Title: BUILD OPERATE TRANSFER
1CONSTRUCTION MANAGEMENT
ARE 413 CONSTRUCTION MANAGEMENT CLASS -2 By
MOHAMMED JALALUDDIN LECTURER CONSTRUCTION
ENGINEERING MANAGEMENT DEPT Handout 3
2Presentation Outline
- Construction Management Process
- Definition of Project
- Definition of Construction Management
- Basic Construction Management Philosophy
- Construction Management Levels
- Iterative process
- Time-Cost relationship
- Production curves
- Why Use Project Management ?
- Without Project Management
- With Project Management
- Major categories of Construction projects
- Residential
- Building
- Infrastructure and heavy construction
- Industrial
3Objectives of Class
- To define Project , Construction Management and
understand the different Construction Management
Levels - To understand the Construction Management
Process, philosophy, goals. - To define the four major categories of
construction projects -
4WHAT IS A PROJECT?
- A project is an interrelated set of activities
- Temporary undertaking that results in a unique
product - Has set start and finish
- Requires resources to complete
- A time frame for completion
- Sequenced events
- The involvement of a cross-functional group of
people - Limited resources and budget
5Some Examples
- Constructing a building / dam / pipeline / road
- Redesigning the layout of a plant or office
- Relocation of a major facility such as a plant,
hospital, or airport - Organizing the Olympic games
- Planning a party or wedding
6Definition of Successful Project Management
- Within time
- Within budget
- At the desired performance / specification level
- While utilizing assigned resources effectively
- and efficiently.
7(No Transcript)
8Construction Management Definition
The planning ,coordination and control of a
project from conception to completion on behalf
of a client requiring the identification of
client objectives in terms of quality , time
,cost and the establishment of relationship
between resources, integrating monitoring and
controlling the contributors to the project
The figure illustrates graphically the definition
of Construction Management system
9Construction Management Levels
Four levels Organizational Level Legal
business structure, various areas of
management, and communication with field
managers Project Level Project activities,
project cost, and resource scheduling
Operation Level Construction technology (How
construction will be performed) Task
Activity breakdown (Task assignment to work crews)
10Construction Management Levels
11(No Transcript)
12Construction Team Goals
13Construction Management Philosophy
- Basic Construction Management Philosophy
- PLAN ,COORDINATE/ORGANIZE AND CONTROL
- Also called Golden Rules of Construction
Management
14 Time-Cost Relationship
- Project costs start slowly, but increase sharply
once the project enters the construction phase - Ability to influence decisions falls off sharply
as time on the project passes
Influence/ Project cost
TIME
15 Production Curve (s-curve)
- Projects build up slowly as workers and
equipment are brought to the project and
mobilized. - Early on only a few activities may occur, but
once mobilization is complete work proceeds at a
rapid pace until the end.
TIME
16- WHY USE PROJECT MANAGEMENT ?
- WITHOUT PROJECT MANAGEMENT
- WITH PROJECT MANAGEMENT ?
17WITHOUT PROJECT MANAGEMENT
- Resources - Ineffectively utilized
- - Not committed
- - Continuous reassignment
- Priorities - Unrecognized
- - Increasing backlog
- Planning Execution - Risks not assessed
- -- Uncontrolled change
- Timing Cost - Missed completion dates
- - Over expended budgets
-
18USING PROJECT MANAGEMENT
- RESOURCES
- Types and quantities required
- When and how long they will be needed
- Obtain commitments for their use
- Provides advanced planning for resource /
facility availability - Facilitate conflicts resolution regarding pooled
resources
19AVAILABLE RESOURCES TO PERFORM WORK
20OVER STAFFING RESOURCES FOR CONTAINABILITY
21LEVELED RESOURCES BASED ON SCHEDULE
22Three Phases of Project Management
- PROJECT FORMULATION
- Project Decomposition(WBS, Action Plan)
- Specification of Precedence Relationships
- Estimation of Activity Durations,Costs, Resource
Requirements - Network Construction
- PLANNING AND SCHEDULING
- Computation of Each Activity's EST and EFT
- Computation of Each Activity's LST and LFT
- Computation of Slacks and Identification of the
CP - Scheduling of Activities
23List of Activities
- Description
- Building excavation area A
- Foundation area A
- Foundation walls area A
- Building excavation area B
- Foundation area B
- Foundation walls area B
- Backfill interior of walls
- Waterproof exterior walls
- Backfill exterior of walls
- Start mechanical/plumbing
