Title: TTC Information Meeting
1TTC Information Meeting
2Aims of this meeting
- Agreement on
- Clock sources
- TTC backbone upgrade principle
- Discussion on
- TTCmi upgrade specifications
- Information on
- Fibres/attenuators procurement
- 2005 commissioning
- 2006 Test Beam
- TTC module production
- AOB
3Available Clocks/Orbits TTC upgrade TTC
backbone upgrade TTCmi upgrade
Fibres/attenuators procurement2005
commissioning 2006 Test Beam Production news
AOB
4RF signal definition
- 2 rings
- 1 RF system / ring
- independent
- During the acceleration ramp, can be driven at
different frequencies (p-Pb collisions) - the 2 RF are naturally convergent, and are equal
to a reference value during physics - For observation during the acceleration ramp, the
2 RF are provided to AB/BDI via BST and
experiments via TTC.
5RF signal generation
- RF tracks the raising magnetic field during the
ramp - RF sinusoidal signal with its phase changing
continuously - RF Spectrum is not perfectly clean (spurious)
- Might be a problem for the beam lifetime
(potential emittance blow-up) - Filtering expected from the VCXO, but still a
concern - To solve this (potential) noise problem
- use a fixed reference frequency, generated by a
pure commercial synthesizer. - Once at top energy, before the physics starts,
re-synchronizing of the 2 rings with this
reference. (like during test beams). More complex.
6At the TTC level
- Signal artifacts (reminder)
- Nothing during access, after beam dump, during
shut-down or repair - During physics the RF guaranties a clean, stable,
non-interrupted BC and Frev - Implications for TTC
- Is this reference clock needed?
- gt if yes, we have to ask the RF to provide it
- Need for common clock outside the LHC physics?
(Cosmics, ) - Need to be able to switch from the machine clock
to a internal clock outside the guaranteed period
7Available Clocks/Orbits TTC upgrade TTC
backbone upgrade TTCmi upgrade
Fibres/attenuators procurement2005
commissioning 2006 Test Beam Production news
AOB
8TTC system status
- The TTC transmission crates (in CCC) are getting
old - Only 4 crates 1
- The number of RF pairs have increased
- Some lasers are ageing
- and are obsolete as some other components
- Some schematics are missing
- Same problem for the receiving crates in
experiments and labs - Only 12 crates, and also getting obsolete
- We are crucially missing remote monitoring
9TTC backbone upgrade
- Backbone from SR4 to the experiments
10TTC backbone upgrade options
- OPTION 1 redesign the TTC crates in CCC
- 3 central crates in the CCC spares (assuming
that the reference clock is needed) - New hardware, with
- Signal shaping (RF signals are sinusoidal)
- monitoring
- BC switching - PLL
- Transmission protocol
- Re-encoding, or
- 2 separated fibres
PRINCIPLE basically just re-transmit the signals
delivered by the RF
QUESTION who will do the 24/24 support?
11TTC backbone upgrade options
- OPTION 2 AB/RF extends the transmission of its
signals up to the experiments - Could deliver directly to the experiments
- RF frequency /10 (40.078xx MHz) - sinusoidal
- Orbit pulse 5ns
- Probably on 2 separated fibres
- RF receivers VME64 6U modules with a simple
monitoring of the optical signal via VME - No special hardware needed (VME 6U crate SBC
for monitoring) - A priori, 2 rx or 2 tx per RF module (BC and
Orbit on separated fibres) - 1 rx/tx pair 5000
- New TTC module design required (TTCmi)
- signal shaping,
- monitoring,
- Clock switching
- PLL
- Clock Orbit Fanout
- INTEREST
- Rx/Tx hardware already selected
- Existing team for the RF support (RF piquet)
PRINCIPLE basically just extend the signals
delivered by the RF up to the experiments
12TTC backbone upgrade options
- If agreement on this option 2
- Possible(?) transmission schemes for
information - No optical fibres have been reserved for the TTC
even in the previous scheme gt should be reserved
asap - Point 7 forbidden for fibres in the tunnel (very
high radiations) - Probably 2 separated fibres for BC and Orbit
- Estimated price for tx/rx per experiment 3x5000
30.000 - Technical solutions will be chosen proposed by
the AB/RF if this option 2 is required and
accepted - Should not take into account the drift with
temperature will be solved presumably
internally in the experiments if needed
13TTC backbone upgrade options
- Conclusion
- Asking the AB/RF group to extend the
transmission of the RF signals seems to be
logical and safer for the system maintenance
14TTC backbone upgrade options
- And now ?
- Many technical discussions already with AB/RF and
TS/EL - Option2 seems to be technically possible (surface
or tunnel) - Needs agreement from the experiments
- If the experiments agree on this
- Needs agreement from AB
- Write an EDMS document in collaboration with the
PH and AB departments - to agree on the principle of the change of
responsibilities - Propose/define a way of financing this change
- Technical solutions will be added later according
to the AB/RF and experiment constraints and
preferences - Begin the specification and design of the new
TTCmi module
15Proposal 40 MHz/Frev distributed by AB/RF
- All experiments must agree.
- We (AB/RF) choose the implementation
- Simple point to point analog optical link.
- Receiver in 160 mm-6U VME cards housed in a VME
crate (monitoring of optical power accessible
from CCR). - No compensation of thermal drifts.
