Title: Gate Review Process
1Gate Review Process
- presented at DODCAS 2009 DON Session
- CAPT Jim Baratta
- Deputy Director, NCCA
2Gate Review Process Overview
- Purpose
- improve governance and insight
- ensure alignment between capability requirements
and acquisition - improve senior leadership decision making
- gain better understanding of RISKS and COSTS
- Objectives
- endorse or approve key JCIDS and acquisition
documents - facilitate decisions regarding capabilities and
material solutions - 2-Pass, 6-Gate Process
- address Requirements and Acquisition governance
respectively - EVERY GATE reviews program health cost, risks,
budget
3Gate Review BoardMembership
- Principal (voting) members
- CNO / CMC / VCNO / ACMC
- ASN (RDA) / PDASN
- ASN (FMC)
- OPNAV N8 / HQMC DC PR and DC CDI
- Appropriate SYSCOM Commander
- Advisory (non-voting) members
- Resource Sponsor, CHSENG
- N80, N81, N091, FMB
- Cognizant DASN
- DASN (CE)
- Attendance limited to Principal or Deputy
(Flag/SES) plus one
4Pass 1 Gates
- Gates 1, 2, and 3 Requirements Gates
- Led by CNO or CMC
- Starts prior to Material Development Decision,
ends after Gate 3 - Leads to
- Approving the ICD
- Approving AOA guidance
- Selecting an AOA optimal alternative
- Approving a CDD
- Developing a CONOPS
- Approving System Design Specification (SDS)
Development Plan
5Pass 2 Gates
- Gates 4, 5, and 6 Acquisition Gates
- Led by ASN(RDA)
- Starts after Gate 3, ends after Milestone B
(initial EMD phase) - Leads to
- Approving the SDS
- Approving release of the RFP
- Assessing readiness for production
- Assessing sufficiency of the EVMS PMB
- Assessing the IBR
- Follow-on Gate 6s pre- and post-Milestone C and
FRP DR - Serve as Configuration Steering Boards and review
program health
6Pass 1 Requirements Gates
- Gate 1 Approval of the ICD
- input Service review of the ICD
- brief AoA assumptions, cost constraints and
life-cycle considerations - outcome Validates AoA guidance, authorizes to
proceed to MSA phase - Gate 2 Approval of the preferred alternative
- input Approved ICD, AoA, sufficiently mature
MS-A documentation - brief AoA assumptions, analysis, findings,
preliminary TRL assessment - brief Projected life cycle costs for all AoA
options - outcome Approves development of CDD and CONOPS
for alternative
7Pass 1 Requirements Gates
- Gate 3 Approval of the Service CDD and CONOPS
- input Approved AoA, SDS development plan
- input Service review of CDD/CONOPS,
- supports LCCE (employment, sustainment, training,
manning, etc) - brief Initial independent cost estimate
schedule assessment - brief Compare to PM estimates
- outcome Approves the CDD/CONOPS, SDS development
plan - outcome Approves program to MS-A (or with MS-B
preparations)
8Pass 2 Acquisition Gates
- Gate 4 Approval of the SDS
- may be combined with Gate 5 and MS-B for ACAT
IC/IAC/II - input Approved CDD, CONOPS, and review of SDS
- input Independent cost estimate, PM cost
estimate, budget - brief Capability, risk, independent/PM
cost/schedule estimates - outcome Authorizes program to proceed to Gate 5
(or Milestone B) - Gate 5 Approval of release of the RFP
- may be before, concurrent with, or after MS-B
- input Approved SDS, key business elements in
acquisition strategy - brief Capability, risk, independent/PM cost and
schedule estimates - outcome RFP approval for release to industry
9Pass 2 Acquisition Gates
- Gate 6 Assesses readiness for production
