BUILD OPERATE TRANSFER - PowerPoint PPT Presentation

1 / 47
About This Presentation
Title:

BUILD OPERATE TRANSFER

Description:

Organizing the Olympic games. Planning a party or wedding. 6. CONSTRUCTION MANAGEMENT ( ARE 413) ... Ability to influence decisions falls off sharply as time on ... – PowerPoint PPT presentation

Number of Views:445
Avg rating:3.0/5.0
Slides: 48
Provided by: mohammedj
Category:

less

Transcript and Presenter's Notes

Title: BUILD OPERATE TRANSFER


1
CONSTRUCTION MANAGEMENT
ARE 413 CONSTRUCTION MANAGEMENT CLASS -2 By
MOHAMMED JALALUDDIN LECTURER CONSTRUCTION
ENGINEERING MANAGEMENT DEPT Handout 3
2
Presentation Outline
  • Construction Management Process
  • Definition of Project
  • Definition of Construction Management
  • Basic Construction Management Philosophy
  • Construction Management Levels
  • Iterative process
  • Time-Cost relationship
  • Production curves
  • Why Use Project Management ?
  • Without Project Management
  • With Project Management
  • Major categories of Construction projects
  • Residential
  • Building
  • Infrastructure and heavy construction
  • Industrial

3
Objectives of Class
  • To define Project , Construction Management and
    understand the different Construction Management
    Levels
  • To understand the Construction Management
    Process, philosophy, goals.
  • To define the four major categories of
    construction projects

4
WHAT IS A PROJECT?
  • A project is an interrelated set of activities
  • Temporary undertaking that results in a unique
    product
  • Has set start and finish
  • Requires resources to complete
  • A time frame for completion
  • Sequenced events
  • The involvement of a cross-functional group of
    people
  • Limited resources and budget

5
Some Examples
  • Constructing a building / dam / pipeline / road
  • Redesigning the layout of a plant or office
  • Relocation of a major facility such as a plant,
    hospital, or airport
  • Organizing the Olympic games
  • Planning a party or wedding

6
Definition of Successful Project Management
  • Within time
  • Within budget
  • At the desired performance / specification level
  • While utilizing assigned resources effectively
  • and efficiently.

7
(No Transcript)
8
Construction Management Definition
The planning ,coordination and control of a
project from conception to completion on behalf
of a client requiring the identification of
client objectives in terms of quality , time
,cost and the establishment of relationship
between resources, integrating monitoring and
controlling the contributors to the project
The figure illustrates graphically the definition
of Construction Management system
9
Construction Management Levels
Four levels Organizational Level Legal
business structure, various areas of
management, and communication with field
managers Project Level Project activities,
project cost, and resource scheduling
Operation Level Construction technology (How
construction will be performed) Task
Activity breakdown (Task assignment to work crews)
10
Construction Management Levels
11
(No Transcript)
12
Construction Team Goals
13
Construction Management Philosophy
  • Basic Construction Management Philosophy
  • PLAN ,COORDINATE/ORGANIZE AND CONTROL
  • Also called Golden Rules of Construction
    Management

14
Time-Cost Relationship
  • Project costs start slowly, but increase sharply
    once the project enters the construction phase
  • Ability to influence decisions falls off sharply
    as time on the project passes

Influence/ Project cost
TIME
15
Production Curve (s-curve)
  • Projects build up slowly as workers and
    equipment are brought to the project and
    mobilized.
  • Early on only a few activities may occur, but
    once mobilization is complete work proceeds at a
    rapid pace until the end.

TIME
16
  • WHY USE PROJECT MANAGEMENT ?
  • WITHOUT PROJECT MANAGEMENT
  • WITH PROJECT MANAGEMENT ?

17
WITHOUT PROJECT MANAGEMENT
  • Resources - Ineffectively utilized
  • - Not committed
  • - Continuous reassignment
  • Priorities - Unrecognized
  • - Increasing backlog
  • Planning Execution - Risks not assessed
  • -- Uncontrolled change
  • Timing Cost - Missed completion dates
  • - Over expended budgets

18
USING PROJECT MANAGEMENT
  • RESOURCES
  • Types and quantities required
  • When and how long they will be needed
  • Obtain commitments for their use
  • Provides advanced planning for resource /
    facility availability
  • Facilitate conflicts resolution regarding pooled
    resources

19
AVAILABLE RESOURCES TO PERFORM WORK
20
OVER STAFFING RESOURCES FOR CONTAINABILITY
21
LEVELED RESOURCES BASED ON SCHEDULE
22
Three Phases of Project Management
  • PROJECT FORMULATION
  • Project Decomposition(WBS, Action Plan)
  • Specification of Precedence Relationships
  • Estimation of Activity Durations,Costs, Resource
    Requirements
  • Network Construction
  • PLANNING AND SCHEDULING
  • Computation of Each Activity's EST and EFT
  • Computation of Each Activity's LST and LFT
  • Computation of Slacks and Identification of the
    CP
  • Scheduling of Activities

