Website: - PowerPoint PPT Presentation

About This Presentation
Title:

Website:

Description:

Resource Parity Assures Least Cost. Principles apply throughout power system ... Resource parity: Energy efficiency, load management, demand-side bidding, and ... – PowerPoint PPT presentation

Number of Views:44
Avg rating:3.0/5.0
Slides: 24
Provided by: RichS6
Category:
Tags: parity | website

less

Transcript and Presenter's Notes

Title: Website:


1
Power SystemPlanning and Investment
  • Richard Sedano and Richard Cowart
  • NEDRI
  • March 26, 2003

2
Demand Side Solutions Have Value
  • But there are barriers
  • Solving Structural Barriers to Demand Response
  • Involves addressing planning and investment
    practices
  • Also removes some barriers affecting energy
    efficiency and distributed generation

3
Priorities and Realities
  • Electric Market is Regional
  • Public Policy Involved, Just a Matter of When
  • Potential to improve investment decisions or slow
    them down
  • Resource Parity Assures Least Cost
  • Principles apply throughout power system

4
Objectives
  • Market oriented decisions with competitive forces
    at work
  • Cost causation has merit
  • Socialization granted only after passing a test
  • Cost recover mechanisms comparable for all
    resource solutions

5
Demand Resources in Grid Planning and Investment
  • Demand resources have a role in three areas
  • Regional System Planning
  • Regional Grid Investment Policy
  • Distribution Utility Planning

6
(A) Symptoms of Regional Electric Market Problems
  • Lack of timely transmission line proposals
  • Generation construction that causes congestion
  • Lack of connection between electricity investment
    decisions and environmental implications
  • Lack of consideration of customer resources to
    solve grid problems
  • Lack of co-ordination of investment plans by
    monopoly and competitive companies

7
System Planning Recommendations
  • Regional cooperation by states
  • Continuing regional planning process
  • Driven by system needs
  • All solutions available

8
Multi-StateCoordination
  • Recommendation 1 Increase coordination among the
    states and between states and the ISO
  • Efficiency to regulatory decision-making
  • Certainty to the marketplace
  • Guide ISO toward more efficient planning
  • Avoid duplication of effort
  • Support authority, independence of states

How far will States Go?
9
Regional Power System Planning Process
  • Recommendation 2 Conduct a continuing regional
    power system planning process to identify system
    needs and alternative strategies to meet them.
  • Cyclical
  • Transparent
  • System needs treated over time
  • Maximum planning horizon
  • Maintain responsiveness to emergent conditions
  • Improve public confidence

10
Regional Power System Planning Process
  • Formal Role for State Governments if states want
    it
  • Focus on areas of interest
  • Involve more stakeholders
  • Attract all solutions

11
ComprehensiveSolution Set
  • Recommendation 3 The outcome of a regional power
    system planning process should be an evaluation
    on an even-handed basis of a wide range of
    feasible solutions to emerging problems,
    including investments in generation,
    transmission, and demand-side options.
  • Regardless of the planning process, all
    reasonable solutions should be considered and
    evaluated similarly
  • Candidate solutions come from competitive and
    regulated entities
  • State regulation would have to support solutions
    coming from regulated entities
  • Implementing a solution affects the economics of
    the others

12
System Investment Recommendations
  • Market oriented investments preferred
  • State authority remains
  • Cost causation is appropriate
  • Socialization is appropriate for some
    reliability-oriented investments
  • Efficient Reliability Standard should apply
  • Resource parity
  • Least cost standard
  • Cost recovery comparability

13
(B) Grid Investment Policies
  • Recommendation 4 Leave investment and siting
    decisions in the hands of market participants and
    state regulators wherever possible, assigning
    cost responsibility to those who create the need
    for system upgrades, and those who benefit from
    them.
  • After grid problems and potential solutions are
    identified in the system planning process, these
    results should be posted publicly so that market
    participants can consider what actions they might
    take within the existing market structure to meet
    emerging needs. Wherever possible, RSAC should
    permit market-based and state-based responses to
    emerge.
  • Public, regional intervention to promote or pay
    for grid solutions should be taken only where it
    is evident that adequate resolution is not
    forthcoming in the market, or that the investment
    in question is one that, as a matter of equity,
    ought to be undertaken by grid managers with cost
    recovery imposed through tariffs.