- occurs after contract award and IBR completion
- input Source Selection completed, contract
awarded, IBR completed - brief Capability, risk, independent/PM cost and
schedule estimates - brief Assesses IBR results, sufficiency of the
SDS and EVMS PMB (EAC) - outcome follow-on Gate 6 reviews prior to and
post MS-C, FRP DR - Gate 6 follow-on Pre-LRIP, Pre-FRP DR
- as needed tailored approach
- specific elements undefined in SECNAV 5000.2,
same as Gate 6
10PASS 1
PASS 2
OSD/JOINT LEVEL
MS B
JROC
JROC
MS A
JROC
CD
NAVY/USMC LEVEL
2
5
1
3
4
6
SDD
SSAC
CDD and CONOPS Approval
ICD Approval
Alternative Selection
SDS Approval
RFP Approval
Contract Award
CBA
Forum Lead Org Chair
R3B OPNAV/HQMC CNO (N8)/DC, CDI
R3B OPNAV/HQMC CNO/CMC
R3B ASN(RDA) ASN(RDA)
R3B ASN(RDA) ASN(RDA)
R3B ASN(RDA) ASN(RDA)
R3B OPNAV/HQMC CNO/CMC
PEO/SYSCOM/ OPNAV/HQMC LEVEL
IBR
AOA
CONOPS CDD
InitiaI SDS
RFP
Updated SDS
Illustrated example for program initiation at
Milestone A
11PASS 1
PASS 2
OSD/JOINT LEVEL
MS B
JROC
MS A
JROC
CD
NAVY/USMC LEVEL
2
1
3
5
4
6
SDD
SSAC
CDD and CONOPS Approval
ICD Approval
Alternative Selection
SDS Approval
RFP Approval
Contract Award
CBA
Forum Lead Org Chair
R3B OPNAV/HQMC CNO (N8)/DC, CDI
R3B OPNAV/HQMC CNO/CMC
R3B ASN(RDA) ASN(RDA)
R3B ASN(RDA) ASN(RDA)
R3B ASN(RDA) ASN(RDA)
R3B OPNAV/HQMC CNO/CMC
PEO/SYSCOM/ OPNAV/HQMC LEVEL
InitiaI SDS
IBR
AOA
CONOPS CDD
RFP
Updated SDS
Illustrated example for program initiation at
Milestone B
12Program Cost UncertaintyOver Time
Pre Systems Acquisition
Pre Systems Acquisition
Systems Acquisition
Sustainment
vs. BUDGET?
Material Solution Analysis
Technology Development
Engineering Manufacturing Development
Production Deployment
Operations Support
Cost, Technical, and Programmatic Uncertainty
A
B
C
IOC
FOC
Disposal
Gate Reviews
1
2
3
4
5
6
6 fo
6 fo
6 fo
ITR
ASR
SRR
IBR
PDR
TRR
OTRR
PCR
Technical Reviews
Preferred System Concept
System Specification/ CDD
SFR
Allocated Baseline
CDR
FRR
SVR/PRR
ECPR
System Functional Baseline
Product Baseline
Product Baseline
Parametric Analogy
Parametric Analogy
Engineering
Build-Up
Parametric Analogy
Extrapolate
Actuals
Engineering
Build-Up Parametric
Extrapolation of
Actuals Engineering Build-Up
Estimating Techniques
13Gate Review ProcessPotential Cost Community
disconnects?
- How often are the programs definition and bounds
changing during the pre-MS-B timeframe? - What reliable data is available to estimate a
program this early in its acquisition life cycle? - What documents are complete and approved leading
up to each Gate? - To what extent are CAIV decisions still being
made prior to RFP release? - Do best practice estimating methods allow
significant cost estimate confidence at this
point? - As the estimate progresses, in what ballpark
should the estimates upper bound of range be
expected to cover potential costs into MS-B? - How will the range and estimates be used to
program a budget at this early phase in the
program? - What value does an independent assessment add in
the early requirements Gates?
14Questions?
COST ANALYSIS
Go Army!
15Cost Estimate Confidence thru Pre-MS-B Phase of
Programs
PROGRAMMATICBASELINE
Mature? Stable?
TECHBASELINE
Defined? Steady?
Analogy? Parametric? Program info?
SCORE
COSTDATA
Methodology? Underlying data?
ESTIMATECONFIDENCE
Budget supportable?
OVERRUNPOTENTIAL
ESTIMATESTABILITY
MOST CASES WILL BE RED OR YELLOW
Upper Bounds Stable?
Small changes early in program life?
COSTRISK