Transmission Issues With the Integration of Large Scale Renewable Energy Projects PowerPoint PPT Presentation

presentation player overlay
1 / 19
About This Presentation
Transcript and Presenter's Notes

Title: Transmission Issues With the Integration of Large Scale Renewable Energy Projects


1
Transmission Issues With the Integration of
Large ScaleRenewable Energy Projects
  • Geothermal Resources Council
  • John Pease PE, MBA
  • Project Manager, Renewable Energy
  • Bonneville Power Administration
  • Monday September 11, 2006

2
(No Transcript)
3
(No Transcript)
4
BPA Today Facilitator Role to Develop New
Renewables
  • History 2001 BPA increases wholesale price of
    power due to additional load placed on the Agency
    then Direct Service industries go out of
    business
  • BPA at load/resource balance
  • Some customers want BPA out of resource
    acquisition the Regional Dialogue
  • BPA helps its customers who want to develop their
    own renewable resources today

5
Activities in Support of Geothermal Development
  • From 1988-94, BPA spent over 1,000,000 on
    activities promoting geothermal
  • Economic impact studies in 5 counties
  • Hydrologic studies at 4 KGRAs
  • Impact analysis at 3 sites
  • Resource assessment in Cascades and SE Oregon
  • Environmental baseline at Newberry
  • Permitting guides
  • Geothermal teaching materials (see handout)
  • Outreach to public interest community

6
Challenges
  • No RPS in the Pacific NW geothermal must
    compete on its own economic merits
  • Conservative utility response Why it wont
    work. Perception can change with education
  • Transmission constraints solutions exist

7
Risk Mitigation Someone elses Problem?
  • Developers face a multitude of risks (ORMAT,
    4/2005)
  • Exploration
  • Resource capacity
  • Regulatory
  • Drilling
  • Plant construction
  • Financing
  • Risk eventually shows up in the PPA power price
  • Potentially jeopardizing project development
  • Partnership lowers the cost for everyone.

8
The Good News!
  • Least Cost Marginal Power for base load resources
    in the Pacific NW - 50 MWh and not going away
  • Risk Adjusted Avoided Cost methodology or How
    would you value a CCCT today?
  • Energy, capacity credit, green tags, fuel risk,
    environmental and societal cost/benefits compared
    to natural gas
  • Geothermal can now compete w/o PTC though PTC
    will help those who can use it (IOUs, IPPs,
    etc.)
  • Idaho Power IRP (2004) Geothermal 3rd out of 15
    alternatives for additional power (55/MWh
    levelized) ahead of gas coal

9
BPA Transmission
  • BPA Transmission 75 of high voltage in the
    Pacific NW
  • BPA building 770 miles of 500 kV circuits
    Largest transmission building program in North
    America
  • Yet, transmission system is over subscribed and
    underutilized. What does this mean?
  • Song You cant get there from here Lee Roy
    Parnel 1978 Country Classic

10
(No Transcript)
11
BPA (FERC) Generation Interconnection Process
(gt20 MW)
  • Interconnection initiated by
  • Letter requesting generating interconnection to
    BPA transmission (TBL) see TBL website
  • Completed Interconnection Study Request
  • Identify service requested Network or Energy
  • Refundable deposit of 10k
  • Once complete, generator is now in the Queue
  • Details at http//www.transmission.bpa.gov/busin
    ess/ generation_interconnection/

12
Once Interconnection Request Completed, Other
Studies Follow
  • Interconnection generator now responsible for
  • Interconnection Feasibility Study - 10k deposit
  • Interconnection System Impact Study - 50k
    deposit
  • Interconnection Facilities Study - 100k deposit
  • Standard Large Generator Agreement (gt20 MW) is
    signed if transmission is available
  • Process is now taking 2 Years

13
Interconnection Request - Continued
  • Studies may indicate Interconnecting generator
    may be blocked by someone higher in the Queue
    who needs, but does not have, transmission
    capacity
  • Consequently, upgrades then paid by pro rata need
    for the transmission, if the generators agree to
  • Paid back by transmission credits after
    construction approximately five years
  • Unfortunately, this process has never worked in
    eight years since FERC Order 888 889 created
    Open Access Transmission Tariff system (OATT)

14
Interconnection Request - Continued
  • When in the queue, transmission provider may
    offer part of a firm transmission request
  • If not accepted, the transmission is offered to
    next in line in the queue
  • May accepted partial firm transmission, then
    fulfill plant needs by buying non-firm until firm
    is available maintain position
  • If rejected, may go to the bottom of the queue
  • May be able to alleviate transmission through
    redirects
  • What is your (bankers) risk tolerance?

15
Conditional Firm New (at least a little) Hope
On the Horizon
  • Access to transmission determined by Firm and
    non-Firm rights
  • Firm transmission guaranteed on all hours
    most expensive, curtailed last (usually in an
    emergency)
  • Non-Firm firm rights not used or unallocated
    transmission made available daily, weekly,
    monthly or annually (higher chance of curtailment
    daily goes first, then weekly, monthly etc.)
  • Conditional firm Firm except in months when
    curtailment may occur, then non-Firm, but
    curtailed last (non-firm curtailment order)

16
Conditional Firm A Little Hope - continued
  • Presented by BPA to FERC March 16th, 2005 in
    Portland
  • Conditional firm holder knows maximum curtailment
    exposure 100s hours/month
  • If not told in preschedule (24 hour notice) that
    a curtailment may occur, then considered firm
  • Uses additional Available Transmission Capacity
    (ATC) that currently goes unused
  • Bounds transmission availability risk to enable
    project financing!
  • Details at http//www.transmission.bpa.gov/Busin
    ess/Customer_Forums_and_Feedback/Business_Practice
    s_Technical_Forum/documents/Cond_Firm_Update_BPF_X
    .pdf

17
Economic Redispatch A Little More Hope
  • Presented by BPA to FERC March 16th, 2005 in
    Portland
  • Transmission provider will adjust generation
    within the hour (TBL hydro) to alleviate a
    transmission curtailment, increasing available
    ATC
  • Pay for net costs of generation (or loads) who
    may reduce generation to alleviate constraint
  • Generators may participate if an economic
    incentive is provided
  • Details at www.transmission.bpa.gov/business/
    CongestionManagement/documents/Within-Hour_Reliabi
    lity_Redispatch.pps

18
Was Lee Roy Parnel Right?
  • What might be a No! from a transmission
    provider might not be true
  • Alternatives may exist
  • Asking the right questions might help you
  • BPA account executives will help you get your
    energy to load

19
Questions and Comments?
Write a Comment
User Comments (0)
About PowerShow.com