Title: Transmission Issues With the Integration of Large Scale Renewable Energy Projects
1Transmission Issues With the Integration of
Large ScaleRenewable Energy Projects
- Geothermal Resources Council
- John Pease PE, MBA
- Project Manager, Renewable Energy
- Bonneville Power Administration
- Monday September 11, 2006
2(No Transcript)
3(No Transcript)
4BPA Today Facilitator Role to Develop New
Renewables
- History 2001 BPA increases wholesale price of
power due to additional load placed on the Agency
then Direct Service industries go out of
business - BPA at load/resource balance
- Some customers want BPA out of resource
acquisition the Regional Dialogue - BPA helps its customers who want to develop their
own renewable resources today
5Activities in Support of Geothermal Development
- From 1988-94, BPA spent over 1,000,000 on
activities promoting geothermal - Economic impact studies in 5 counties
- Hydrologic studies at 4 KGRAs
- Impact analysis at 3 sites
- Resource assessment in Cascades and SE Oregon
- Environmental baseline at Newberry
- Permitting guides
- Geothermal teaching materials (see handout)
- Outreach to public interest community
6Challenges
- No RPS in the Pacific NW geothermal must
compete on its own economic merits - Conservative utility response Why it wont
work. Perception can change with education - Transmission constraints solutions exist
7Risk Mitigation Someone elses Problem?
- Developers face a multitude of risks (ORMAT,
4/2005) - Exploration
- Resource capacity
- Regulatory
- Drilling
- Plant construction
- Financing
- Risk eventually shows up in the PPA power price
- Potentially jeopardizing project development
- Partnership lowers the cost for everyone.
-
8The Good News!
- Least Cost Marginal Power for base load resources
in the Pacific NW - 50 MWh and not going away - Risk Adjusted Avoided Cost methodology or How
would you value a CCCT today? - Energy, capacity credit, green tags, fuel risk,
environmental and societal cost/benefits compared
to natural gas - Geothermal can now compete w/o PTC though PTC
will help those who can use it (IOUs, IPPs,
etc.) - Idaho Power IRP (2004) Geothermal 3rd out of 15
alternatives for additional power (55/MWh
levelized) ahead of gas coal
9BPA Transmission
- BPA Transmission 75 of high voltage in the
Pacific NW - BPA building 770 miles of 500 kV circuits
Largest transmission building program in North
America - Yet, transmission system is over subscribed and
underutilized. What does this mean? - Song You cant get there from here Lee Roy
Parnel 1978 Country Classic
10(No Transcript)
11BPA (FERC) Generation Interconnection Process
(gt20 MW)
- Interconnection initiated by
- Letter requesting generating interconnection to
BPA transmission (TBL) see TBL website - Completed Interconnection Study Request
- Identify service requested Network or Energy
- Refundable deposit of 10k
- Once complete, generator is now in the Queue
- Details at http//www.transmission.bpa.gov/busin
ess/ generation_interconnection/
12Once Interconnection Request Completed, Other
Studies Follow
- Interconnection generator now responsible for
- Interconnection Feasibility Study - 10k deposit
- Interconnection System Impact Study - 50k
deposit - Interconnection Facilities Study - 100k deposit
- Standard Large Generator Agreement (gt20 MW) is
signed if transmission is available - Process is now taking 2 Years
13Interconnection Request - Continued
- Studies may indicate Interconnecting generator
may be blocked by someone higher in the Queue
who needs, but does not have, transmission
capacity - Consequently, upgrades then paid by pro rata need
for the transmission, if the generators agree to - Paid back by transmission credits after
construction approximately five years - Unfortunately, this process has never worked in
eight years since FERC Order 888 889 created
Open Access Transmission Tariff system (OATT)
14Interconnection Request - Continued
- When in the queue, transmission provider may
offer part of a firm transmission request - If not accepted, the transmission is offered to
next in line in the queue - May accepted partial firm transmission, then
fulfill plant needs by buying non-firm until firm
is available maintain position - If rejected, may go to the bottom of the queue
- May be able to alleviate transmission through
redirects - What is your (bankers) risk tolerance?
15Conditional Firm New (at least a little) Hope
On the Horizon
- Access to transmission determined by Firm and
non-Firm rights - Firm transmission guaranteed on all hours
most expensive, curtailed last (usually in an
emergency) - Non-Firm firm rights not used or unallocated
transmission made available daily, weekly,
monthly or annually (higher chance of curtailment
daily goes first, then weekly, monthly etc.) - Conditional firm Firm except in months when
curtailment may occur, then non-Firm, but
curtailed last (non-firm curtailment order)
16Conditional Firm A Little Hope - continued
- Presented by BPA to FERC March 16th, 2005 in
Portland - Conditional firm holder knows maximum curtailment
exposure 100s hours/month - If not told in preschedule (24 hour notice) that
a curtailment may occur, then considered firm - Uses additional Available Transmission Capacity
(ATC) that currently goes unused - Bounds transmission availability risk to enable
project financing! - Details at http//www.transmission.bpa.gov/Busin
ess/Customer_Forums_and_Feedback/Business_Practice
s_Technical_Forum/documents/Cond_Firm_Update_BPF_X
.pdf
17Economic Redispatch A Little More Hope
- Presented by BPA to FERC March 16th, 2005 in
Portland - Transmission provider will adjust generation
within the hour (TBL hydro) to alleviate a
transmission curtailment, increasing available
ATC - Pay for net costs of generation (or loads) who
may reduce generation to alleviate constraint - Generators may participate if an economic
incentive is provided - Details at www.transmission.bpa.gov/business/
CongestionManagement/documents/Within-Hour_Reliabi
lity_Redispatch.pps
18Was Lee Roy Parnel Right?
- What might be a No! from a transmission
provider might not be true - Alternatives may exist
- Asking the right questions might help you
- BPA account executives will help you get your
energy to load
19Questions and Comments?