PWL 18201 - PowerPoint PPT Presentation

1 / 17
About This Presentation
Title:

PWL 18201

Description:

LANSCE is a Unique Multidisciplinary Science Facility. Manual Lujan Jr. ... PHAROS: New wide-angle detector bank installed. New data acquisition electronics installed ... – PowerPoint PPT presentation

Number of Views:163
Avg rating:3.0/5.0
Slides: 18
Provided by: gartht
Category:
Tags: pwl | pharos

less

Transcript and Presenter's Notes

Title: PWL 18201


1
LANSCE Status and Progress Update
Presentation to Basic Energy Sciences Advisory
Committee August 2, 2001 Paul W. Lisowski Los
Alamos National Laboratory LANSCE Division
Director
2
Outline
  • Realizing the full potential of LANSCE
  • Progress to Date
  • 2001 Run Cycle
  • Target Moderator
  • Summary

3
LANSCE is a Unique Multidisciplinary Science
Facility
800 MeV Proton Linac
Isotope Production Facility (Under Construction)
Weapons Neutron Research
Manual Lujan Jr. Neutron Scattering Center
Proton Radiography
4
LANL Goal Deliver Neutrons and Protons Safely
and Reliably for All LANSCE Users
  • Appoint new LANSCE management team
  • Engage other scientific user facilities to
    benchmark and improve LANSCE performance
  • Develop and implement effective governance model
    involving NNSA, SC, NE, LANL and user communities
  • Ensure appropriate support and oversight,
    informed by independent review of bottom-up cost
    estimate
  • Pause BES development of new Lujan instruments to
    focus on operation of the user program
  • Increase LDRD investment in Lujan science program
  • Maintain strong communication with LANSCE User
    Group (LUG)

5
LANL Plan to Realize the Full Potential of LANSCE
(1)
  • Management team in place
  • Benchmarking of scientific user facilities is
    underway
  • Visits to NIST and ANL completed, planning
    underway for fall trips
  • Governance model developed and being implemented
  • Incorporates the ideas and expertise of the
    LANSCE User Group and many at DOE, NNSA and other
    facilities
  • Held initial meeting in April, 2001
  • Maureen McCarthy NNSA Chair, Pat Dehmer DOE-SC,
    Dave Crandall NNSA-DP, Owen Lowe DOE-NE and
    others attended
  • MOA ready for signature
  • Next meeting planned for September, 2001
  • LANSCE User Facility Cost Estimate review (K.
    Berkner, Chair)
  • Underway at Los Alamos

6
LANL Plan to Realize the Full Potential of LANSCE
(2)
  • Pause in BES Spectrometer Development
  • Funding reprogrammed
  • LANSCE science planning
  • Neutron scattering plan based on user input
    completed by Alan Hurd and others
  • Will be incorporated into overall LANSCE
    Strategic Plan with a first draft in September
  • A LANSCE planning workshop involving the broader
    user community is planned for the next LUG
    meeting, August 12 -14, 2001
  • Strategic Plan will be integrated into NNSA/DP
    5-year planning process
  • Additional LDRD investments in Lujan science
    secured for FY2001

7
DOE has Clarified its Governance of LANSCE
  • Assign Defense Programs as the Organizational
    entity with corporate responsibility and
    accountability for strategic integration of all
    three program offices using LANSCE. This
    approach applies both to the short-term objective
    of facilitating IPF construction and the
    long-term goal of reliable accelerator
    operations.from Memorandum from the Deputy
    Secretary of Energy to General Gordon 12/21/2000
  • Single Point Accountability
  • Single Line of Authority
  • Participation of all stakeholders
  • Authority and Responsibility chain includes
    accountability for those controlling the
    resources

DOE
NNSA/DP
NE
SC
NNSA/DP LANSCE Program Manager

LANL
LANSCE
8
Highest Priority Establish a Long-Term
Sustainable Program Serving All Users Safely,
Reliably Predictably
  • Completed outage 20 days ahead of schedule and
    started user program on schedule July 1, 2001
  • Proposals arrived March 12, 2001 for PAC review
  • Proposals evaluated and instrument time scheduled
  • User Facility Production started July 1, 2001
  • User Program will run through December 23, 2001-
    a total of 2544 hours for Lujan Center
  • Run safely, reliably and predictably for all
    users
  • Implement the governance, management, and science
    plans to realize the full potential of LANSCE and
    the Lujan Center

9
All Major Accelerator Outage Tasks Completed on
Schedule
  • Interim Safety Assessment Document (ISAD)
  • MPF-963 Cooling Tower tie-in
  • Nuclear Facility Maintenance
  • IPF Shield Wall Construction
  • IPF Transition Region Modifications
  • Accelerator Maintenance
  • Facility Maintenance
  • Accelerator Start-up