14
(5) Efficient Reliability Test
  • Recommendation 5
  • ISO-New England, NEPOOL, and FERC should apply an
    Efficient Reliability test, based on principles
    of least-cost analysis and resource parity, when
    considering proposals to socialize the costs of
    system improvements through wholesale rules and
    transmission tariffs.

15
(5a)Two principles
  • Resource parity Energy efficiency, load
    management, demand-side bidding, and distributed
    resources in addition to traditional generation
    and transmission resources -- are all potentially
    cost-effective means of meeting reliability needs
    identified by system operators and power pool
    managers. NEDRI recommends that when socialized
    cost recovery is sought, that demand-side
    resources be treated comparably to supply-side
    and wires options both in analysis and in access
    to funding.
  • Least-cost standard A principal criterion for
    selecting a solution that is qualified to receive
    socialized support should be whether it is the
    lowest-cost, reasonably available solution to an
    unmet system need, considered on a total cost
    basis.

16
(5b) Screening proposals to socialize grid costs
  • NEDRI recommends that NEPOOL, ISO-New England,
    and FERC adopt the following standard as a means
    of screening proposals to socialize grid
    enhancements
  • Before socializing the costs of a proposed
    reliability-enhancing investment through tariff,
    uplift, or other cost-sharing requirement, ISO-NE
    (and FERC) should require the applicant to
    demonstrate
  • (1) That the relevant market is fully open to
    demand-side as well as supply-side resources
  • (2) That the proposed investment is the lowest
    cost, reasonably-available means to correct a
    remaining market failure and
  • (3) That benefits from the investment will be
    widespread, and thus appropriate for support
    through broad-based funding.

17
(6) Comparable cost recovery opportunities
  • Recommendation 6 Ensure comparable cost recovery
    opportunities for transmission and
    non-transmission resource solutions
  • Whether a grid problem is resolved through a
    transmission or non-transmission solution, or a
    combination of them, the solution should qualify
    for cost recovery through transmission tariffs or
    wholesale uplift charges on the same basis.

18
(C) Distribution System Planning and Demand
Resources
  • Recommendation 7 Distribution companies can and
    should apply recommendations 1-6
  • Distribution needs distinct from regional system
    needs
  • Many circuits, shorter horizons
  • Practices focus on traditional solutions
  • Demand opportunities significant
  • All resource planning focus requires a new
    perspective

19
Distribution needs distinct from regional system
needs
  • Localized
  • Distinct performance of individual circuits
  • Timing driven by specific events or customers
  • Shorter time horizons

20
Redefinition of Distribution Planning
  • Focus on wire solutions to address growth-related
    challenges
  • Challenge to distribution planners
  • A distinct source of value from customer
    resources avoided distribution costs
  • Construction
  • Losses, voltage support
  • Full menu of customer resources

21
Distributed Utility Planning
  • Focus on circuits
  • Factor in cost of incremental customer resources
    (societal test)
  • Regulatory Policy matters
  • Expect DUP to consider customer resources
  • Pricing
  • Break link between net income and sales
  • Staffing
  • Pilot

22
Possible Roles of the Multi-State Entity
  • Transmission Siting Advice
  • Regional Resource Adequacy
  • Congestion Monitoring
  • Market Power Monitoring
  • Gas Supply Co-ordination
  • Environmental Issue Integration
  • Technical Potential Assessments
  • Innovative Solutions Advice
  • Public Benefits Co-ordination

23
RTEP Process Flow with observations
Need longer horizon
Opportunity to engage more rings of interested
people
Meetings throughout region are good
Public Policy input is inconsistent, not reliable
Unequal treatment for cost recovery among
resources is too large a barrier to get best
choices
Non-transmission alternatives not permitted to
compete (planning, cost recovery) here unclear
how any distributed resource options are
considered
Declaration of appropriate projects lacks weight
Queueing remains a problem
No effect on state decision-making on pricing,
metering, siting, distributed resources
Write a Comment
User Comments (0)
About PowerShow.com