- 6 ns drift in ½ year for 10 km long link
(measured) - 100 ps drift in ½ day for 10 km long link
(measured) - Receiving modules must be located in a room that
is easily accessible to our piquet service. - Hardware must be paid for by the experiments.
16Available Clocks/Orbits TTC upgrade TTC
backbone upgrade TTCmi upgrade
Fibres/attenuators procurement2005
commissioning 2006 Test Beam Production news
AOB
17TTCmi upgrade
- Must follow the backbone upgrade option
- If option2 is chosen gt Required
- Signal shaping RF signals sinusoidal
- Clock switching
- Automatic
- Using the machine timing events (GMT or BOBR)
- PLL
- Fanout
- Monitoring
- Form factor
- Presumably VME64x 6U to fit with
- RF receivers
- GMT mezzanine SBC
- Quantities
- 3 per experiments (many) spares
18Available Clocks/Orbits TTC upgrade TTC
backbone upgrade TTCmi upgrade
Fibres/attenuators procurement2005
commissioning 2006 Test Beam Production news
AOB
19Fibres/attenuators procurement
- For single mode patch-cords (9/125um, ST/PC), the
standard available lengths/approx prices are - Simplex 1m 15 Sfr., 2m 16 Sfr., 5m 17 Sfr., 10m
20 Sfr. - Duplex 1m 30 Sfr., 2m 32 Sfr., 5m 34 Sfr., 10m
40 Sfr. - For single mode attenuators, the standard
attenuation levels are - 3dB, 5dB (for connection between TTCex and TTCrq
with a 116 splitter) - 10dB
- 15dB (for connection between TTCex and TTCrq
without a splitter) - For caps, the 2 types are
- female (transmitter/coupler/receiver side)
- male (fibre side)
20Fibres/attenuators procurement
- provided by the TS/EL group not by the Stores
because of administrative complications - Some patch-cords, attenuators and caps as
describe above will be stored in TS/EL for urgent
request, - the normal delay you can expect for delivery will
be 15 days. - To place an order, send
- a budget code
- the description of what you need to
- Oystein Olsen (Oystein.Olsen_at_cern.ch)
- with a copy to Luit de Jonge (Luit.Koert.de.Jonge_at_
cern.ch). - If you have some special request (special fibre,
connector type, attenuators, etc...), you can as
well contact Oystein Olsen or Luit De Jonge.
21Available Clocks/Orbits TTC upgrade TTC
backbone upgrade TTCmi upgrade
Fibres/attenuators procurement2005
commissioning 2006 Test Beam requirements
Production news AOB
222005 commissioning
- Fibres and signal potentially available
- Possible to receive a clock from a central TTC
transmitter crate installed in AB/CO lab - Fibres installed from AB/CO to CCC and from CCC
to SR - Just ask if you need to receive the signal
- Patch at the CCC
- Turn on the crate and verify the quality of the
transmission
232005 commissioning
- Material probably available at the Pool this
summer - OTDR negotiations with LUCIOL in course
- Used for length measurement (2-3 cm precision)
- Or as a classical OTDR (connection quality, error
location..) - A priori, 2 would be purchased
- VFL Visual Fault Locator
- Optical Power Meters
24Available Clocks/Orbits TTC upgrade TTC
backbone upgrade TTCmi upgrade
Fibres/attenuators procurement2005
commissioning2006 Test BeamProduction news AOB
252006 Test Beam
- ATLAS, CMS and LHCb requested a 25ns beam during
next year test beam - ALICE?
- Please send me the needs you may have in term of
TTC installation, so as we can either use the new
scheme or the current one.
26Available Clocks/Orbits TTC upgrade TTC
backbone upgrade TTCmi upgrade
Fibres/attenuators procurement2005
commissioning 2006 Test Beam Production news
AOB
27Production news
- TTCrq V5
- 1st batch delivered in March 200 boards
- 2nd batch 2200
- PCB in production
- New tester board
- Delivery August
- TTCex/tx
- PCB produced
- Assembly now
- Store delays () components for 60 modules
- 20 tx and 30 ex presently being assembled
- The rest as soon as the components arrive
- TTCvi
- 10 already produced but still at EFACEC needed?
- The rest mid-june
- TTCoc
- DAI still in the purchasing office
- But should leave CERN soon
- TTCoc16 2-3 weeks delivery delays
28Available Clocks/Orbits TTC upgrade TTC
backbone upgrade TTCmi upgrade
Fibres/attenuators procurement2005
commissioning 2006 Test Beam Production news
AOB
29AOB
- TTC Clock Gen
- Prototypes being assembled now
- Manual switch for internal/external clock
- 40.078MHz
- 6 ECL outputs
- 1 TTL
- 2LVDS
- TTCrq back from radiation
- Regulators were monitored during radiation tests
in December (F. Anghinolfi) - OK - LVDS drivers to be tested next week
- GBT13 for SLHC discussions are beginning
30Required to move forward
- Do the experiments
- need the Reference Clock?
- need a common 40MHz clock outside the physics?
- agree on the principle of asking the AB/RF group
to extend the signal transmission? - need to standardize more components?
- need something special for the commissioning?
- need something special for the 25ns beam next year
Available Clocks/Orbits TTC upgrade TTC
backbone TTCmi Fibres/attenuators
procurement2005 commissioning 2006 Test Beam