23
List of Activities
  • Description
  • Building excavation area A
  • Foundation area A
  • Foundation walls area A
  • Building excavation area B
  • Foundation area B
  • Foundation walls area B
  • Backfill interior of walls
  • Waterproof exterior walls
  • Backfill exterior of walls
  • Start mechanical/plumbing
  • Slab rough in

Duration 10 9 8 8 7 8 5 1 2 4 3
24
PRIORITIES
Critical Path Schedule with Logic
25
PRIORITIES
Project Schedule with Resources and Baseline
26
USING PROJECT MANAGEMENT
  • PLANNING EXECUTION
  • Provides a means to accommodate feedback
  • Priorities and responsibilities are understood
  • Risks are assessed and mitigation occurs
  • Communicate work plans for first line supervision

27
USING PROJECT MANAGEMENT
  • DEVELOPMENT OF CASH FLOW
  • Estimate durations of activities
  • Estimate cost of activities
  • Crew size performing work scope
  • Crew, wages, Installation of Equipment

28
Typical Cash Flow Diagram

Time
29
USING PROJECT MANAGEMENT
  • TIMING COST
  • Updated projected completion dates and budgets
  • Perform to meet delivery schedules
  • Manage and control change
  • Avoid penalties
  • Project completed as planned

30
PLAN/TARGET/BASELINE
Thousands
PLANNED
C 20,000
C 20,000
C 20,000
C 20,000
C 10,000
C 10,000
B
C
D
E
F
A
20
20
20
20
20
20
31
SCHEDULE VARIANCE
Thousands
ProgressDate
PLANNED
PROJECTED EARNED
ProjectedSlippage
ScheduleVariance
EARNED
C 20,000
C 10,000
C 20,000
C 20,000
C 20,000
C 10,000
B
A
C
D
E
F
20
40
20
20
20
20
32
COST/SCHEDULE VARIANCE
33
Three Phases of Project Management-Continued
  • MONITORING AND REPLANNING
  • Monitoring of the Projects Activities
  • Replanning of the Remaining Portion of the
    Project
  • Is the revised estimate of projects shortest
    completion time acceptable ?
  • Is there a need to allocate additional resources
    or shift resources from non-critical activities ?
  • Monitoring and Controlling of Project costs.
    Budgeted vs. Actual Costs

34
CONCLUSION
  • Using Project Management allows the project team
    to
  • identify potential problems before they occur
  • plan for their solutions
  • Resulting in
  • Better planned and managed projects
  • Finishing on time within budget
  • Performing to acceptable quality standards

35
Categories of Construction Projects
  • Residential
  • Building construction.
  • Infrastructure and heavy construction
  • Industrial
  • Major differences exist
  • In the way the projects are funded,
  • In the technologies involved,
  • And in the manner in which the designers,
    builders, and owners interact.

36
Categories of Construction Projects
37
Residential Construction
  • Residential construction projects include the
    construction of individual homes as well as small
    condominium and apartment building complexes.
  • Privately funded by individual owners for their
    own use or by developers for profit.
  • This industry tends towards the use of fairly
    low technologies and requires little investment
    to enter.
  • Such projects are typically designed by
    architects, but in some cases a single home may
    be designed by the individual home owner or
    builder.
  • The industry is characterized by large numbers
    of small designers and builders and suppliers

38
Residential Construction
39
Building construction
  • Examples of building construction projects
    include office buildings, large apartment
    buildings, shopping malls.
  • Projects such as these are designed by
    architects with engineering support and are
    generally built by general contractors.
  • Most of these projects are privately funded,
    though some projects like schools, and city
    offices are publicly funded.
  • The technical sophistication of building
    construction projects is greater than residential
    construction as is the investment necessary to
    enter.
  • These factors provide for fewer players than in
    residential construction

40
Building construction
41
Infrastructure and heavy construction
  • Some examples of infrastructure and heavy
    construction are roadways, bridges, dams, and
    tunnels.
  • Designed principally by civil engineers and
    built by heavy construction contractors having
    engineering backgrounds or support.
  • These projects are usually publicly funded
  • Long in duration and they involve the heavy use
    of equipment

42
Infrastructure and heavy construction
43
Infrastructure and heavy construction
44
Industrial Construction
  • Steel mills, petroleum refineries, chemical
    processing plants, and automobile production
    facilities all serve as examples of industrial
    facilities.
  • These projects are defined more by the production
    activities within the facility than by the
    facility itself.
  • The design and construction is dependent on the
    needs of the process and production equipment.

45
Industrial Construction
46
CONCLUSION
  • Using Project Management allows the project team
    to
  • identify potential problems before they occur
  • plan for their solutions
  • Resulting in
  • Better planned and managed projects
  • Finishing on time within budget
  • Performing to acceptable quality standards
  • Categories of Construction Projects Residential,
    Building construction, Infrastructure and heavy
    construction, Industrial

47
Questions
Write a Comment
User Comments (0)
About PowerShow.com