera analysis ref
Driemeyer, Ulrickson
19Combined stress, with VDE
- Stresses due to gravity, coolant pressure,
vacuum, VDE - VDE load includes direct EM loads on vessel
(induced current and halo) and non-halo divertor
loads
Stress concentrations around div suport pins
(need reinforcement and finer FEA model)
1.5Sm 26 ksi (195 Mpa)
Stress is in psi
Stress gt 50 ksi is in gray color
20Nuclear htg and thermal effects
- Vacuum vessel is subject to two basic heat loads
- Direct nuclear heating from neutrons and gammas
- Heating by conduction from first wall tiles
(which in turn are heated by direct nuclear
heating and surface heat flux) - A range of operating scenarios is possible, but
the baseline case for analysis assumes - 200 MW fusion power, 150 MW is current baseline
- 100 W/cm2 surface heat load on first wall, 45
MW/cm2 is current baseline - pulse length of 20 seconds
- Vessel is cooled by water
- Flowing in copper first wall cladding
- Flowing between walls of double wall structure
21Heat loads on vessel, at IB midplane
- Fusion power of 200 MW (baseline power is 150 MW)
- Surface heat flux is variable, but 100 W/cm2 is
assumed
Volumetric Nuclear Heating, IB
midplane Location (W/cm3) A - Be FW 33.3 B
- Cu FW 46.9 C VV 33.8 D VV
30.3 ref M. Sawan
B
C
D
A
Cu cladding
Double wall VV
Tile
222-D temp distr after 20 sec pulse
- Inboard midplane Outboard midplane
23Nuclear heating distribution
Neutron wall loading Volumetric heating
plasma side coil side divertor
243-D temp distr in VV after 20 s
25VV thermal deformation and stress
Peak
- Stress
- (High stress region very localized)
Deformation (Max 3 mm)
26Combined stresses, 20 s pulse
- Nuclear heating, gravity, coolant pressure, vacuum
- Only very local regions exceed 3Sm (390 Mpa or
52 ksi)
27Combined stresses, 20 s pulse, with VDE
- Nuclear heating, gravity, coolant pressure,
vacuum, VDE
Only facesheets and Cu are plotted
Stress is in psi
28Conclusions of analysis so far
- Have disruption loads been analyzed? YES
- but additional load cases must be run using
updated geometry - Does Vacuum Vessel limit pulse length? ITS CLOSE
- 20 second pulse should be achieveable
- Thicker tiles, external heaters are options to be
explored for more margin - What would logically be next?
- Optimized geometry and refined FEA models
- Revised load cases, including lower fusion power,
lower surface heat flux, higher plasma current - Dynamic analysis
- Fatigue analysis, including plastic effects
29Task 1 Address open technical issues
- Scale existing thermal and thermal stress
analysis of vessel for revised fusion power and
pulse length combinations (2-D, approx. 3-D
calc.) - Run new thermal stress analysis with preheated
outboard wall, thicker tiles on outboard - Perform self-consistent EM calculations for new
disruption cases (Dennis Strickler has run some
cases) - Integrate FW tiles / magnetic loops with VV
- Schedule Now through June
- Resources TBD, but budget 2 man months
30Task 1b Technical issues outside budget
- Develop, in conjunction with RH and PFC groups,
the basic divertor and FW attachment schemes
consistent with loads and RH requirements - Perform integrated structural analysis of vacuum
vessel for disruption load conditions, including
divertors, tiles, and port mounted equipment - Develop, in conjunction with RH, the basic
concepts for structural and vacuum interfaces
between the port plugs and the vessel - Re-evaluate vessel supports
- Develop basic plumbing schematic for cooling
water, leak checking -
- Schedule TBD
- Resources TBD
31Task 2 Requirements definition
- New Geometry
- What is the radial and vertical build?
- What is space needed for RWM coils?
- How much do we tweak VV geometry to solve stress
issues? - Operating basis, including fusion power, pulse
length, plasma current, field - What will be the baseline operating space?
