Title: Presenta.IndeNov.01
1(No Transcript)
2Licensing Assistance and Design Certification
3Licensing Assistance The Daya Bay- Ling Ao
Example
4Daya Bay NPP
2 Reactors (985 MWe)
- First high power reactor in China
- Design benefiting from improvements derived from
return on experience from similar reactors in
France and export
5General Tasks of the NI Supplier in Assistance
Licensing to the Operator
- Provide all the data and informations during the
redaction of the safety documents for each of the
three steps preliminary , provisional, final - Provide all information necessary to answer the
questions raised by the safety authorities during
the evaluation realised by the safety authorities
on the safety analysis report
6The Safety Analysis Report
- The Safety Analysis Report describes and
justifies to the Safety Authority the provisions
adopted at each stage in the life of the
installation (design, construction,
commissioning, operation and decommissioning) to
comply with the regulations and guarantee nuclear
safety
- Provides information enabling verification
- That all risks (whether of nuclear origin or not)
and all possible events (of internal and external
origin) have been properly taken into
consideration - That the event of an accident, protection of the
staff, the population and environment is properly
assured by adequate means in place
- The nuclear operator is responsible for the
safety analysis report and associated licensing - The designer supports the operator
7SAR - Typical Sharing of Responsibilities
8Daya Bays Reference Plant Gravelines 5
9Summary of the Main Approval Steps
- Preliminary Safety Report
- Construction Permit
- Provisional Safety Report
- Fuel Loading Authorization
- Final Safety Report
- Authorization of Commercial Operation
10Positioning of the Main Approval Steps
11Daya Bay Licensing Previous Steps
- CREATION OF THE CHINESE NUCLEAR SAFETY NATIONAL
ADMINISTRATION OCT, 1984 - GENERAL COOPERATION AGREEMENT WITH DSN AND IPSN
DEC, 1984 - TRANSFER OF CODES
- CATHARE
- ESCADRE
- ICARE
- TRAINING BY IPSN TO SAFETY EVALUATION METHODS
- (60 trainees)
12Daya Bay Licensing Main Steps
- SPECIFIC AGREEMENT WITH IPSN FOR DAYA BAY SAFETY
EVALUATION APRIL 1986 - PSAR EVALUATION 1987
- DESIGN DOCUMENTS EVALUATION 1988-1990
- FSAR EVALUATION 1991
- EVALUATION OF COMMISSIONING TESTS PROGRAMS AND
RESULTS 1990-1992
Along this process, Framatome ANP addressed more
than 3000 questions
13Daya Bay Operation the Operators Quick Learning
- Operation started in 1994
- Excellent availability
- In 2000, Daya Bay was above global average for
seven out of ten WANO factors
Availability factorlearning curve
14Ling Ao NPP
2 Reactors (990 MWe)
- Improvements compared to Daya Bay
15Ling Ao Licensing Main Steps
- GENERAL COOPERATION AGREEMENT WITH DSIN
- NOV.
1995 - GENERAL COOPERATION AGREEMENT WITH IPSN
- DEC.
1995 - LING AO LICENSING BY THE CHINESE SAFETY
ADMINISTRATION - SUPPORT PROVIDED THROUGH THE TWO AGREEMENTS
16Suppliers Tasks for Ling Ao
- Similar to Daya Bay
- Identical Responsibilities for PSAR/FSAR Chapters
Along this process, Framatome ANP addressed less
than 300 questions
17Suppliers Tasks for Backfittings
The NPP Supplier Assists the Operator in his
Relationship with the Safety Authorities during
the Whole Lifetime of the NPP
- When additional justifications are required
- When technical modifications on the installation
influence the safety analysis report - When evolutions on the management methods or the
fuel types influence the safety analysis report
18Framatome ANP Engineering Services Plant
Performance Improvement
- Plant nominal power uprating
- Improved fuel management
- Improved plant manoeuvrability
- Improved plant availability
- Contribution to outage duration reduction
19Improved fuel management 18-month cycle Daya Bay
- 1998 GNPJVC decides on a new strategy for fuel
cycle management - 18-month cycle
- 52 gwj/TU burnup
- Enrichment 4,45
- Contract to Framatome-ANP in 1998
20Improved fuel management 18-month cycle Daya Bay
- Transfer of tools and methods to institutes NPIC
and BINE - Technology Transfer for fuel fabrication AFA 3G
to Yibin - Assistance for AFA 3G licensing by NNSA
- Assistance for 18-month fuel cycle licensing by
NNSA - 2002 implementation of the 18-month fuel cycle
for Daya Bay both Reactors
21 Design CertificationExample of The U.S. EPR
22EPR Plot Plan
Safeguard Building 23 MCR
23- AREVAs goal is to deploy EPR plants in the US
- AREVA has therefore decided to apply for design
certification - EPR design is evolutionary so the design
certification reviewis expected to be
straightforward - Design Certification Document submittal end 2007
- Several US utilities have expressed strong
interestand consider the EPR as a viable option
for future needs.
24(No Transcript)
25Status of U.S. EPR Licensing Activities
- Design Certification (DC)
- In Phase 2 of NRC pre-application review for
design certification - Continued series of technical exchange meetings
- Submittal of topical reports for review
- Design Certification application to be submitted
in December 2007
- Combined License (COL)
- UniStar Nuclear plans to submit at least four COL
applications referencing the U.S. EPR - First UniStar Nuclear COL application to be
submitted no later than June 2008
Licensing preparations on schedule to support
U.S. EPR deployment in 2015.
26NRC Meetings and Submittals
- Meetings with NRC for 2006
- 14 meetings originally planned
- 14 meetings completed
- 2 more meetings planned
- Pre-application submittals
- 21 submittals planned
- 5 reports submitted (on or ahead of schedule)
- 7 more reports to be submitted in 2006
27EPR Design Certification Time schedule
28(No Transcript)