- Slab rough in
Duration 10 9 8 8 7 8 5 1 2 4 3
24PRIORITIES
Critical Path Schedule with Logic
25PRIORITIES
Project Schedule with Resources and Baseline
26USING PROJECT MANAGEMENT
- PLANNING EXECUTION
- Provides a means to accommodate feedback
- Priorities and responsibilities are understood
- Risks are assessed and mitigation occurs
- Communicate work plans for first line supervision
27USING PROJECT MANAGEMENT
- DEVELOPMENT OF CASH FLOW
- Estimate durations of activities
- Estimate cost of activities
- Crew size performing work scope
- Crew, wages, Installation of Equipment
28Typical Cash Flow Diagram
Time
29USING PROJECT MANAGEMENT
- TIMING COST
- Updated projected completion dates and budgets
- Perform to meet delivery schedules
- Manage and control change
- Avoid penalties
- Project completed as planned
30PLAN/TARGET/BASELINE
Thousands
PLANNED
C 20,000
C 20,000
C 20,000
C 20,000
C 10,000
C 10,000
B
C
D
E
F
A
20
20
20
20
20
20
31SCHEDULE VARIANCE
Thousands
ProgressDate
PLANNED
PROJECTED EARNED
ProjectedSlippage
ScheduleVariance
EARNED
C 20,000
C 10,000
C 20,000
C 20,000
C 20,000
C 10,000
B
A
C
D
E
F
20
40
20
20
20
20
32COST/SCHEDULE VARIANCE
33Three Phases of Project Management-Continued
- MONITORING AND REPLANNING
- Monitoring of the Projects Activities
- Replanning of the Remaining Portion of the
Project - Is the revised estimate of projects shortest
completion time acceptable ? - Is there a need to allocate additional resources
or shift resources from non-critical activities ?
- Monitoring and Controlling of Project costs.
Budgeted vs. Actual Costs
34CONCLUSION
- Using Project Management allows the project team
to - identify potential problems before they occur
- plan for their solutions
- Resulting in
- Better planned and managed projects
- Finishing on time within budget
- Performing to acceptable quality standards
35Categories of Construction Projects
-
- Residential
- Building construction.
- Infrastructure and heavy construction
- Industrial
- Major differences exist
- In the way the projects are funded,
- In the technologies involved,
- And in the manner in which the designers,
builders, and owners interact.
36Categories of Construction Projects
37 Residential Construction
-
- Residential construction projects include the
construction of individual homes as well as small
condominium and apartment building complexes. - Privately funded by individual owners for their
own use or by developers for profit. - This industry tends towards the use of fairly
low technologies and requires little investment
to enter. - Such projects are typically designed by
architects, but in some cases a single home may
be designed by the individual home owner or
builder. - The industry is characterized by large numbers
of small designers and builders and suppliers
38 Residential Construction
39 Building construction
- Examples of building construction projects
include office buildings, large apartment
buildings, shopping malls. - Projects such as these are designed by
architects with engineering support and are
generally built by general contractors. - Most of these projects are privately funded,
though some projects like schools, and city
offices are publicly funded. - The technical sophistication of building
construction projects is greater than residential
construction as is the investment necessary to
enter. - These factors provide for fewer players than in
residential construction
40 Building construction
41 Infrastructure and heavy construction
- Some examples of infrastructure and heavy
construction are roadways, bridges, dams, and
tunnels. - Designed principally by civil engineers and
built by heavy construction contractors having
engineering backgrounds or support. - These projects are usually publicly funded
- Long in duration and they involve the heavy use
of equipment
42 Infrastructure and heavy construction
43 Infrastructure and heavy construction
44Industrial Construction
- Steel mills, petroleum refineries, chemical
processing plants, and automobile production
facilities all serve as examples of industrial
facilities. - These projects are defined more by the production
activities within the facility than by the
facility itself. - The design and construction is dependent on the
needs of the process and production equipment.
45Industrial Construction
46CONCLUSION
- Using Project Management allows the project team
to - identify potential problems before they occur
- plan for their solutions
- Resulting in
- Better planned and managed projects
- Finishing on time within budget
- Performing to acceptable quality standards
- Categories of Construction Projects Residential,
Building construction, Infrastructure and heavy
construction, Industrial -
47Questions