LANSCE Web Page Outage Display
10
Lujan Center Received 152 Proposals for the 2001
Run Cycle
Number of Proposals Received152 Defense Non-Def
ense FDS 0 10 HIPD 4 34 LQD 6 18 NPD 10 2
7 SCD 0 6 SPEAR 5 28 FP11A 0 3 FP14 1 1 FP
5 2 4 Average Oversubscription rate is 21

106 Days Available
In User Program
Not supported in user program for FY01 will
run if support becomes available Nuclear
physics beam lines located in Lujan Center, FP11A
shared with neutron scattering program
11
LANSCE has Implemented a Standard 28-Day
Operating Cycle with Contingency
LANSCE Operating Schedule for CY2001
May
June
July
August
September
October
November
December
Turn-on
Contingency For Turn-on
1L Maintenance
Lujan/ WNR User Program
Prad, NRS, .
Reserve or Contingency
2002 Outage
  • Incorporates formal change control and
    contingency allocation process

12
We have Identified Funding, Developed a Detailed
Project Schedule, and Plan to Install a
Switchyard Kicker in 2003
  • Five-fold increase in beam available to Proton
    Radiography program
  • 20 more beam time scheduled for Lujan Center
    and WNR
  • Makes an Ultra-Cold Neutron program possible
  • Make changeovers between Line X and Line D
    operations more efficient, increasing beam
    availability
  • Stable accelerator operation at fixed beam
    intensity yields more reliable beam delivery for
    all programs

13
We are Greatly Improving our Scattering
Instrument Suite with New Construction and
Upgrades
  • HIPPO Received first beam on sample, July 7,
    2001
  • SMARTS Turntable, slits, and controls readied,
    July 2001
  • First beam expected August 2001
  • PROTEIN First beam on sample December 2000
  • Alignment improvement studies underway
  • New BNL detector received July 27, 2001
  • NPD Upgrade Design for new detector banks for
    pair-density functions
  • underway with
    University of Pennsylvania
  • PHAROS New wide-angle detector bank installed
  • New data acquisition electronics installed
  • Chopper reworked and balanced
  • ASTERIX First beam December 2000
  • First data June 2001
  • IN500 Thimble installation April 2000
  • Ballistic guide design completed and procurement
    order
  • placed

14
Beam Delivery to the User Program has been
Reliable thus far, but Current is Limited by the
Target Moderator System
93.2
75 mA
56 mA
7/1
7/22
15
We have Funding and are Developing a Plan and
Schedule to Replace the Lujan Target Moderator if
Necessary
  • Target Moderator Reflector system is experiencing
    overheating of the lower lead reflector
  • Potential problem with lead reflector cooling
  • Thermal cycling may have separated cooling coils
    from lead
  • Analysis to determine maximum current without
    melting lead underway
  • The current Target will last through this run
    cycle
  • Operating conservatively until we understand the
    problem
  • 60 mA limit at present gives stable heat load
  • Attempting to develop a work-around to allow
    higher current
  • Funding and parts to assemble the spare are in
    hand assembly planning has begun
  • Develop an engineering solution to the lead
    heating problem
  • Redesign and fabricate lower reflector
  • Develop a plan for possible installation during
    the next outage
  • Will install during the next outage if no
    solution is found

16
Some of the Exciting Experiments that are Planned
and Underway at the Lujan Center
Tony Cheetham, UCSB Tonya Kuhl, UCSD Anne
Mayes, MIT Takeshi Egami, UPenn Ersan
Ustundag, CalTech Wayne Goodman, Texas
AM Dave Mao, Carnegie Institute
  • HIPD In-Situ Synthesis of Bismuth Transition
    Metal Perovskites, Structure and Magnetic
    Ordering
  • SPEAR Molecular Density and Orientation in
    Confined Polymer Layers Under Static and Dynamic
    (flow) Conditions
  • LQD Chain Statistics of Polystyrene Dissolved in
    Lower Molecular Weight Polystyrene
  • NPD Local Structure of Superconducting Cuprates
    with Stripes
  • FP5 Solid State Reaction Studies
  • FDS Identification of CHx Intermediates Formed
    Over Surface During Methane Decomposition Over
    Supported Catalysts
  • SCD In-situ Neutron Single-crystal Diffraction
    Study on Ice II, III, V, VI and IX at High
    Pressure

17
Summary
  • DOE, NNSA, the LANL Director, and LANL Senior
    Management have made a commitment for success at
    LANSCE
  • We are responding to the BESAC recommendations
    for governance
  • LANSCE Division completed the outage and started
    up 20 days earlier than scheduled
  • User program started as promised on July 1, 2001
  • Operating with high reliability at less than full
    power
  • Funding for kicker magnet in place and project
    underway
  • Funding to build replacement target for Lujan
    Center in place
  • To be installed at next outage
  • We are succeeding at the activities needed to
    operate the LANSCE user facilities safely and
    reliably
Write a Comment
User Comments (0)
About PowerShow.com