Scaffold Appreciation - PowerPoint PPT Presentation

1 / 23
About This Presentation
Title:

Scaffold Appreciation

Description:

CISRS scaffold cards indicate training, but not necessarily ... should wear a harness with lanyard, shock absorber and scaffold hook for one handed operation. ... – PowerPoint PPT presentation

Number of Views:534
Avg rating:3.0/5.0
Slides: 24
Provided by: hsf
Category:

less

Transcript and Presenter's Notes

Title: Scaffold Appreciation


1
Scaffold Appreciation
  • Session 3 Site Practices

2
Preparation
  • Risk Assessment
  • Organise, Plan and Manage
  • Method Statement
  • HASAW Section 3 generally applies
  • CISRS scaffold cards indicate training, but not
    necessarily competency
  • Level of Training, basic - advanced

3
Supervision
  • HASAW applies
  • Appropriate to the work task
  • Supervisor should be an advanced scaffolder
  • Must stick to the method statement
  • Vicarious liability can apply

4
Public Protection
  • Additional precautions must be taken to prevent
    the public entering a work area
  • Can apply to unloading of lorries as well as work
    areas
  • Protect public from falling objects
  • Secure tools, exclusion zones, fans, temporary
    structures etc.

5
Falls
  • Account for more than half of the fatalities in
    construction annually
  • Scaffolders have to work in hazardous situations
  • Working methods should be as safe as reasonably
    practicable
  • Safety harnesses issued and used by all
    scaffolders

6
Illustration
7
CDM
  • CDM Regs 1994 place duties on client, designer
    and principle contractor to eliminate/reduce
    hazards
  • Reasonable steps should be taken to provide good
    anchorage points

8
Harnesses
  • All involved in scaffolding should wear a harness
    with lanyard, shock absorber and scaffold hook
    for one handed operation.
  • They must receive appropriate and recorded
    training in use, maintenance and inspection
  • A suitable anchor point must be used to clip on
  • Guardrails should be erected as a matter of
    priority at all locations at which a fall can
    occur

9
Clipping On
  • Scaffolders must clip on at the first suitable
    anchor point at 4m or more above ground level
    when
  • Not working in a protected area
  • Moving their working platform
  • Climbing up or down the structure
  • Working directly of the structure
  • Anchor points should be above waist height
  • Adopt a method of work which will limit
    traversing an exposed edge

10
Illustrations
11
Illustrations
12
Materials
  • When raising or lowering materials Scaffolders
    should be clipped on at all times
  • Working within guardrails is preferable to
    clipping off if it can be achieved
  • Manual handling issues should be considered

13
Illustrations
14
Ladder Access
  • Ladders should be included as early as possible
    and removed as late as possible
  • This will reduce the need for scaffolders to
    climb the structure
  • Recommend that a ladder bay is constructed in the
    early part of the operation

15
Decking
  • Scaffolders should use a minimum 600mm wide
    platform placed centrally
  • On wider structures, scaffolders should utilise
    sufficient boards to allow space to clip on
  • Boards used for decking should be adequately
    supported by transoms and bearers as appropriate

16
Illustration
17
Anchor Points
  • Attachment to horizontal tubes only by an
    appropriate scaffold hook
  • Scaffold should be tied in before anchoring
  • Avoid hooking on near joints
  • Rescue plan must be in place
  • Suspension trauma must be considered

18
Illustration
19
Ladders
  • Timber ladders only
  • Do not paint timber ladders
  • Wire rods beneath the rungs
  • Should extend 1 metre above the working platform
  • Landing stage required if more than 9 metres
  • Must be secured, lashed or clipped

20
Rubbish Chutes
  • Scaffold design must take into account the
    additional loads imposed
  • Must be securely fixed
  • Must be inspected prior to use
  • Anchored every 6 metres
  • Competent person for chute operations

21
Care and Maintenance of Materials
  • Maintenance is of prime importance
  • Tubes should only be straightened by experts
  • Damage tube should be cut out and discarded
  • Split or damaged boards should be discarded
  • Hoops or bands should be replace as required
  • Steel should be checked for corrosion,
    excessively corroded tube should be discarded.
  • Couplers and fitting should be lubricated and
    inspected before use.
  • Particular attention should be paid to threads.

22
Dismantling
  • Normal procedure is to dismantle in reverse order
  • Dismantling should be carried out progressively
  • Guardrails should be left in position as long as
    possible
  • Additional temporary ties may be required
  • Warning signs should be displayed on partially
    dismantled scaffold
  • Materials must be lowered carefully not dropped
  • The public must be protected at all times

23
Sheeting and Debris Netting
  • Debris netting does not replace brick guards
  • Sheeted scaffolds must be designed
  • Sheets must be securely tied using the correct
    ties
  • Wind loading must be countered by extra bracing
Write a Comment
User Comments (0)
About PowerShow.com