- Ports for diagnostic access, especially any
tangential viewing requirements - Ken Young is developing this
- Diagnostic magnetic loops / coils
- Ken Young is defining these, and they may have
significant design impact due to large number and
type (50 toroidal loops, 10 saddle coils, BR/BZ
coils, 2 arrays of 70 each, toroidal and poloidal
arrays of Mirnov coils and some number of
diagnostic sockets) - Schedule Now through April?
- Resources TBD, but ltlt 1 man months budget
available
32Vessel shell dimensions to tweak
33Task 3 Prepare for PVR
- Summarize baseline design and analysis
- Re-model VV??
- Attend PVR (?)
- Schedule July, primarily
- Resources TBD, budget lt 1 man months
34Summary
- Draft task list for FY-03 has been developed
- Technical issues to be addressed include
- Combined disruption / thermal stress estimates
and thermal stress limit on pulse length - Look at potential fixes for thermal stress
problem - Magnetic diagnostic integration
- Technical issues to be defered include
- in-vessel component attachments and integrated
analysis - Port plug integration
- Requirements definition is key task for migration
to 2.14 m size - Geometry sizes, thicknesses, for stress
problems, RWM coils - Baseline performance envelope
- Diagnostic access, especially magnetic
diagnostics (do we need more space inboard?) - Preparation for PVR is primary milestone for
FY-03
35Preliminary VV stress summary
36Additional backup slides
37Vacuum vessel design issues
- Thermal stresses vs pulse length
- Disruptions
- Load definition
- Divertor supports
- Vessel supports
- Passive stabilizing conductor integration / fab
- Concepts are being developed for
- Divertor interface
- Vertical and lateral supports
38Vessel octant subassembly fab. (3)
- Octant-to-octant splice joint requires double
wall weld - All welding done from plasma side of vessel
- Splice plates used on plasma side only to take up
tolerance and provide clearance - Plasma side splice plate wide enough to
accommodate welding the coil side joint
39Vessel port configuration
40Vessel port details
Auxiliary port Port dimensions 0.47 x .104 x
.180 m Cross sectional area of port .067 m2
Midplane port Port dimensions 0.71 x 0.63 x
1.25 m Cross sectional area of port .8 m2
41Vessel inboard shell fabrication
Weld the formed extrusions together
- Machine surfaces of steel weldment,
- Fab copper by gun drilling/machining or use a
sandwich structure - Attach manifolds to copper
Diffusion bond the formed copper assembly to the
steel assembly
42Vessel outboard shell fabrication
Diffusion bond copper to inner face sheet
Join two ½ sections to form one octant
- Weld ribs and port stubs to inner skin
- Add conduit for active control coils
43Vessel upper and lower shell fab.
Form and trim inner skin
- Weld ribs to inner skin
- Add port reinforcing stubs
44Vessel octant subassembly fab.
Weld inner skins and ribs of inboard, outboard,
top and bottom sections together
Add shielding subassemblies between ribs
45Vessel octant subassembly fab. (2)
Add outer skin on / between ribs
Completed octant ready for assembly
46VV analysis, ANSYS FEA model
- Model prepared by HM Fan
- 64 poloidal ribs inboard, 64 poloidal ribs
outboard - thickness of elements assumed as
- 15 mm for vessel facesheets,
- 30 mm for port at midplane,
- 15 mm for port above/below midplane,
- 15 mm for most poloidal ribs,
- 30 mm for OB ribs at supports
- 25 mm for copper stabilizers
Ref H.M. Fan
47Heat loads on vessel, at midplane
- Fusion power of 200 MW
- Surface heat flux is variable, but 100 W/cm2 is
assumed
Volumetric Nuclear Heating, IB
midplane Location (W/cm3) A - Be FW 33.3 B
- Cu FW 46.9 C VV 33.8 D VV
30.3 ref M. Sawan
B
C
D
A
Cu cladding
Double wall VV
Tile
48Nuclear heating distribution
Neutron wall loading Volumetric heating
plasma side coil side divertor
492-D temp distr after 20 sec pulse
- Inboard midplane Outboard midplane
50VV thermal stress in skin and ribs