Title: Hall X PED
1Hall X PED Construction
Sample TalkMinimum Required Vugraphs
John Doe
Project Directors Review Jefferson Lab May 9
11, 2005
Proj_mgmnt/presentation_misc/rode_misc/12gevprojdi
rrev
2Hall X Cost Distribution
Supplied by OPM
3Hall X Cost Methodology
- Costs are based on
- Quotes from vendors 0
- Catalog price 30 (ZZZ)
- Estimates from vendors 30 (XXX , YYY)
- previous procurements
- Information from other labs, 20 (AAA)
- Universities, etc.
- Engineering judgment 20 (BBB)
-
4 Hall X Overview
1 to 5 VG
5Hall X Level 4(3) TEC Elements
1.2.2.1 PED Construction 1.4.1.1 Magnet 1.4
.1.2 Detector 1.4.1.3 Computing 1.4.1.4 Fast
Electronics 1.4.1.5 Beam line 1.4.1.6 Infrastr
ucture
Supplied by OPM
6 WBS 1.4.1.1
Data By CAM, VG By OPM
7WBS 1.2.2.1 Hall X PED K
Contingency Labor Exp Proc 1.2.2.1
.1 Magnet 1.2.2.1.2 Detector 1.2.2.1
.3 Computing 1.2.2.1.4 Fast
Electronics 1.2.2.1.5 Beam
line 1.2.2.1.6 Infrastructure Total
base VG supplied by OPM
8WBS 1.4.1.1 Hall X Magnet
Drawing or Scope
9WBS 1.4.1.1 Hall X Magnet K
- Contingency
- Labor Exp Proc Reason
- 1.4.1.1.1 Dipoles ????
- 1.4.1.1.2 Quads ????
- 1.4.1.1.3 Cryogenics ????
- 1.4.1.1.4 Power Supplies ????
- 1.4.1.1.5 Support Structure
- Motion System ????
- 1.4.1.1.6 Controls ????
- Total
- Reason
- 1. Design Complete
- 2. Incomplete Design
base VG supplied by OPM
10WBS 1.4.1.2 Hall X Detector
Drawing or Scope
Continue for all level 4s
11 Hall X Conclusions
Why Should the Reviewers Believe You ?